17-SECTION 012200 - UNIT PRICES.pdf

PDF 66 KB Posted

Attached to
CMR Services for Garden City Elementary School Renovation Project
Solicitation number
RFP C27-03 (ESPLOST)
Issued by
Chatham County, Georgia

About this file

This is a Unit Prices specification section for the Garden City Elementary School Renovations project undertaken by Savannah-Chatham County Public Schools in Georgia. The document establishes the framework and procedures for unit pricing that will be used to adjust the Contract Sum if the scope of work or estimated quantities change during construction. The specification outlines 17 distinct unit price line items covering site work, infrastructure, and utility improvements, including unsuitable material removal and replacement, curb and gutter installation, concrete sidewalk work, PVC water mains and sewer systems, fire hydrant assemblies, manholes, grinder pump stations, and forcemain connections. Unit prices are to be submitted as part of the Guaranteed Maximum Price (GMP) bid proposal. The Construction Management at Risk (CMR) services for this project are governed by AIA Document A133-2019 Agreement Between Owner and Construction Manager as Constructor.

All unit prices must include materials, delivery, installation, insurance, applicable taxes, overhead, and profit. The Owner reserves the right to reject the Contractor's measurement of work-in-place involving established unit prices and may engage an independent surveyor at the Owner's expense to verify measurements. Measurement and payment methodologies for individual unit prices are detailed in relevant specification sections referenced throughout the contract documents. The project documents are dated August 7, 2026, with Addendum 1 issued on September 8, 2026, prepared by SSOE, Inc. (Project No. 025-00581-00). This specification section is based on AIA MasterSpec standards and emphasizes the administrative and procedural requirements for establishing and implementing unit prices as change order mechanisms throughout the construction phase.

View the file

Other files

File Type Posted
8-RFP C27-03 - Solicitation Form 1 - Offeror Information Form.pdf PDF
11-RFP C27-03 - Solicitation Form 4 - Lobbying.pdf PDF
5-RFP C27-03 - Phasing Option 4.1 reduced 2026-07-30.pdf PDF
18-SECTION 012100 - ALLOWANCES.pdf PDF
13-RFP C27-03 - Solicitation Form 6 - Performance Bond Form.pdf PDF
23-RFP C27-03 - Solicitation Document - Pages 25-27.pdf PDF
21-RFP C27-03 - Pre-Proposal Register.pdf PDF
19-SECTION 012300 - ALTERNATES.pdf PDF
25-Garden City Elementary BDA Signal Survey 12-1-2025.pdf PDF
9-RFP C27-03 - Solicitation Form 2 - Contractor Affidavit.pdf PDF
3-RFP C27-03 - A201-2017 Sample Contract.pdf PDF
14-RFP C27-03 - Solicitation Form 7 - Payment Bond Form.pdf PDF
7-RFP C27-03 - Solicitation Document.pdf PDF
4-RFP C27-03 - DRAWINGS 100 CD R2 Add-0.pdf PDF
10-RFP C27-03 - Solicitation Form 3 - Debarment.pdf PDF
26-Garden City Elementary Parking Lot Geotech Report - WSP.pdf PDF
20-RFP C27-03 - Addendum 2.pdf PDF
12-RFP C27-03 - Solicitation Form 5 - Bid Security Form.pdf PDF
15-RFP C27-03 - Solicitation Form 8 - GMP Proposal Form.pdf PDF
16-RFP C27-03 - Addendum 1.pdf PDF
1-RFP C27-03 - A133-2019 Sample Contract.pdf PDF
22-RFP C27-03 - Addendum 3.pdf PDF
27-RFP C27-03 - Addendum 4.pdf PDF
24-Garden City Updated Spec Sections Addendum 4.pdf PDF
6-RFP C27-03 - Project Manual 082826.pdf PDF
2-RFP C27-03 - A133-2019 Sample Exhibit A - GMP Amendment.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Garden City ES Renovations Savannah-Chatham County Public Schools

100% Construction Documents R2 August 7, 2026

Addendum 1, September 8, 2026

SSOE, Inc.

Project No. 025-00581-00

012200 - 1

UNIT PRICES

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

SECTION 012200 - UNIT PRICES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

B. Related Requirements:

1. Section 012100 "Allowances" for procedures for using unit prices to adjust quantity allowances.

1.2 DEFINITIONS

A. Unit price is a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1.3 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the Part 3 "Schedule of Unit Prices" Article contain requirements for materials described under each unit price.

PART 2 - PRODUCTS (Not Used)

Garden City ES Renovations Savannah-Chatham County Public Schools

100% Construction Documents R2 August 7, 2026

Addendum 1, September 8, 2026

SSOE, Inc.

Project No. 025-00581-00

012200 - 2

UNIT PRICES

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec based document is protected by U.S.

Copyright Law and International Treaties. A valid, current MasterSpec license is required for editing or use of this document.

PART 3 - EXECUTION

3.1 SCHEDULE OF UNIT PRICES

A. For the scopes of work noted, provide Unit Pricing in the below table.

1. Submit unit pricing for consideration with GMP Bid pricing.

Item Description Unit Unit Price

1 Unsuitable Material – Remove and Replace CY

2 Remove and Replace 18” Standard Curb and

Gutter

LF

3 18” Standard Curb and Gutter LF

4 Remove and Replace 4” Concrete Sidewalk SY

5 4” Concrete Sidewalk SY

6 6” PVC Water Main LF

7 Fire Hydrant Assembly EA

8 8” PVC Gravity Sewer (0 – 6’ deep) LF

9 8” PVC Gravity Sewer (6’ – 8’ deep) LF

10 8” PVC Gravity Sewer (8’ – 10’ deep) LF

11 4'Ø Standard Manhole (0-6 deep) EA

12 4'Ø Standard Manhole (6-8 deep) EA

13 4'Ø Standard Manhole (8-10 deep) EA

500 Gallon, 36” Dia. Grinder Pump Station with 3

Hp Pump

LS

15 1-1/2" HDPE Forcemain LF

16 Connect 8” PVC Gravity Sewer to Existing

Manhole

EA

17 Connect Forcemain to Existing Manhole EA

END OF SECTION 012200