D08 TUC Conference Room Upgrades Questions:
1. Does equipment have to follow the APL list of Approved devices from DISA?
1. Does the equipment need to be TAA Compliant ?
1. Due to the global microchip shortage APL approved equipment is up to 250 days backorder, will the government take this into account for POP timeline?
Responses:
1. No, DISA only applies to DoD projects as far as what I am reading.
1. Yes it must be TAA compliant, but I believe the TAA threshold is $183,000 so may not apply here.
1. See #1, probably does not apply since not using DISA APL.