Pre-Bid Meeting Minutes.pdf
PDF 505 KB Posted
- Attached to
- FCC Beaumont- Paint Water Tower Federal contract opportunity
- Solicitation number
- 15BFA023B00000011
About this file
The pre-bid meeting minutes document the meeting for solicitation number 15BFA023B00000011 to paint the water tower at FCC Beaumont. The federal Bureau of Prisons seeks a contractor to paint the water tower with a project magnitude between $1,000,000 to $5,000,000. The contractor must complete the work within 119 calendar days of the notice to proceed, and liquidated damages are $1,382.81 per day for delays. The pre-bid meeting informed attendees about the site visit, bid submission requirements, wage decisions, hiring goals, work hours and other project details. Attendees were also advised of safety and security requirements for working at the federal correctional complex.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Wage Determination TX20230256 Mod 2.pdf | ||
| Instruction to Bidders.pdf | ||
| SF24- Bid Bond Form.pdf | ||
| Solicitation.pdf | ||
| Criminal History Check Form.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-BID CONFERENCE MEETING MINUTES
15BFA023B00000011 - PAINT WATER TOWER
FCC BEAUMONT- PROJECT 5AM9
DATE: Tuesday, July 18, 2023, at 9:00 AM CST Place: FCC Beaumont - Facilities Trailer
CONTRACTING OFFICER (Hope Alexander):
I. INTRODUCTIONS:
Round table introduction of all attendees.
Name
Hope Alexander, Contract Specialist
Melissa Matt, Business Administrator
Michael DeMatteo, Acting Facilities Manager
Logan Rodgers, Engineering Tech
Steven McBride, Utility Systems Operator
David Arredondo, Safety Compliance Specialist
Chase Troutman, Captain
Patrick White
Ben Brandau
II. PURPOSE OF MEETING:
Organization Represented
Federal Bureau of Prisons, FCC Beaumont
Federal Bureau of Prisons, FCC Beaumont
Federal Bureau of Prisons, FCC Beaumont
Federal Bureau of Prisons, FCC Beaumont
Federal Bureau of Prisons, FCC Beaumont
Federal Bureau of Prisons, FCC Beaumont
Federal Bureau of Prisons, FCC Beaumont
US Coatings
US Coatings
Indicate the purpose of this meeting is to familiarize the contractor with the unique circumstances and requirements surrounding a correctional setting . This meeting is also to explain the solicitation, as issued, and not to furnish additional information .
State - nothing said here shall be interpreted as a change to the solicitation without the issuance of a formal amendment through the FAQ Contracting Officer, Patrick Ford .
Ill. MINUTES:
Advised minutes will be recorded and distributed via the System for Award Management (SAM) database at www.sam.gov.
IV. SITE VISIT INFORMATION:
Walk to selected site for Paint Water Tower immediately following the meeting .
1 I Page
FCC BEAUMONT- PROJECT 5AM9
V. FRONT COVER PAGE FORMS AND INSTRUCTIONS:
Note the instructions on the cover letter in the Solicitation and all bids sent by mail shall be addressed to the Department of Justice JEFS system URL link included on the documents. Original copies of bid bonds shall be sent by mail to the following address:
FEDERAL BUREAU OF PRISONS
U.S. ARMED FORCES RESERVE COMPLEX
ATTN: Patrick Ford
346 MARINE FORCES DRIVE
GRAND PRAIRIE, TX 75051
VI. TIME FRAMES AND LOCATION FOR SUBMISSION OF BIDS:
State the deadline for submission of bids for this project is August 9, 2023, by 1 :00 PM PST. To the above-mentioned addresses.
VII. GENERAL TOPICS:
The following submission/completion items will be addressed :
1. From the solicitation, each bidder SHALL complete and submit the following forms , clauses, and statements with his/her bid. Failure to do so may cause your bid to be considered as non responsive:
• STANDARD FORM 1442 Pages 1 & 2: Please include DUNS number and Tax ID# and e-mail address where indicated in block 10 and complete blocks 14-20c. If your company has a "doing business as" name reflected in you SAM registration , include this name as well in Block 14.
Ensure the address typed in block 14 matches the address in your SAM registration .
• PAST PERFORMANCE SUBMISSION: Please ensure the Cover letter is reviewed and complied with its entirety. References and banking submissions must be submitted in advance to the bid opening directly to Patrick Ford , Contracting Officer, via email.
• COMMODITY OR SERVICES SCHEDULE (PAGE 4): Complete the Unit Price (JB = job) and Amount blocks (these amounts will be the same) . Note: The amounts listed in this section should be the same as the amount listed in block 17 of the SF-1442.
• BID GUARANTEE: See Page 5 of the solicitation . A bid bond must be submitted in original (ink signatures) with your solicitation . The penal sum of the bond must be at least 20% of the bid price, not to exceed $3 million , whichever is less. A blank bid bond was included in the solicitation. The bid bond must be from a Government approved surety. A list of approved sureties can be located on the Department of Treasury, Bureau of the Fiscal Service website.
2 I Page
FCC BEAUMONT- PROJECT 5AM9
• REPRESENTATIONS AND CERTIFICATIONS: All contractors submitting a bid must be registered in the System for Award Management (SAM) at www.sam.gov with the North American Industry Classification Standard code (NAICS) 238320 which is applicable to this acquisition.
• FAR PROVISION 52.204-8: Pursuant to the section (b) (1) of this provision , provision 52.204-7 is included in this solicitation. Bidders should not mark either of the two options under section (b)
(2) . Leave these options unmarked.
• FAR PROVISION 52.204-24: Pursuant to section (c) of this provision , bidder shall complete section (d) as applicable.
• FAR PROVISION 52.209-7: Bidder shall complete section (b) of this provision.
• FAR PROVISION 52.209-13: Pursuant to section (b) of this provision, Certification. Bidder shall check either ( 1) or (2).
• FAR PROVISION 52.229-11: Bidder shall complete section (d) of this provision and follow the remaining requirements of the provision as applicable.
• AMENDMENTS: Amendments (if any) must be acknowledged and submitted with the bid by one of the methods as described in item eleven of the Standard Form 30.
2. Other general items addressed :
• DAVIS BACON ACT: This contract is subject to the Davis Bacon Act. Wage Decision TX20230256 is applicable for this area. All applicable workers must be paid according to the terms of the wage decision .
• HIRING GOALS: Hiring goals for this project are 22.6% for minorities and 6.9% for females - A "Good Faith" effort should be put forth by the contractor to achieve these goals.
• LICENSING AND PERMITS: All required licensing and permits are required to be obtained by the contractor who receives contract award.
• MAGNITUDE: The magnitude of the project is between $1,000,000 and $5,000,000.
• WORK HOURS: Work hours within the secure perimeter shall be between 7:00 am and 3:30 pm Monday through Friday excluding weekends and federal holidays.
• COR: The Contracting Officer's Representative (COR) is Mr. James Fennel, Facilities Manager at FCC Beaumont.
• PERIOD OF PERFORMANCE: The completion period is 119 calendar days after issuance of notice to proceed .
3j Page
FCC BEAUMONT- PROJECT 5AM9
• TIME EXTENSIONS: Time extensions for inclement weather will not be granted unless the weather is unusually severe and abnormal in comparison to prior years.
• LIQUIDATED DAMAGES: Liquidated damages for this project are in the amount of $1,382.81 per calendar day of delay after scheduled completion .
• PRE-CONSTRUCTION CONFERENCE: A Pre-Construction conference is required after the contract is awarded and will be scheduled accordingly.
• PROGRESS SCHEDULE: A copy of the progress schedule is to be provided to the Contracting Officer and COR as soon as possible. Each time the progress schedule is changed , it must be provided to both the Contracting Officer and COR. It is suggested an updated document be provided by the Prime Contractor at the mandatory monthly progress meeting.
• PROGRESS MEETINGS: Progress meetings are mandatory and will be scheduled monthly.
• PAYMENT REQUESTS: Applications for payment are to be submitted on AIA G702(Continuation) or the contractors own form as long as the information is similar to the G702. Contactors can get these forms from the following website www.aiabookstore.com
• QUESTIONS: Oral questions asked at Site Visit of a technical nature are not acceptable due to the possibility of misunderstanding or misinterpretation . All questions shall be sent in WORD FORMAT to Patrick Ford, FAQ Contracting Officer, via email at pford@bop.gov. In order to provide sufficient response time prior to the bid due date, the Government has establ ishing that questions be submitted no later than July 25, 2023, at 10:00 AM, PST.
• ACCESS TO SITE/PARKING OF VEHICLES: Parking will be provided for employee vehicles and contractor work vehicles.
• STORAGE OF MATERIALS: Storage of materials will be coordinated with the COR.
• CONTRACTOR TEMPORARY OFFICE: No temporary office space will be provided .
• INSPECTIONS: "Punch List" items generated by inspections will be corrected and discrepancy items re-inspected and approved before contract closure takes place. Should any work be covered without proper notification, the contractor shall uncover that work for inspection at his own expense.
SAFETY MANAGER (D. Arredondo):
3. SAFETY POINTS:
• The contractor is responsible for providing required protective gear to all contractor workers, should it be required. Contractor will ensure that all workers have proper safety gear at all times.
4I Page
FCC BEAUMONT- PROJECT 5AM9
• Contractor is responsible for the prevention of accidents on the project site and has spill kit onsite and containment procedures. OSHA requirements will be adhered to.
• The Contractor will have a Safety Representative on site at all times during the completion of this project.
• Proper storage of any chemicals in lay down yard with SOS present.
CAPTAIN (C. Troutman):
4. SECURITY
• ADVERSE WEATHER: Whenever adverse weather conditions or other institution emergency contingencies are in effect, contract workers will not be permitted passage into the secure institution . Should emergency conditions be implemented while contract workers are inside the secure perimeter, they will be required to secure their tools , remove vehicles and equipment, and leave the institution grounds until the emergency situation has been resolved.
Depending upon the nature of the emergency, this normally will not affect any construction outside of the secure perimeter. Contractor is reminded that fog days will be treated like rain days. The performance period of 119 days will allow adequate time to complete the job, and no consideration will be allowed for normal rain days and normal fog days. The normal rain , snow or fog days will be based on the average over the last ten (10) years for the local community.
• SECURITY CLEARANCES: Contract workers are subject to security investigative procedures.
Please refer to the contract for details. Please refer to Page 30 of the contract.
• EMPLOYEE IDENTIFICATION: Contractor personnel working on project site must bring valid photo identification to the institution each day. The identification will be surrendered upon entry to and returned upon exit from institution property.
• TOOL ACCOUNTABILITY: Strict accountability and control of all contractor tools and hazardous materials must be maintained at all times. All contractor tools to be used inside the secure perimeter must be inventoried and accounted for at the conclusion of the workday Contractor tools may not be stored on-site overnight. The contractor should provide for enough time at the conclusion of the workday for the return and accounting of all tools issued during the workday. Lost or missing tools must be reported to the COR the Captain immediately.
• ILLEGAL ITEMS ON FEDERAL PROPERTY: Firearms, ammunition, knives, other weapons, drugs, narcotics, and alcoholic beverages are not permitted inside/outside the secure perimeter or anywhere else on Federal property at any time. This includes the private vehicles of contract workers. Violators will be subject to criminal prosecution. All persons, vehicles, and equipment are subject to search by institution authorities at any time.
5j Page
FCC BEAUMONT- PROJECT 5AM9
• NO CONTACT WITH INMATES: Contract workers are not to have any contact with inmates at any time. No photographs may be taken of inmates.
• CONTRACTOR EMPLOYEE WORK DRESS: Camouflage, green or khaki-colored clothing is not allowed , as inmates wear these colors.
• PHOTOGRAPHS: The institution's Facilities Department maintains a digital camera that will be utilized by FBOP staff to document the project work. The Contractor may request copies of these photos and may request that photos be taken for specific conditions. Cellular telephones equipped with photographic capabilities are prohibited on the project construction site.
VIII. ADDITIONAL DISCUSSION:
Job-site trailer and Conex space is available on site. The contractor must provide the job-site trailer and/or Conex box and it will be placed in designated areas assigned by Facilities staff. If the performance period of 119 days is a concern, please send questions in WORD FORMAT to Patrick Ford, FAQ Contracting Officer, via email at pford@bop.gov.
Meeting minutes recorded by:
NOTICE:
MEETING MINUTES ARE PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THEY ARE NOT
INTENDED TO CHANGE ANY SPECIFICATIONS, TERMS OR CONDITIONS OF THE
SOLICITATION. ANY AND ALL CHANGES TO THE SOLICITATION SHALL BE ISSUED IN
SUBSEQUENT AMENDMENTS ISSUED BY THE CONTRACTING OFFICER ON A STANDARD
FORM 30 (SF-30).
61 Page
Name n \ A \ r _'C\,(.. W '-' :
5. rnc{31, - e ~ Arr lJ.-t.e..-J o
(v'1 DCMA[(rf)
L f<-v~rRs C:-Tizo~M~
PRE-BID CONFERENCE/SITE VISIT
SIGN-IN SHEET
TUESDAY, JULY 18@ 9:00 AM
PAINT WATER TOWER- PROJECT SAM9
SOLICITATION NO.: 15BFA023B00000011
FEDERAL CORRECTIONAL COMPLEX
BEAUMONT, TEXAS
Title Company
~ VS, C.
t/J' ~ 4,'/.1.
p(_c_ Geut1~!
SI>\\~ <y=c c. ?>LJ\._ ....... ...-vv.!> /), -r
&r Cf) ~cc f 0:, ltL h FCL fee..~~ .. ~
Signature
12--
| Pre-Bid Meeting Minutes Signed |
| PREBID SITE VISIT SIGN IN SHEET |
File details come from the government source that posted it. Updated .