This document is a Statement of Work (SOW) for landscaping services at the Federal Bureau of Prisons (FBOP) Metropolitan Detention Center - Building 4 in Brooklyn, NY. The contractor will be responsible for providing all necessary equipment, labor, materials, and incidentals to maintain the common areas around the building, including weed control, debris removal, and ensuring walkways and edges are free of weeds. The initial cleanup is scheduled for April 2024, followed by bi-weekly services from May 1, 2024 through September 30, 2024. The FBOP will provide water, restrooms, and minimal electricity, while the contractor must obtain any required permits. The contractor must adhere to all environmental, safety, and local regulations. Security clearances and personal protective equipment are required for contractor personnel. The related federal contract opportunity is Solicitation Number 15BBR024Q00000013 for MDC Brooklyn Building 4 and Dayton Manor landscaping services. Quotes are due by April 19, 2024, and the award will be based on past performance, lowest price, and delivery time.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CONTRACTOR INFORMATION SHEET.pdf | ||
| Service Contract Act WD 2015-4187.pdf | ||
| SOW Landscape Dayton Manor.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK/SPECIFICATIONS
MDC Brooklyn – Building 4
Landscaping Services
I. SPECIFICATIONS:
A. INTRODUCTION
The Federal Bureau of Prisons (FBOP), Metropolitan Detention Center- Building 4, located at 199 Flushing Avenue in Brooklyn, NY 11205 intends to make a single award to a responsible entity that will provide all necessary equipment, labor, materials, and incidentals to perform landscaping services.
B. SCOPE OF WORK
The contractor is responsible to provide all equipment, materials and labor to maintain all common areas with weed control on all roadways, pavement, sidewalks, and gravel areas, on all sides of the building. All leaves and foreign debris will be removed from the site on a bi-weekly basis. All walkways, driveways and edges of the building will be kept free of weeds. An initial cleanup will be performed in April 2024, followed by bi-weekly services to maintain the area. Any time chemicals are applied warning signs must be posted in the area, so occupants know that chemicals have been applied to the area. The schedule of services is as follows:
• Initial cleanup (April 2024)
• Bi-weekly services (May 1, 2024 – September 30, 2024)
C. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS
All requirements, environmental compliance, Life Safety, and Federal, State and Local codes and regulations will be considered during all phases of this contract.
Services and materials provided by the contractor will adhere to and shall be consistent with the most current industry standards.
It is the contractor’s responsibility to obtain permitting, should it be required. Copies of all permits must be submitted to the COR upon receipt from local agency.
D. UTILITIES
The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.
E. HOUSEKEEPING AND MATERIAL DISPOSAL
The contractor awarded the contract will be responsible to remove any cut grass, brush, and other debris from the services off the premises.
F. SUBMITTALS & TRAINING
1. All security clearance paperwork/documentation shall be submitted to the COR a minimum of (14) working day prior to the start of work (see below).
2. Any deviations from this Statement of Work will be considered a Change Order Request and must be authorized through the institution’s Contracting Officer prior to the implementation of the requested change.
3. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractors’ employees. Damage will be corrected and restored to previous condition at no cost to the Government.
II. CONTRACTOR SECURITY/WORKING REGULATIONS
A. Work Hours:
Work Hours for the contractor are 7:00 AM – 2:00 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work.
C. Storage of Materials and Equipment:
The storage of any type of chemical on site is prohibited.
D. Security Clearance/Contractor Badges:
The contractor shall provide the COR with all the necessary security clearance documents for all contractors and subcontractor employees accessing the work area. In the event a contractor or subcontractor employee cannot pass the security clearance process, it will be the contractor’s responsibility to provide another candidate. By law the BOP cannot, and will not, release any information to the contractor concerning the nature of why a contractors or subcontractor employee was not able to pass the security clearance process.
E. Safety and Personal Protective Equipment:
All contractors and employees shall have and wear the required personal protective equipment (PPE) always prescribed by industry standards while on the job site. It is the responsibility of the contractor to provide all PPE equipment. All ladders regardless of the size shall be stored and secured to a stationary fixture with a chain and lock in a predetermined area, in a way that they cannot be removed. If ladders are required, immediately consult with the COR to ensure that he or she can make timely notification to appropriate institution staff. All extension cords regardless of length shall be in good condition with no broken outer insulation and will be secured in a locked construction gang box.