Questions_and_Answer.pdf

PDF 47 KB Posted

Attached to
FCI Sheridan - Replace Cooling Tower Federal contract opportunity
Solicitation number
15B61219B00000001
Issued by
Department of Justice Bureau of Prisons Field Acquisition Office

About this file

Questions and Answer

View the file

Other files for this federal contract opportunity

Other files attached to FCI Sheridan - Replace Cooling Tower, newest first.
File Type Posted
Bid_Abstract.pdf PDF
5_-_Construction_Wage_Rate_(UPDATED).pdf PDF
AMEND_0002_Sheridan.pdf PDF
AMEND_0001_Sheridan.pdf PDF
3_-_Statement_of_Work_(UPDATED).pdf PDF
Site_Visit_Meeting_Minutes.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FCI SHERIDAN – REPLACE COOLING TOWER

PROJECT 6C5E QUESTIONS & ANSWERS

SOLICITATION 15B61219B00000001

SUBMITTED BY JOHNSON CONTROLS:

1. Work Hours: The statement of work says the working hours are between 6:00 AM – 2:00 PM, while the pre-bid conference meeting notes states the work hours are between 7:00 AM – 3:30 PM. Could you clarify when the working hours are?

CLARIFICATION: Statement of Work; Page 2, Section G, 1

2. Will FCI Sheridan be reusing existing transformers and panels that are located under the cooling tower?

CLARIFICATION: The existing transformers and panels located underneath the cooling tower that provide service to other equipment than the cooling tower, will be reused and remain in use throughout the length of the project.

3. Talking to facilities staff at FCI Sheridan, it was mentioned that we wouldn’t be replacing the Water Treatment System. Can this be confirmed?

CLARIFICATION: Statement of Work; Page 5-6

4. Talking to facilities staff at FCI Sheridan, they mentioned a VFD would be running either the fans or pumps, but I don’t see any VFDs in the specs. Are VFDs included in this scope of work?

CHANGE: Statement of Work; Page 4, Section B

5. The lead time on the cooling tower may be an issue if the project duration is 88 days. Is it possible to extend the completion period?

CHANGE: We will change the lead time in Period of Performance to reflect 120 days.

6. For the past performance submission, is this only for the prime or do the subcontractors also need the previous experience?

CLARIFICATION: The past performance submission is only required for the prime.