This document is an Amendment (Amendment 00003) to Solicitation 15BFA025B00000019 for an Elevator Modernization project at the Federal Detention Center in Philadelphia. The amendment extends the bid submission deadline to Friday, May 30, 2025 at 10:00 a.m. and incorporates responses to questions submitted by prospective bidders, including clarifications on contractor responsibilities for Fire Alarm Recall updates, electrical upgrades, emergency phone lines, generator signals, and other technical aspects of the elevator modernization project.
The questions and answers provide detailed guidance on the project scope, specifically for the four existing passenger elevators. Key contractor responsibilities include implementing Fire Alarm Recall updates, performing all electrical upgrades, installing emergency phone lines, replacing controllers with new microprocessor controllers, and testing various system components. The project is a 100% small business set-aside with a NAICS code of 238290, and the estimated project value falls between $1,000,000 and $5,000,000, with a performance period of 875 calendar days from the notice to proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Abstract.pdf | ||
| Amendment 00006.pdf | ||
| Wage Determination PA20250003 Mod 4.pdf | ||
| Amendment 00005.pdf | ||
| Amendment 00004.pdf | ||
| Amendment 00002.pdf | ||
| Amendment 00001.pdf | ||
| 15BFA025B00000019.pdf | ||
| Instructions to Bidders.pdf | ||
| Criminal History Check Form.pdf | ||
| Wage Determination PA20250003 Mod 3.pdf | ||
| Bid Bond SF24.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
3. EFFECTIVE DATE
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
00003
BFAO
Joshua Cortez, Contracting Officer
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
1. CONTRACT ID CODE
15BFA025B00000019
4. REQUISITION/PURCHASE REQUISITION NUMBER
9A. AMENDMENT OF SOLICITATION NUMBER
15BFA025B00000019
5. PROJECT NUMBER (If applicable)
25Z2AD3
1 1
05/20/2025
9B. DATED (SEE ITEM 11)
04/18/2025
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15B21725PR000041
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to incorporate the following:
1) Responses to questions submitted by prospective bidders. This document is added to the solicitation for reference.
2) The date and time for the submission of bids is hereby extended. Bids are now due by Friday, May 30, 2025 at 10:00 a.m.
All other terms and conditions of the contract remain unchanged.
X
FDC PHILADELPHIA – ELEVATOR MODERNIZATION
PROJECT 25Z2AD3 QUESTIONS & ANSWERS
SOLICITATION 15BFA025B00000019
SUBMITTED BY JGM PROPERTY GROUP:
1. Who is responsible for Fire Alarm Recall updates for this project? Along with testing this?
Clarification: The contractor is responsible for implementing all required Fire Alarm Recall updates as part of this elevator modernization project. See the section titled “Controllers”, which specifies that the new controllers must include onboard diagnostic capabilities and support Fireman's Service Phase I and Phase II operations, in compliance with current fire and elevator code requirements.
See Section E: Testing and Acceptance, which states that the contractor is responsible for performing all operational testing, system break-in, adjustments, and optimizations. This includes verifying that the fire recall functions operate properly and ensuring the elevator control system is fully functional and compliant prior to final acceptance.
2. Who is responsible for electrical upgrades for this job? Shunt trips, Disconnect Switches, Pit Lighting Etc?
Clarification: The contractor is responsible for all electrical upgrades associated with this project. See Traveling Cables/Hoistway & Machine Room Wiring (Page 1), which includes providing all new machine room and hoistway wiring, along with any necessary electrical upgrades such as fittings, conduit, junction boxes, and lighting. All wiring and cable routing must comply with current fire and electrical codes.
3. Who is responsible for phone lines and phone monitoring?
Clarification: The contractor is responsible for the installation of the emergency phone lines as part of this project. See Car Operating Station (Page 2), which states that each car will be equipped with a digital position indicator display, an emergency hands-free phone, and an emergency light. See Traveling Cables/Hoistway & Machine Room Wiring (Page 1), which specifies that new cables will include a shielded pair designated for emergency phone communication and a CAT6 cable for cab security camera operation.
4. There are sprinkler heads that may need to be moved depending on equipment placement. Who’s responsible it that?
Clarification: If the sprinkler heads need to be moved during this project or after the project is complete the BOP will be responsible for having them moved.
5. Are we replacing the remote car operating panels in the central control station with another remote car opening panel or just replacing them to match what is on the spec? Also, the replacement of the intercom is currently set up for all 6 cars in the building. We would need to update the intercom on the other two cars technically. What do we do about this?
Clarification: The existing controllers will be removed and replaced with new microprocessor controllers by the contractor. The new panels must match what is specified in the SOW. At this time, the other two cars in the building on the intercom panel will remain on the original system.
6. Also the wiring to remove car operating panels in the central control may need to be retained depending on if the conduits are accessible or not. Will that be Ok?
Clairification: The wiring for car operating panels in the central control is accessible and will not need to be retained.
7. Who is responsible for the generator signal to control room along with testing this?
Clarification: The contractor is responsible for the generator signal to the control room along with having it tested when complete.