This is an official advertisement for a state-level construction contract issued by the Texas Department of Transportation (TxDOT) for highway improvement projects in Montague County. The project encompasses multiple highway segments including FM 455, FM 1655, and Greenwood Lane, focusing on hazard elimination and safety improvements. The contract (Control Number 1604-01-007) has a total estimated cost of $10,216,776.75, with a project completion time of 437 working days. Bids will be received and opened on July 2, 2025, at 1:00 PM, with a required bid guaranty of $100,000.00.
The contract includes a Disadvantaged Business Enterprise (DBE) goal of 7.0% and covers multiple highway segments in Montague County and adjacent areas. Interested bidders can obtain project details through the Electronic State Business Daily (ESBD) and Electronic Bidding System, which are considered the official sources of advertisement and bidding information. For project inquiries, potential bidders can contact Colby Shelton at the TxDOT Austin headquarters, with contact information provided in the document. The project is funded through the Surface Transportation Program (STP) and classified as a Hazard Elimination & Safety (HES) initiative.
Text of this file
******* OFFICIAL ADVERTISEMENT *******
*** STATE LET CONSTRUCTION CONTRACT ***
COUNTY: MONTAGUE HIGHWAY: FM 1655, ETC LENGTH: 0 MI
CONTROL NUMBER: 1604-01-007, ETC DBE GOAL: 7.0%
PROJECT NUMBER: STP 2B25(079)HES
TYPE: HAZARD ELIMINATION & SAFETY
TIME FOR COMPLETION: 437 WORKING DAYS GUARANTY: 100,000.00
BIDS RECEIVED UNTIL: 1:00 PM July 2, 2025 EST.COST: 10,216,776.75 BIDS WILL BE OPENED: 1:00 PM July 2, 2025
MAIL OR DELIVER BIDS TO: FOR QUESTIONS CALL:
TEXAS DEPARTMENT OF TRANSPORTATION COLBY SHELTON
2615 WEST HIGHWAY 82
AUSTIN HQ - STASSNEY GAINESVILLE TX 76241
6230 E STASSNEY LN RM MIC3.02 (940) 641-7896
AUSTIN TX 78744-3147
(512) 416-2498
COUNTY CONTROL LIMITS FROM
HIGHWAY PROJECT LIMITS TO
MONTAGUE 1604-01-007 FM 455
FM 1655 STP 2B25(079)HES GREENWOOD LANE
LENGTH:
MONTAGUE 2292-02-005 FM 455
FM 730 F 2B25(113) WISE COUNTY LINE
LENGTH:
MONTAGUE 1604-01-010 GREENWOOD LANE
FM 1655 STP 2B25(079)HES WISE COUNTY LINE
LENGTH:
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .