17 - BKTZ122009 SOW Repair Fencing and Cable.docx

DOCX document 23 KB Posted

Attached to
Repair Fencing and Cabling Federal contract opportunity
Solicitation number
W50S97-21-B-0002
Issued by
Department of the Army National Guard

About this file

This statement of work outlines a project to repair fencing and install cabling at Berry Field in Nashville, Tennessee. The project includes reinforcing or replacing over 4,000 linear feet of chain link fencing across 10 sections of the base, installing cable reinforcement, and repairing a fence stream crossing. The performance period is 90 calendar days. The contractor will be responsible for all labor, equipment, materials, and permits to complete the project in accordance with construction plans, specifications, and building codes. The contractor must also report labor hours and adhere to security requirements at the site. The deliverable schedule requires 10% completion upon notice to proceed, 30% after 30 days, 60% after 50 days, 90% after 75 days, and 100% completion including punch list, seeding, and clean up within 90 days. This supports the related federal contract opportunity posted by the Department of the Army National Guard to repair fencing and cabling at the 118th Wing location.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fencing and Cabling, newest first.
File Type Posted
Sign In Roster.pdf PDF
Abstract of offers 21B0002.xls XLS spreadsheet
W50S97-21-B-0002 00002.pdf PDF
BKTZ122009 SOW Repair Fencing and Cable REV 6-8-21.docx DOCX document
BKTZ122009 Drawings Amendment1 REV6-8-21.pdf PDF
W50S97-21-B-0002 SOLIC Amendment 1.pdf PDF
Site Visit Slides 3 June 2021.ppt PPT presentation
W50S97-21-B-0002 SOLIC.pdf PDF
Installation Access Request Form - Wing Form 13.xlsx XLSX spreadsheet
W50S97-21-B-0002 SOLIC.pdf PDF
11 - BKTZ122009 Repair Fencing and Cable Drawings 5-13-21.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

118th WingSECTION 01000
Nashville, TennesseeStatement of Work
BKTZ12200918 February 2020

STATEMENT OF WORK

REPAIR FENCING AND CABLE, BASEWIDE

BERRY FIELD, NASHVILLE, TENNESSEE

1) GENERAL

a) The work covered by this Statement of Work (SOW) consists of furnishing all labor, equipment, and materials to Repair Fencing and Cable, Basewide in accordance with this written statement of work, all construction plans, specifications, and the building code. The work location is the 118th Wing, Nashville, Tennessee. Contractor will be fully responsible for compliance with all base, local, state, and federal laws and regulations that apply to include environmental and occupational safety.

2) PERFORMANCE PERIOD

a) The performance period for this project is 90 calendar days.

3) SCOPE OF WORK

a) Contractor will perform all work as described herein and as shown on drawings for project BKTZ122009, Repair Fencing and Cable, Basewide. Work included in this project consists of 10 areas of repair as listed below.

1. Project Section 1 – Reinforce approximately 437 linear feet of chain link fence with steel cabling.

2. Project Section 2 – Reinforce approximately 319 linear feet of chain link fence with steel cabling.

3. Project Section 3 – Remove and replace approximately 287 linear feet of chain link fence and install cable reinforcement.

4. Project Section 4 – Remove and replace approximately 354 linear feet of chain link fence and install cable reinforcement.

5. Project Section 5 – Repair fence stream crossing with new abutments, fence, grating, and details.

6. Project Section 6 – Remove and replace approximately 517 linear feet of chain link fence and install cable reinforcement.

7. Project Section 7 – Reinforce approximately 450 linear feet of chain link fence with steel cabling.

8. Project Section 8 – Reinforce approximately 486 linear feet of chain link fence with steel cabling.

9. Project Section 9 – Remove and replace approximately 116 linear feet of chain link fence and install cable reinforcement.

10. Project Section 10 – Reinforce approximately 354 linear feet of chain link fence with steel cabling.

b) Contractor Manpower Reporting

1. The contractor will report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Air Force collection site. The contractor is required to completely fill in all required data fields using the following web ad-dress: https://afcmra.hqda.pentagon.mil/

2. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data must be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at http://www.ecmra.mil/.

3. Unit Identification Code (UIC) for the Requiring Activity: L41CFMLV

4. Issuing Office DoDAAC: W912L7

c) Contract Requirements

1. The contractor will adhere to all contract requirements in the solicitation and subsequent contract or delivery order.

2. In addition to those items in the solicitation/contract, the contractor will also be responsible to:

a. Obtain all dig permits, crane permits, or any other permits prior to starting construction.

b. Verify all field and plan measurements and notify the contracting officer’s representative (COR) of any discrepancies.

c. Perform all required construction staking.

d. Prepare project site for construction by placing adequate signage and other devices indicating construction zone for vehicular traffic and pedestrians.

e. Submit all project submittals to the COR for approval prior to the manufacture or placement of any construction materials.

f. Perform all material testing as required by specifications and building code.

g. Perform site finishing and cleanup to include seeding and grass establishment.

h. Remove all work related debris and dispose of it off the base property upon completion of project.

4) REFERENCES

a) In general, all technical specifications are provided within the Construction Documents. In the event any project element is not covered in the specifications provided, the contractor will refer to the Specification Hierarchy for direction related to the element. All work in this project will adhere to the Unified Facilities Criteria.

5) SPECIFICATION HIERARCHY

a) The specification hierarchy is the collection of technical specifications to be used for all projects. The contractor should refer to the specifications provided in the Construction Documents first before moving to the next technical specification listed in the specification hierarchy. The hierarchy is listed in the order of precedence (i.e. “1” supersedes “2”). The hierarchy is as follows:

1. Specifications provided with Construction Documents

a. Technical Specifications

b. Construction Drawings

2. For MATOC contracts, the 118th Base Design Standards

3. Unified Facilities Guide Specifications on www.wbdg.org.

4. Unified Facilities Criteria available on www.wbdg.org.

a. UFC 4-022-03, Security Fences and Gates

6) SECURITY REQUIREMENTS

a) Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor will comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

b) The contractor will be required to secure all areas of perimeter work at the end of each day’s work. At a minimum, fence fabric and 3-strrand barbed wire extensions will be required. Contractor will not remove any more fence fabric sections in a day than can be replaced. All work performed when the existing fence is removed will be done under the watch of the 118th Security Forces Squadron.

7) CONTRACT DELIVERABLE SCHEDULE

Deliverable
Time Period
Deliverable Threshold
10%
Upon Notice to Proceed (NTP)
Submitted bonds and project schedule
30%
30 days after NTP
30% of work completed. All material submittals approved.
60%
50 days after NTP
60% of work completed
90%
75 days after NTP
Pre-final inspection. Work 90% complete.
100%
90 days after NTP
Punch list 100% complete. Finish seeding, strawing and clean area. Project documentation supplied to contracting officer.

'End of Statement of Work’