Questions_and_Answer_VIX.pdf
PDF 46 KB Posted
- Solicitation number
- 15B61618B00000003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract.pdf | ||
| Amendment_00004_-_Victorville.pdf | ||
| AMEND_0003_Victorville.pdf | ||
| 3_-_Statement_of_Work_(AMENDED).pdf | ||
| AMEND_0002_Victorville.pdf | ||
| AMEND_0001_Victorville.pdf | ||
| Sign-in_Sheet.pdf | ||
| Meeting_Minutes.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FCC VICTORVILLE – REPLACE CNG FUELING SYSTEM
PROJECT 6C2A QUESTIONS & ANSWERS
SOLICITATION 15B61618B00000003
SUBMITTED BY JAYCOX CONSTRUCTION CNG:
1. Drawings- will they be required to be stamped by an Engineer?
CLARIFICATION: No, Compressor package and dispensers will be pre-engineered with all associated piping installed in compliance with NFPA 52 and NFPA 70.
2. Permitting- Will Permitting be required?
CLARIFICATION: Permitting is not required through the municipality, any permits if required through Mojave Desert Air Quality Management District or San Bernardino County Fire Department CUPA will be the responsibility of the contractor.
3. If all specifications cannot be met for the compressor system, will it be accepted? if so, is there a suggested submittal for the difference in systems?
CLARIFICATION: All minimum specifications shall be met,
4. Is there a possibility for an extension for the questions on equipment for determination of approval of systems?
CLARIFICATION: No
5. Is there a possibility for an extension of the bid deadline?
CLARIFICATION: No
6. PM service is not mentioned only training. Could you clarify whether or not PM service should be part of this bid?
CLARIFICATION: No, PM service is not to be included in bid.
7. How many more vehicles will be added? What is the expected growth that you anticipate needed for this system to fuel?
CLARIFICATION: Expected growth within the service life of the system will be 7 vehicles.
8. Is there current inlet gas analysis available for the site?
CLARIFICATION: No current inlet gas analysis is available for the site.
9. Do you want the compressors to have dial out ability for alarm and fault?
CLARIFICATION: No, “dial out ability” is not a requirement of the system.
10. Specifications state that crank case should run at 230 psig which is not applicable to the compressor package, will that specification be removed?
CLARIFICATION: Please see SOW I.B.2. Page 1 states “Compressors will have an encapsulated crankcase that is pressure-resistant up to 230 psig”, This is a minimum requirement.