This is a Questions and Answers (Q&A) document for a federal contract opportunity related to tower installation work at Tesuque Peak, New Mexico. The document addresses contractor inquiries regarding the Statement of Work (SOW) and Request for Quote (RFQ) for antenna and equipment installation services.
Key technical clarifications include: contractors are responsible for paying electrical contractors and incorporating costs into their price quotes; prevailing wage or Davis Bacon rates applicability was under government review at the time of publication; contractors must provide new antenna mounts compatible with the existing tower frame structure with no removal required; the Cambium PTP-820 installation requires two LMR-400 coaxial cables per assembly as specified in the SOW; and no minimum antenna protrusion requirement exists. Regarding contractor qualifications, the government declined to waive the Motorola R56 Installer Certification requirement despite contractor concerns about limited availability and high costs. Scheduling requirements mandate that all tower work, including antenna and cable mounting, be completed by Tuesday of each work week to accommodate FBI team testing and training activities Wednesday through Friday, which typically requires contractors to work the preceding weekend. All government responses indicated no changes were required to the solicitation documents based on these clarifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA Tesuque Peak Responses and Answers V2.pdf | ||
| ACRx RFQ 15F06726Q0000315.pdf | ||
| QA Tesuque Peak.xlsx | XLSX spreadsheet | |
| Statement of Work (SOW) - Tesuque Peak.pdf | ||
| Tesuque Peak_NM_FCDs_Rev0_2026-04-16_5.pdf | ||
| Sandia Crest_FCDs_Rev0_2026-04-16_4.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Document Pages/Section/Paragraph Question Government Response RFQ Change Required? (Y/N)
Statement of Work(SOW)-
Tesuque Peak Page 5 / Section 3.15
Who's responsibility is it to pay for the electrical contractor?
It is the contractors responsibility to pay for the electrical contractor and include this work in their price quote.
N
NA NA
Do prevailing wage rates or davis bacon rates apply to this project?
This is being reviewed. The Government's response to this question will be posted early next week.
Tesuque
Peak_NM_FCDs_Rev0_2026-
04-16_5 and Statement of
Work(SOW)-Tesuque Peak
CD Page C-4 and SOW Page 3
/ Section 3.4
The construction drawings show us reusing the existing mounts for the panel antenna installs but the SOW states we are to provide new ones. Please confirm scope.
The tower has an existing rectangular metal structure/frame that antennas or other equipment can be mounted to. The bidder will need to provide new mounts that will allow the antenna to attach to this existing structure. The CDs reference the existing structure on the tower, not the mounting equipment that will allow the antenna to attach to that structure.
N
Tesuque
Peak_NM_FCDs_Rev0_2026-
04-16_5 and Statement of
Work(SOW)-Tesuque Peak
CD Page C-4 and SOW Page 3
/ Section 3.4
If we are provide new mounts, are we removing the existing or have they already been removed?
The new mounts will allow the antenna to attach to the existing frame/structure on the tower. There is nothing to remove.
N
Tesuque
Peak_NM_FCDs_Rev0_2026-
04-16_5 and Statement of
Work(SOW)-Tesuque Peak
CD Page C-4 and SOW Page 3
/ Section 3.4
If we are provide new mounts, is there a minimum amount the antennas need to stick out from the tower?
No N
Statement of Work(SOW)-
Tesuque Peak Page 6 / Section 5
The SOW requires the contractor to possess a Motorola R56 Installer
Certification. Due to the limited availability and high cost of this specific certification, would the Government consider waiving this requirement if the contractor can demonstrate substantial experience performing tower grounding, bonding, and site installation work in accordance with Motorola R56 standards?
No N
Statement of Work(SOW)-
Tesuque Peak
NA
Previously, when doing these super sector installs, we would have to do site integrations on Tuesday's so we would have to work weekends to finish the installations. Will that be the case for this project as well?
Reference Section 4 of the SOW for scheduling details. This is based on the contractor's coordination with tower owners. Contractor will need to have work completed on or before Tuesday of the work week. This will require the contractor to work the previous week and/or weekend. The FBI team requires the tower work complete (antennas and cables mounted to towers, cables dressed to equipement racks) by the Tuesday of a work week to allow FBI technicians to handle final testing and/or training Wednesday through
Friday.
N
Statement of Work (SOW) -
Tesuque Peak.pdf
Sections 3.9, 3.10, and 3.11 /
Pages 4–5
The SOW states that the Cambium PTP-
820 installation uses a dual ODU configuration requiring two LMR 400 coaxial cables per assembly. A tower vendor reviewing the scope noted that typical PTP-820 installations may require fiber/data and power or hybrid cabling instead of LMR 400. Please confirm the correct cable type, data connection method, power method, and whether any adapter, converter, hybrid cable, or alternate cabling configuration is required for the PTP-820 ODU assemblies.
The SOW is correct. A Cambium PTP-820 needs 2 runs of LMR-400 per assembly.