This document is a Project Manual for the Security Vestibules for Critzer and Snowville Elementary Schools in Pulaski County, Virginia, prepared for Pulaski County Public Schools. The project consists of the construction of security vestibules at the two elementary schools. The Project Manual includes the advertisement for bids, instructions to bidders, bid forms, bonds, agreements, and specifications. Bids are due by February 20, 2024, and a non-mandatory pre-bid conference will be held on January 30, 2024. The Contract will be awarded to the lowest responsive and responsible bidder. The work is to be substantially completed by August 2, 2024, with final completion within 30 days thereafter.
The Contract Sum is to be stated as a lump sum price for each school, with the total base bid being the sum of the two lump sums. Liquidated damages of $250 per day will be assessed for failure to meet the substantial completion date. The Owner will withhold 5% retainage from each progress payment until final acceptance. MBE/WBE firms are encouraged to submit bids. The Owner reserves the right to reject any and all bids.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 17102_01-18-24_Critzer, Snowville Security Vestibules Bid.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Security Vestibules for Critzer and Snowville Elementary Schools Pulaski County, Virginia
Prepared for
Pulaski County Public Schools
T&L Project No. 17102 Issued for Bids January 18, 2024
PROJECT MANUAL
00 0101
PROJECT MANUAL
Security Vestibules for Critzer and Snowville Elementary Schools
Pulaski County, Virginia
Prepared For
This document and the ideas and designs incorporated herein, as an instrument of professional service, is the property of Thompson & Litton and is not to be used in whole or in part for any other project without the written authorization of Thompson & Litton.
726 Auburn Avenue Radford, Virginia 24141
T&L Project No. 17102 Issued for Bids January 18, 2024
00 0107
Pulaski, Virginia
For
SEALS PAGE
For Architectural & Life Safety Only
00 0110/1
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 0101 Project Title Page 00 0107 Seals Page 00 0110 Table of Contents 00 0115 Drawings Index 00 1113 Advertisement for Bids 00 2113 Instructions to Bidders 00 2515 Pre-Bid Question Form 00 4100 Bid Form 00 4313 Bid Bond (AIA A310) 00 4513 Contractor’s Qualification Statement (AIA A305) 00 4546.13 Workers’ Compensation Certificate (DGS 30-076) 00 4546.16 Certification of Bidder Regarding Debarment 00 5213 Standard Form of Agreement Between Owner & Contractor (AIA A101) 00 5213.10 Insurance and Bonds (AIA A101 - Exhibit A) 00 5433 Request for Electronic Files Form 00 6113 Performance Bond & Payment Bond (AIA A312)* 00 6275 Payment Application Checklist 00 6276 Application & Certificate for Payment (AIA G702)* 00 6276.10 Continuation Sheet (AIA G703)* 00 6313 Request for Information (RFI) Form 00 6325 Request for Substitution Form 00 6333 Architect’s Supplemental Instructions (AIA G710)* 00 6346 Construction Change Directive (AIA G714)* 00 6353 Proposal Request (AIA G709)* 00 6363 Change Order (AIA G701)* 00 6516 Certificate of Substantial Completion (AIA G704)* 00 6519.13 Contractor’s Affidavit of Payment of Debts & Claims (AIA G706)* 00 6519.16 Contractor’s Affidavit of Release of Liens (AIA G706A)* 00 6519.19 Consent of Surety Company to Final Payment (AIA G707)* 00 7210 General Conditions of the Contract for Construction (AIA A201) 00 7310 Supplementary General Conditions
* Asterisks indicate references made to AIA (American Institute of Architects) documents - latest edition, which are hereby made a part of the Contract Documents. All provisions and requirements contained in reference, after being duly executed, shall be considered as part of the Contract Documents, as if bound herein. Copies of the referenced documents are available for review at the office of the Architect. Contractors shall purchase copies from the American Institute of Architects. The original document shall be provided by the Contractor and will be required for the execution of the “Contract”.
TABLE OF CONTENTS (CONTINUED)
00 0110/2
SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 1000 Summary
01 2000 Price and Payment Procedures
01 3000 Administrative Requirements
01 4000 Quality Requirements
01 5000 Temporary Facilities and Controls
01 6000 Product Requirements
01 7000 Execution and Closeout Requirements
01 7800 Closeout Submittals
DIVISION 02 - EXISTING CONDITIONS
02 4119 Selective Structure Demolition
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 4100 Architectural Wood Casework
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 9200 Joint Sealants
DIVISION 08 - OPENINGS
08 1113 Hollow Metal Doors And Frames
08 1213 Hollow Metal Frames
08 1416 Flush Wood Doors
TABLE OF CONTENTS (CONTINUED)
00 0110/3
08 4313 Aluminum-Framed Storefronts
08 7100 Door Hardware
08 8000 Glazing
08 8723 Safety And Security Films
08 8813 Fire-Rated Glazing
DIVISION 09 - FINISHES
09 2116 Gypsum Board Assemblies
09 5100 Acoustical Ceilings
09 9123 Interior Painting
DIVISION 10 - SPECIALTIES
10 2641 Ballistics Resistant Panels
DIVISION 12 - FURNISHINGS
12 3600 Countertops
Pulaski, Virginia
For
DRAWINGS INDEX
00 0115/1
DRAWING TITLE: DRAWING NUMBER:
GENERAL
TITLE SHEET G001
PROJECT INFORMATION AND DATA G002
ARCHITECTURAL
CRITZER ELEMENTARY SCHOOL DEMOLITION & NEW WORK PLANS A101
CRITZER ELEMENTRY SCHOOL REFLECTED CEILING PLAN & INTERIOR ELEVATIONS A102
SNOWVILLE ELEMENTARY SCHOOL DEMOLITION & NEW WORK PLANS A103
SNOWVILLE ELEMENTARY REFLECTED CEILING PLAN & INTERIOR ELEVATIONS A104
DOOR AND FINISH SCHEDULES, NOTES, AND LEGEND A601
STOREFRONT ELEVATIONS A602
ELECTRICAL
ELECTRICAL LEGEND, GENERAL NOTES, ABBREVIATIONS AND DETAIL E001
CRITZER ELEMENTARY SCHOOL DEMOLITION & NEW WORK PLANS E101
CRITZER ELEMENTRY SCHOOL LIGHTING PLAN E102
SNOWVILLE ELEMENTARY SCHOOL DEMOLITION & NEW WORK PLANS E103
SNOWVILLE ELEMENTARY SCHOOL LIGHTING PLAN E104
00 1113/1
ADVERTISEMENT FOR BIDS
202 North Washington Avenue Pulaski, Virginia 24301
Separate sealed Bids for the Security Vestibules for Critzer and Snowville Elementary Schools for Pulaski County Public Schools which consists of the Construction of security vestibules as Critzer and Snowville Elementary Schools, will be received by Jess Shull/Morgan Sklar at the office of Jess Shull/Morgan Sklar, 202 N. Washington Street, Pulaski, Virginia 24021, 3rd Floor, until 2:00 P.M., local prevailing time, on February 20, 2024, and then at said office publicly opened and read aloud.
The Contract Documents may be examined at the 202 N. Washington Street, Pulaski, Virginia 24021, 3rd Floor; Thompson & Litton, 726 Auburn Avenue, Radford, VA; and online at TRASCO (http://www.trascoplanroom.com).
Copies of the Contract Documents (electronic and/or hard copy) are available for purchase through TRASCO at http://www.trascoplanroom.com.
A non-mandatory Pre-Bid Conference will be held on Tuesday, January 30, 2024 at 10:00 A.M. All interested parties are requested to meet the Architect at Critzer Elementary School, 100 Critzer Drive, Pulaski, VA, then travel to Snowville Elementary School, 4858 Lead Mine Road, Hiwasee, VA. at that time.
Withdrawal of bids shall be according to procedure (i) of the Virginia Public Procurement Act and to the Code of Virginia (§ 2.2-4330).
Bids must be accompanied by Bid security as specified in the Instructions to Bidders.
Each Bidder must be licensed as a Class A contractor in the State of Virginia; Bidders are instructed to review the Code of Virginia, Title 54.1, Chapter 11, prior to bidding.
The Owner does not discriminate against faith-based organizations in accordance with the Code of Virginia, § 2.2-4343.1.
MBE/WBE firms are encouraged to submit Bids.
The Contract(s) shall be awarded to the lowest responsive and responsible Bidder(s).
The Owner reserves the right to reject any and all Bids if it appears in its best interest to do so.
Jess Shull January 18, 2024 Pulaski County Public Schools Date By http://www.trascoplanroom.com/ http://www.trascoplanroom.com/
00 2113/1
INSTRUCTIONS TO BIDDERS
1. Defined Terms
1.1 Terms used in these Instructions to Bidders which are defined in the General Conditions of the
Contract for Construction (AIA A201-2017) have the meanings assigned to them in the General
Conditions. Additional terms used in these Instructions to Bidders have the meaning indicated below:
A. The term "Bidder" means one who submits a Bid directly to Owner, as distinct from a sub-bidder, who submits a Bid to a Bidder.
B. The term "Successful Bidder" means the qualified, responsible, and responsive Bidder to whom Owner (on the basis of Owner's evaluation hereinafter provided) makes an award.
C. The term "Bidding Documents" includes the Advertisement or Invitation for Bids, Instructions to Bidders, the Bid Form, sample forms, and the proposed Contract
Documents (including all Addenda issued prior to receipt of Bids).
D. The term “Days” means calendar days.
1.2 Terms as used in the Code of Virginia, § 2.2-4301.
2. Copies of Bidding Documents
2.1 Complete sets of the Bidding Documents are available as stated in the Advertisement or
Invitation for Bids.
2.2 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor
Architect assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.3 Owner and Architect, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use.
3. Qualifications of Bidders
3.1 Each Bidder shall submit to the Owner, through the Architect, on the form entitled "Contractor's
Qualification Statement" a statement of its qualifications, its experience record in constructing the types of improvements embraced in the Contract, and its organization and equipment available for the Work contemplated. The Owner shall have the right to take such steps as it deems necessary to determine the ability of the Bidder to perform its obligation under the
00 2113/2
Contract, and the Bidder shall furnish the Owner all such information and data indicated on the form. The right is reserved to reject any Bid where an investigation of the available evidence or information does not satisfy the Owner that the Bidder is qualified to properly carry out the terms of the Contract.
4. Examination of Contract Documents and Site
4.1 Before submitting a Bid, it is each Bidder's responsibility to (a) examine the Contract Documents thoroughly; (b) visit the site to become familiar with local conditions that may in any manner affect cost, progress or performance of the Work; (c) consider Federal, State, and local laws;
ordinances; and rules and regulations that may in any manner affect cost, progress or performance of the Work; (d) study and carefully correlate Bidders' observations with the
Contract Documents; and (e) notify Architect of all conflicts, errors or discrepancies in the
Contract Documents.
4.2 The submission of a Bid will constitute an incontrovertible representation by Bidder that it has complied with every requirement of this Article 4; that without exception, the Bid is premised upon performing and furnishing the Work required by the Contract Documents and such means, methods, techniques, sequences, or procedures of construction as may be indicated in or required by the Contract Documents; and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
5. Interpretations and Addenda
5.1 All questions about the meaning or intent of the Contract Documents are to be submitted to the
Architect on the Pre-Bid Question Form provided herein. Interpretations and/or clarifications considered necessary by Architect in response to such questions will be issued by Addenda and delivered to all parties recorded by Architect as having received the Bidding Documents.
Questions received less than ten (10) days prior to the date for opening of Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
5.2 Addenda may also be issued to modify the Bidding Documents as deemed advisable by Owner or Architect.
6. Bid Security
6.1 Bid Security shall be made payable to Owner in an amount of five percent (5%) of the Bidder's maximum Bid price and in the form of a certified check or a Bid Bond (on form provided or form supplied by Bidder's Surety).
6.2 The Bid Security of the Successful Bidder will be retained until such Bidder has executed the
Agreement and furnished the required Contract Security, whereupon it will be returned. If the successful Bidder fails to execute and deliver the Agreement and furnish the required Contract
00 2113/3
Security within fifteen (15) days of the Notice of Award, Owner may annul the Notice of Award and the Bid Security of that Bidder will be forfeited. The Bid Security of other Bidders whom
Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of the seventh day after the "effective date of the Agreement" or the thirty-first day after the Bid opening, whereupon Bid Security furnished by such Bidders will be returned.
Bid Security with Bids which are not competitive will be returned within seven (7) days after the
Bid opening.
7. Contract Time(s)
7.1 The number of calendar days within which, or the date by which, the Work is to be substantially completed and ready for final payment. Contract Time(s) are set forth in the Bid Form.
8. Substitute or "Or Equal" Items
8.1 The Contract, if awarded, will be on the basis of material and equipment described in the
Drawings or specified in the Specifications without consideration of possible substitute or "or equal" items. Whenever it is indicated in the Drawings or specified in the Specifications that a substitute or "or equal" item of material or equipment may be furnished or used by Contractor if acceptable to Architect, application for such acceptance will not be considered by Architect until after the "effective date of the Agreement".
9. Subcontractors, Etc.
9.1 In advance of the Notice of Award, the apparent Successful Bidder will, within ten (10) days after the day of the Bid opening, submit to Owner through Architect a list of all Subcontractors and other persons and organizations (including those who are to furnish the principal items of material and equipment) proposed for those portions of the Work as to which such identification is so required. The Architect may additionally request such list be accompanied by an experience statement with pertinent information as to similar projects and other evidence of qualification for each such Subcontractor, person and organization, if requested by Owner. If
Owner or Architect, after due investigation, has reasonable objection to any proposed
Subcontractor, other person or organization, either may, before giving the Notice of Award, request the apparent Successful Bidder to submit an acceptable substitute without an increase in Bid price. If the apparent Successful Bidder declines to make any such substitution, the contract shall not be awarded to such Bidder. Any Subcontractor, other person or organization so listed and to whom Owner or Architect does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Architect.
9.2 No Contractor shall be required to employ any Subcontractor, other person, or organization against whom it has reasonable objection.
00 2113/4
9.3 In accordance with Code of Virginia, § 2.2-4332, all Subcontractors must provide evidence of
Workers' Compensation Insurance prior to award of contract by completing the Workers'
Compensation Certificate of Coverage.
9.4 In accordance with Code of Virginia, Title 54.1, Chapter 11, all Subcontractors must be registered either as a Class A or Class B Contractor with the Virginia Board for Contractors.
10. Bid Form
10.1 The Bid Form is provided herein. One (1) separate unbound copy of the Bid Form to be completed and submitted with the Bid Security and other documents is additionally provided
(hard sets only).
10.2 All blanks on the Bid Form must be completed in ink or by typewriter. The Bid price of each item on the form and the Total Bid Price must be stated in both words and numerals; in case of a conflict, words will take precedence.
10.3 Bids by corporations must be executed in the corporate name by the President or a Vice
President (or other corporate officer accompanied by evidence of authority to sign) and the corporate seal must be affixed and attested by the Secretary or an Assistant Secretary. The corporate address and state of incorporation shall be shown below the signature.
10.4 Bids by Partnership must be executed in the partnership name and signed by a partner whose title must appear under the signature and the official address of the Partnership must be shown below the signature.
10.5 A Bid by a Limited Liability Company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.
10.6 All names must be typed or printed below the signature.
10.7 The Bid shall contain an acknowledgment of receipt of all Addenda (the numbers of which shall be filled in on the Bid Form).
10.8 For the purposes of directing telecommunications regarding the Bid, the postal address, email address, and telephone number must be shown.
11. Submission of Bids
11.1 Prior to submitting a Bid, a nonresident Bidder must appoint the Director of the Virginia
Department of Professional and Occupational Regulation as the Bidder’s statutory agent for service of process pursuant to Code of Virginia, Section 54.1-1113.
11.2 Bids shall be submitted at the time and place indicated in the Advertisement or Invitation for
Bids and shall be included in an opaque sealed envelope, marked with the Project title and name and address of the Bidder, Bidder's applicable State Contractor License Number and
00 2113/5
Classification/Specialty Code Name, and accompanied by the other required documents. If the
Bid is sent through the mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope with the notation "BID ENCLOSED" on the face thereof.
11.3 Bids shall be addressed to the Owner as indicated on the Bid Form. No Bid submitted by fax or email transmission shall be allowed.
12. Modification and Withdrawal of Bids
12.1 Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and as allowed and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids.
12.2 If, in accordance with Code of Virginia, § 2.2-4330, B.1, within two (2) business days after the Bid date, any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid and the Bid security will be returned. Thereafter, that Bidder will be disqualified from further bidding on the Work.
12.3 No Bidder who is permitted to withdraw a Bid shall, for compensation, supply any material or labor to or perform any subcontract or other work agreement for the person or firm to whom the Contract is awarded or otherwise benefit, directly or indirectly, from the performance of the
Project for which the withdrawn Bid was submitted.
12.4 No Bid may be withdrawn due to error when the result would be the awarding of the Contract on another Bid of the same Bidder or of another Bidder in which the ownership of the withdrawing Bidder is more than five percent (5%).
12.5 If a Bid is withdrawn due to error, the lowest remaining Bid shall be deemed to be the low Bid.
13. Opening of Bids
13.1 Bids will be opened and (unless obviously nonresponsive) read aloud publicly. An abstract of the amounts of the Base Bids and major alternates (if any) will be made available to Bidders after the opening of Bids. If, however, the Owner chooses not to accept any of the Bids and re-advertises the Contract or re-invites Bidders, no abstract will be made, and Bids submitted will not be available for examination.
14. Bids to Remain Open
14.1 All Bids shall remain open for sixty (60) days after the day of the Bid opening, but Owner may, in its sole discretion, release any Bid prior to that date.
00 2113/6
15. Award of Contract
15.1 Owner reserves the right to reject any and all Bids; to waive any and all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the successful
Bidder, and the right to disregard all nonconforming, nonresponsive, or conditional Bids. Also, Owner reserves the right to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive, Bidder is unqualified, of doubtful financial ability, or fails to meet any other pertinent standard or criteria established by Owner.
15.2 In evaluating Bids, Owner will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
15.3 Owner may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of
Subcontractors, Suppliers, and other persons and organizations must be submitted as provided in the Supplementary Conditions. Owner may also consider the operating costs, maintenance requirements, performance data, and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the
Notice of Award.
15.4 Owner may conduct such investigations as it deems necessary to assist in the evaluation of any
Bid and to establish the responsibility, qualifications, and financial ability of the Bidders, proposed Subcontractors, Suppliers, and other persons and organizations to perform and furnish the Work in accordance with the Contract Documents to Owner's satisfaction within the prescribed time.
15.5 If the Contract is to be awarded, such award shall be to the responsible Bidder submitting the lowest responsive Bid. Evaluation shall be made on the basis of the Base Bid; Alternates, if any, will be considered by the Owner following Contract award.
15.6 If the Contract is to be awarded, Owner will give the Successful Bidder Notice of Award within sixty (60) days after the day of the Bid opening.
15.7 Unless cancelled or rejected, the responsive Bid from the successful Bidder shall be accepted as submitted, except that if the Bid from the successful Bidder exceeds available funds, the Owner or designated official may negotiate with the successful Bidder to obtain a contract within available funds. Negotiations will be conducted in accordance with the following procedures:
1. Proposals and Counter Proposals shall be set forth in writing through the Architect.
2. Time limit for negotiations shall be thirty (30) days from the Bid date.
00 2113/7
3. The Owner has the right to reject any or all proposals or counter proposals of the
Contractor.
15.8 In accordance with Code of Virginia, § 2.2-4332, all Bidders must provide evidence of Workers
Compensation Insurance by submitting a Workers’ Compensation Certificate of Coverage with each Bid.
16. Contract Security
16.1 The General Conditions (Articles 11.1.2 and 11.1.3) and the Supplementary Conditions (SC-11) set forth Owner's requirements as to Performance and other Bonds. When the Successful
Bidder delivers the executed Agreement to Owner, it shall be accompanied by the required
Contract Security.
17. Signing of Agreement
17.1 When Owner gives a Notice of Award to the Successful Bidder, it will be accompanied by at least three (3) unsigned counterparts of the Agreement and all other Contract Documents. Within fifteen (15) days thereafter, the Successful Bidder shall sign and deliver at least three (3) counterparts of the Agreement to Owner with all other Contract Documents attached. Within ten (10) days thereafter, Owner will deliver all fully signed counterparts to Architect who will distribute one each of the executed contracts to the Owner, the Contractor, and the Architect.
00 2113/8
18. Sales and Use Taxes
18.1 Applicable State Sales and Use Taxes on materials and equipment to be incorporated in the
Work shall be included in the Contract price.
19. Retainage
19.1 In accordance with Code of Virginia, § 2.2-4333, a sum equal to five percent (5%) of the
Contractor's pay requests shall be held as retainage throughout the entire project until final acceptance by the Owner.
20. Liquidated Damages
20.1 Owner and Contractor recognize that time is of the essence with regard to this Agreement and that the Owner will suffer financial loss and inconvenience if Work is not completed within the designated time. They also recognize the delays, expense and difficulties involved in proving in a legal proceeding the actual loss suffered by Owner if the Work is not completed on time.
Accordingly, instead of requiring any proof, Owner and Contractor agree that the Contractor shall pay the Owner liquidated damages as outlined in the Bid Form for each calendar day that expires after the time specified for project completion.
21. Anti-Discrimination
21.1 In accordance with Code of Virginia, § 2.2-4311, during the performance of this Contract, the
Contractor agrees as follows:
A. The Contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex or national origin, age, disability, or other basis prohibited by state law relating to discrimination in employment, except where there is a bona fide occupational qualification reasonably necessary to the normal operation of the
Contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.
B. The Contractor, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, will state that such Contractor is an equal opportunity employer.
C. Notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this section.
21.2 The Contractor will include the provisions of the foregoing paragraphs A., B., and C., in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor.
00 2113/9
22. Special Legal Requirements
22.1 Bidders and Contractors performing Work under this Advertisement are bound by the requirements of the Occupational Safety and Health Administration (OSHA) regulations (29 CFR
Part 1910).
22.2 During the performance of this Contract, the Contractor shall not knowingly employ an unauthorized alien as defined in the Federal Immigration Reform and Control Act of 1986, pursuant to the Code of Virginia, § 2.2-4311.1.
22.3 Drug-Free Workplace
A. During the performance of this Contract, the Contractor agrees to (i) provide a drug-free workplace for the Contractor’s employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor.
B. For the purposes of this section, ‘‘drug-free workplace’’ means a site for the performance of work done in connection with a specific contract awarded to a Contractor in accordance with this chapter, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled
00 2515
PRE-BID QUESTION FORM
(Use separate Form for each question submitted.)
Date:
Project Name: Security Vestibules for Critzer and Snowville Elementary Schools
T&L Project No.: 17102
The following question concerns Drawing Sheet (number) :
The following question concerns Specification Section (number) , page ______, paragraph
Refer to “Instructions to Bidders”, Part 5 - “Interpretations and Addenda”.
NOTE: QUESTIONS MAY NOT BE CONSIDERED IF RECEIVED WITHIN TEN (10) CALENDAR DAYS OF THE
BID DATE. All responses to questions will be made by Addendum.
Question submitted by:
Name Organization:
Telephone:
Bidders shall submit form to: Thompson & Litton, Inc
Email address: prebid@T-L.com or FAX No.: (540) 633-1896
00 4100/1
BID FORM
PROJECT IDENTIFICATION: Security Vestibules for Critzer and Snowville
Elementary Schools
CONTRACT IDENTIFICATION NO: T&L Project No. 17102
THIS BID IS SUBMITTED TO: Pulaski County Public Schools 202 North Washington Avenue Pulaski, Virginia 24301
1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Contract Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.
2. Bidder accepts all of the terms and conditions of the Advertisement and Instructions to Bidders, including without limitation those dealing with the disposition of Bid Security. This Bid will remain subject to acceptance for sixty (60) days after the day of Bid Opening. Bidder will sign and submit the Agreement with the Bonds and other documents required by the Bidding Requirements within the timeframe presented in the Instructions to Bidders.
3. In submitting this Bid, Bidder represents, as more fully set forth in the Agreement, that:
(A) Bidder has examined copies of all Bidding Documents and of the following Addenda
(receipt of all which is hereby acknowledged):
Number Date
(B) Bidder has familiarized itself with the nature and extent of the Contract Documents, Work, site, locality, and all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance, or furnishing of the Work.
(C) Bidder has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests, and studies which pertain to the subsurface or physical conditions at the site or otherwise may affect the cost, progress, performance, or furnishing of the Work as Bidder considers
00 4100/2 necessary for the performance or furnishing of the Work at the Contract time and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of Paragraph 3.2 of the General Conditions; and no additional examinations, investigations, explorations, tests, reports, or similar information or data are or will be required by Bidder for such purposes.
(D) Bidder has reviewed and checked all information and data shown or indicated on the
Contract Documents with respect to existing utilities at or contiguous to the site and assumes responsibility for the accurate location of said utilities. No additional examinations, investigations, explorations, tests, reports or similar information or data in respect of said utilities are or will be required by Bidder in order to perform and furnish the Work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of Paragraph 3.2 of the General Conditions.
(E) Bidder has correlated the results of all such observations, examinations, investigations, explorations, tests, reports, and studies with the terms and conditions of the Contract
(F) Bidder has given Architect written notice of all conflicts, errors, or discrepancies that it has discovered in the Contract Documents and the written resolution thereof by Architect is acceptable to Bidder.
(G) This Bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm, or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any person, firm, or corporation to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner.
4. Bidder will complete the Work for the following price:
PART A – LUMP SUM PRICE FOR SNOWVILLE ELEMENTARY SCHOOL IN ACCORDANCE WITH DRAWINGS AND
SPECIFICATIONS.
Dollars ($ )
PART B - LUMP SUM PRICE FOR CRITZER ELEMENTARY SCHOOL IN
ACCORDANCE WITH DRAWINGS AND SPECIFICATIONS
00 4100/3
TOTAL BASE BID (PART A + PART B)
NOTE: The Contract, if awarded, will be based on the Total Base Bid.
5. Bidder agrees that the Work will be substantially completed by August 2, 2024, and Final Completion shall be achieved within thirty (30) consecutive calendar days after Substantial Completion.
6. In the event that the project does not reach Substantial Completion within the time specified in Paragraph 5 above, Owner and Contractor recognize that time is of the essence with regard to this Agreement and that the Owner will suffer financial loss and inconvenience if Work is not completed within the designated time. They also recognize the delays, expense and difficulties involved in proving in a legal proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty), the Contractor shall pay the Owner two hundred and fifty dollars ($250.00) for each calendar day that expires after the time specified for project completion.
7. The following documents are attached to and made a condition of this Bid:
(A) Required Bid Security in the form of .
(B) Required Contractor's Qualification Statement with supporting data.
(C) Certification of Bidder Regarding Debarment.
(D) Workers’ Compensation Certificate of Coverage.
8. Communications concerning this Bid shall be addressed to the address of Bidder indicated below.
The following address:
9. The terms used in this Bid which are defined in the General Conditions of the Construction Contract included as part of the Contract Documents have the meanings assigned to them in the General Conditions.
SUBMITTED on __________________, 20___.
00 4100/4
BIDDER hereby submits this Bid as set forth above:
Bidder:
(typed or printed name of organization)
By:
(authorized signature)
Name:
(typed or printed)
Title:
Attest:
(individual’s signature)
Address for giving notices:
Bidder’s Contact:
(typed or printed)
Phone:
Email:
Address:
Bidder’s Contractor License No.: (if applicable)
AIA
Document A310TM – 2010
Bid Bond
AIA Document A310™ – 2010. Copyright © 1963, 1970 and 2010 by The American Institute of Architects. All rights reserved. WARNING: This AIA®
Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 08:25:26 on 02/12/2016 under Order No.9425570011_1 which expires on 11/25/2016, and is not for resale.
User Notes: (1666476906)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion.
The author may also have revised the text of the original AIA standard form.
An Additions and Deletions
Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences.
Consultation with an attorney is encouraged with respect to its completion or modification.
Any singular reference to
Contractor, Surety, Owner or other party shall be considered plural where applicable.
ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
CONTRACTOR:
(Name, legal status and address)
SURETY:
(Name, legal status and principal place of business)
OWNER:
(Name, legal status and address)
BOND AMOUNT: $ « »
PROJECT:
(Name, location or address, and Project number, if any)
«Stacy's Samples»
The Contractor and Surety are bound to the Owner in the amount set forth above, for the payment of which the Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, as provided herein. The conditions of this Bond are such that if the Owner accepts the bid of the Contractor within the time specified in the bid documents, or within such time period as may be agreed to by the Owner and Contractor, and the Contractor either (1) enters into a contract with the Owner in accordance with the terms of such bid, and gives such bond or bonds as may be specified in the bidding or Contract Documents, with a surety admitted in the jurisdiction of the Project and otherwise acceptable to the Owner, for the faithful performance of such Contract and for the prompt payment of labor and material furnished in the prosecution thereof; or (2) pays to the Owner the difference, not to exceed the amount of this Bond, between the amount specified in said bid and such larger amount for which the Owner may in good faith contract with another party to perform the work covered by said bid, then this obligation shall be null and void, otherwise to remain in full force and effect. The Surety hereby waives any notice of an agreement between the
Owner and Contractor to extend the time in which the Owner may accept the bid. Waiver of notice by the Surety shall not apply to any extension exceeding sixty (60) days in the aggregate beyond the time for acceptance of bids specified in the bid documents, and the
Owner and Contractor shall obtain the Surety’s consent for an extension beyond sixty
(60) days.
If this Bond is issued in connection with a subcontractor’s bid to a Contractor, the term
Contractor in this Bond shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor.
When this Bond has been furnished to comply with a statutory or other legal requirement in the location of the Project, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond.
00 4313
AIA Document A310™ – 2010. Copyright © 1963, 1970 and 2010 by The American Institute of Architects. All rights reserved. WARNING: This AIA®
Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 08:25:26 on 02/12/2016 under Order No.9425570011_1 which expires on 11/25/2016, and is not for resale.
User Notes: (1666476906)
Signed and sealed this « » day of « » , « »
(Contractor as Principal) (Seal)
(Witness) (Title)
(Surety) (Seal)
(Witness) (Title)
00 4313
Document A305TM – 1986
Contractor's Qualification Statement
AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING:
This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®
Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 08:27:13 on 02/12/2016 under Order No.9425570011_1 which expires on 11/25/2016, and is not for resale.
User Notes: (1179398967)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion.
The author may also have revised the text of the original AIA standard form.
An Additions and Deletions
Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences.
Consultation with an attorney is encouraged with respect to its completion or modification.
This form is approved and recommended by the American
Institute of Architects
(AIA) and The Associated
General Contractors of
America (AGC) for use in evaluating the qualifications of contractors. No endorsement of the submitting party or verification of the information is made by AIA or AGC.
ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
The Undersigned certifies under oath that the information provided herein is true and sufficiently complete so as not to be misleading.
SUBMITTED TO: « »
ADDRESS: « »
SUBMITTED BY: « »
NAME: « »
ADDRESS: « »
PRINCIPAL OFFICE: « »
[ « » ] Corporation
[ « » ] Partnership
[ « » ] Individual
[ « » ] Joint Venture
[ « » ] Other « »
NAME OF PROJECT: (if applicable) « »
TYPE OF WORK: (file separate form for each Classification of Work)
[ « » ] General Construction
[ « » ] HVAC
[ « » ] Electrical
[ « » ] Plumbing
[ « » ] Other: (Specify) « »
§ 1 ORGANIZATION
§ 1.1 How many years has your organization been in business as a Contractor? « »
§ 1.2 How many years has your organization been in business under its present business name? « »
§ 1.2.1 Under what other or former names has your organization operated?
§ 1.3 If your organization is a corporation, answer the following:
§ 1.3.1 Date of incorporation: « »
§ 1.3.2 State of incorporation: « »
§ 1.3.3 President's name: « » 00 4513
AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING:
This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®
Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 08:27:13 on 02/12/2016 under Order No.9425570011_1 which expires on 11/25/2016, § 1.3.4 Vice-president's name(s)
§ 1.3.5 Secretary's name: « »
§ 1.3.6 Treasurer's name: « »
§ 1.4 If your organization is a partnership, answer the following:
§ 1.4.1 Date of organization: « »
§ 1.4.2 Type of partnership (if applicable): « »
§ 1.4.3 Name(s) of general partner(s)
§ 1.5 If your organization is individually owned, answer the following:
§ 1.5.1 Date of organization: « »
§ 1.5.2 Name of owner:
§ 1.6 If the form of your organization is other than those listed above, describe it and name the principals:
§ 2 LICENSING
§ 2.1 List jurisdictions and trade categories in which your organization is legally qualified to do business, and indicate registration or license numbers, if applicable.
§ 2.2 List jurisdictions in which your organization's partnership or trade name is filed.
§ 3 EXPERIENCE
§ 3.1 List the categories of work that your organization normally performs with its own forces.
§ 3.2 Claims and Suits. (If the answer to any of the questions below is yes, please attach details.)
§ 3.2.1 Has your organization ever failed to complete any work awarded to it?
§ 3.2.2 Are there any judgments, claims, arbitration proceedings or suits pending or outstanding against your organization or its officers?
§ 3.2.3 Has your organization filed any law suits or requested arbitration with regard to construction contracts within the last five years?
§ 3.3 Within the last five years, has any officer or principal of your organization ever been an officer or principal of another organization when it failed to complete a construction contract? (If the answer is yes, please attach details.)
AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING:
This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®
Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 08:27:13 on 02/12/2016 under Order No.9425570011_1 which expires on 11/25/2016, § 3.4 On a separate sheet, list major construction projects your organization has in progress, giving the name of project, owner, architect, contract amount, percent complete and scheduled completion date.
§ 3.4.1 State total worth of work in progress and under contract:
§ 3.5 On a separate sheet, list the major projects your organization has completed in the past five years, giving the name of project, owner, architect, contract amount, date of completion and percentage of the cost of the work performed with your own forces.
§ 3.5.1 State average annual amount of construction work performed during the past five years:
§ 3.6 On a separate sheet, list the construction experience and present commitments of the key individuals of your organization.
§ 4 REFERENCES
§ 4.1 Trade References:
§ 4.2 Bank References:
§ 4.3 Surety:
§ 4.3.1 Name of bonding company:
§ 4.3.2 Name and address of agent:
§ 5 FINANCING
§ 5.1 Financial Statement.
§ 5.1.1 Attach a financial statement, preferably audited, including your organization's latest balance sheet and income statement showing the following items:
Current Assets (e.g., cash, joint venture accounts, accounts receivable, notes receivable, accrued income, deposits, materials inventory and prepaid expenses);
Net Fixed Assets;
Other Assets;
AIA Document A305™ – 1986. Copyright © 1964, 1969, 1979 and 1986 by The American Institute of Architects. All rights reserved. WARNING:
This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®
Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 08:27:13 on 02/12/2016 under Order No.9425570011_1 which expires on 11/25/2016, Current Liabilities (e.g., accounts payable, notes payable, accrued expenses, provision for income taxes, advances, accrued salaries and accrued payroll taxes);
Other Liabilities (e.g., capital, capital stock, authorized and outstanding shares par values, earned surplus and retained earnings).
§ 5.1.2 Name and address of firm preparing attached financial statement, and date thereof:
§ 5.1.3 Is the attached financial statement for the identical organization named on page one?
§ 5.1.4 If not, explain the relationship and financial responsibility of the organization whose financial statement is provided (e.g., parent-subsidiary).
§ 5.2 Will the organization whose financial statement is attached act as guarantor of the contract for construction?
§ 6 SIGNATURE
§ 6.1 Dated at this « » day of « » « »
Name of Organization: « »
By: « »
Title: « »
§ 6.2
M « » being duly sworn deposes and says that the information provided herein is true and sufficiently complete so as not to be misleading.
Subscribed and sworn before me this « » day of « » « »
Notary Public: « »
My Commission Expires: « »
00 4546.13
DGS-30-076 CO-9a
(Rev. 05/02) Page 1 of 1
COMMONWEALTH OF VIRGINIA
WORKERS' COMPENSATION
Certificate of Coverage
Section 2.2-4332, Code of Virginia, requires construction contractors and subcontractors to obtain and maintain workers' compensation insurance while performing work on behalf of the Commonwealth of Virginia, its departments, institutions, or agencies. This same requirement applies on behalf of local governments.
Evidence of coverage must be provided prior to commencement of Work.
This form must be completed and returned to the organization contracting the Work.
The undersigned organization stipulates that it:
A. has workers' compensation insurance and is in compliance with the Workers' Compensation statutes of the Commonwealth of Virginia. _____ Yes _____ No
Insurance Company ____________________________________
Policy expiration date __________________________________
B. is self insured for workers' compensation. _______ Yes
Title of Construction Contract: ___________________________________________________
Contract Number: ______________________________________________________________
Signed by: _____________________________________
Title:_____________________________________
Firm Name: _____________________________________
Address:_____________________________________
00 4546.16
CERTIFICATION OF BIDDER REGARDING DEBARMENT
BY AGENCY OF THE COMMONWEALTH OF VIRGINIA
This is to certify that this person/firm/corporation has not been barred from bidding on contracts by any agency of The Commonwealth of Virginia, nor is this person/firm/corporation a part of any firm/corporation that has been barred from bidding on contracts by any agency of The Commonwealth of
Virginia.
Name of Official
Title
Firm or Corporation
Date
Document A101® – 2017
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:39:35 ET on 12/05/2023 under Order No.4104240625 which expires on 03/11/2024, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®
Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
User Notes: (1496012872)
ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .