15B61120B00000001A.pdf

PDF 280 KB Posted

Attached to
Gun Lockers at the Federal Detention Center (FDC) SeaTac, WA.
Solicitation number
15B61120B00000001
Issued by

View the file

Other files

File Type Posted
Questions and Answers 2020-08-27.pdf PDF
Wage Determination.pdf PDF
15B61120B00000001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO.

15B61120B00000001

INSTALL GUN LOCKER

FDC SEATAC

UNITED STATES DEPARTMENT OF JUSTICE

FEDERAL BUREAU OF PRISONS

FDC SEATAC

SEATAC, WA 98198

ISSUE DATE: AUGUST 4, 2020

OFFER DUE DATE: SEPTEMBER 14, 2020, by 12:00 P.M.(PST)

OFFERS SHALL BE ADDRESSED TO:

FEDERAL BUREAU OF PRISONS

FDC SEATAC

2425 SOUTH 200TH STREET SEATAC, WA 98198-5202

ATTN: JERRY LUCAS, SUPERVISORY CONTRACT SPECIALIST

INSTRUCTIONS TO OFFERORS

OFFERFFER SUBMISSION PROCEDURES

SOLICITATION/INVATION FOR BID

15B61120B00000001

TITLE: FDC SEATAC

INSTALL GUN LOCKER

DEADLINE FOR SEPTEMBER 14, 2020

RECEIPT OF OFFERS: 12:00 PM (PST)

MAIL OFFERS TO:

FEDERAL BUREAU OF PRISONS

FDC SEATAC

2425 SOUTH 200TH STREET

SEATAC, WA 98198-5202

ATTN: JERRY LUCAS, SUPERVISORY CONTRACT SPECIALIST

(206) 870-5768

***********************************IMPORTANT*********************************

CONTRACTORS MUST BE REGISTERED IN THE SYSTEM FOR AWARD MANAGEMENT (SAM) AT

WWW.SAM.GOV. THIS IS A 100% SMALL BUSINESS SET-ASIDE. YOUR BUSINESS SIZE

METRICS INFORMATION IN SAM MUST MEET THE SMALL BUSINESS SIZE STANDARD

REQUIREMENT FOR NAICS CODE 236220 (reference FAR provision 52.219-1 in the Representations & Certifications section of your SAM registration).

I. Each offeror SHALL complete and submit the following forms, clauses, and statements with his/her offer.

Failure to furnish all required information or any rejection of or addition to the terms and conditions of the solicitation may cause your offer to be considered as non-responsive and ineligible for award.

*SUBMIT PAGES 1, 2, 4, 20, 26-30 OF THE SOLICITATION DOCUMENT*

A. SECTION 1:

Standard Form-1442 – Solicitation, Offer, and Award, pages 1 & 2

Complete blocks 14 thru 20c (remember to include the signer’s title in block 20a). Ensure the address typed in block 14 matches the address in your SAM registration.

Blocks 21 thru 32 are to be completed only by the Government!

Include duns#, tax id#, CAGE code, and email address where indicated in block 10.

B. SECTION 2:

Commodity or Services Schedule, page 4

Complete the unit price (JB = job) and Amount blocks (these amounts will be the same).

NOTE: the amounts listed in this section should be the same as the amount listed in block 17 of the Standard Form-1442.

C. SECTION 6:

Provisions, page 25

Provision 52.215-20 Alternate-IV:

Submit a cost breakdown of your quotation pursuant to the instructions in this provision. This listing should be of individual costs (e.g., labor hours and cost per hour, material units and cost per unit, etc.), not merely lump sums.

D. SECTION 7:

Representations and Certifications, pages 26-30

1. FAR Provision 52.204-8

NOTE: Pursuant to section (b)(1) of this provision, provision 52.204-7 is included in this solicitation.

Therefore, offerors should not mark either of the two options under section (b)(2) since paragraph (d) AUTOMATICALLY applies. Leave these options unmarked.

2. FAO-0021

Complete in entirety.

D. Amendments, if any, must be acknowledged and submitted with the offer by one of the methods described in item eleven of the Standard Form-30 (amendment of solicitation/modification of contract).

*SUBMIT PAGES 1, 2, 4, 20, 26-30 OF THE SOLICITATION DOCUMENT*

II. PRE-QUOTATION CONFERENCE/SITE VISIT:

*********************************IMPORTANT**********************************

A pre-quotation site visit are scheduled for Monday, August 17, 2020 at 9:00 a.m. local time at FDC Seatac, 2425 South 200th Street, Seatac, WA 98198. Please present yourself in the Front Lobby no later than 8:45 a.m. This will ensure the meeting is started on time.

This is the only pre-quotation site visit scheduled.

The pre-quotation site visit is not mandatory (see provision 52.236-27 Alternate I of the solicitation). However, all offerors are urged to attend.

If you wish to attend, email Kenneth Muma at kmuma@bop.gov (Subject: Install Gun Locker project), no later than Thursday, August 14, 2020 at noon, with the following information:

Company name and list of individuals from the company who will be attending.

Phone number/point of contact for the company.

Questions regarding the site visit is to be directed to Jerry Lucas, Supervisory Contract Specialist, (206)870-5768, SET/Contracting@bop.gov.

Any questions relating to the solicitation after the closing of the pre-quotation site visit shall be sent to Jerry Lucas, Supervisory Contract Specialist, via email SET/Contracting@bop.gov no later than Friday, September 4, 2020 at 12:00 p.m. (PST). In order to provide sufficient response time prior to the offer due date, the Government is establishing the above cut-off date for questions about the solicitation. All offerors shall offer in accordance with the current solicitation to include all amendments (if any) as issued by the Contracting Officer only.

A. Offer Label (see template below)

1. This label shall be completed and used on the envelope containing the offer. This envelope shall be placed inside of shipping boxes or envelopes supplied by couriers such as FedEx. Complete the information on the label and cut and paste or transfer it to the LOWER left corner of the envelope containing your offer (not on the courier envelope/packaging). Print or type your name and address in the UPPER left corner of the envelope containing your offer.

*Double check all amendments (if issued) for any offer due date extension and enter accordingly on label* mailto:kmuma@bop.gov

BID/OFFER

SOLICITATION NO.

15B61120B00000001

DATE FOR RECEIPT OF BIDS/

OFFERS September 14, 2020

TIME FOR RECEIPT OF BIDS/OFFERS

12:00 P.M. PST (Noon)

OFFICE DESIGNATED TO RECEIVE BIDS/OFFERS

Federal Bureau of Prisons

FDC SEATAC

2425 SOUTH 200th STREET

SEATAC, WA 98198

CONTRACTING OFFICER

NAME JERRY LUCAS

15B61120B00000001 Page 1 of 30

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

15B61120B00000001

X SEALED BID (IFB)

NEGOTIATED (RFP)

2. TYPE OF SOLICITATION 3. DATE ISSUED

08/04/2020

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

6C6F

CODE 15B611

Federal Bureau of Prisons FDC Seatac 2425 S. 200th Street SeaTac, WA 98198

7. ISSUED BY

Federal Bureau of Prisons FDC Seatac 2425 S. 200th Street

8. ADDRESS OFFER TO

9. FOR INFORMATION CALL: a. NAME

Jerry Lucas SET/Contracting@bop.gov

b. TELEPHONE NUMBER (Include area code)(NO COLLECT CALLS)

206-870-5768

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

The contractor receiving award shall provide all materials, labor, and equipment to Install Gun Locker at FDC Seatac in accordance with the requirements of 15B61120B00000001 solicitation .

*INCLUDE THE FOLLOWING INFORMATION*

DUNS NUMBER: ______________________

TAX ID NUMBER: _____________________

CAGE CODE: ________________________

E-MAIL: ____________________________

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 190 award, X notice to proceed. This performance period is X mandatory negotiable. (See FAR 52.211-10.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

12:00US/

Pacific a.

09/14/2020

b. An offer guarantee X is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

60d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

15B61120B00000001 Page 2 of 30

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

TOTAL FIRM-FIXED-PRICE OFFER AMOUNT: $__________________

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified) 27

ITEM

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY 15B611

Federal Bureau of Prisons FDC Seatac 2425 S. 200th Street SeaTac, WA 98198

Contracting Office

(O) 206-870-5768 SET/Contracting@bop.gov

Federal Bureau of Prisons FDC Seatac

PO BOX 13901

SEATTLE, WA 98198-1091

Accounting Office SETAccountsPayable@bop.gov

27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

Jerry Lucas

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 8/2014)BACK

15B61120B00000001 Page 3 of 30

Table of Contents

Section Description Page Number

1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements

FAO-0007 Payment Services FAO-0006 Contractor Use of Premises FAO-0008 Request for Final Inspection FAO-0012 Progress Meetings FAO-0010 Assignment of Contract Administration Office and Functions FAO-0013 Contract Closeout Procedures (for construction contracts exceeding $150,000) 52.24-403-70 Notice of Contractor Personnel Security Requirements (OCT 2005)

52.218-000 CONTINUING CONTRACT PERFORMANCE DURING A PANDEMIC INFLUENZA

OR OTHER NATIONAL EMERGENCY (May 2008) 2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (June 1996) 52.21-603-70 Contracting Officer's Representative (COR) (June 2012)

52.27-103-72 DOJ CONTRACTOR RESIDENCY REQUIREMENT BUREAU OF PRISONS (JUNE

2004) FAO-0001 Bonds FAO-0003 Required Insurance FAO-0004 Pre-Construction Conference FAO-0005 Submittals

4 Contract Clauses 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 52.211-12 Liquidated Damages-Construction (Sept 2000) 52.228-13 Alternative Payment Protections (July 2000) 52.225-9 Buy American-Construction Materials (May 2014) FAO-0015 Changes

5 Attachments 6 Solicitation Provisions

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) 52.236-27 Alt I Site Visit (Construction) (Feb 1995) - Alternate I (Feb 1995)

52.27-103-71 FAITH-BASED AND COMMUNITY-BASED ORGANIZATIONS (AUG 2005)

52.215-20 Alt IV Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data (Oct 2010) - Alternate IV (Oct 2010) 52.216-1 Type of Contract (Apr 1984)

7 Representations and Certifications 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran--Representation and Certifications (Jun 2020) 52.204-8 Annual Representations and Certifications (Mar 2020) FAO-0021 Business Management Questionnaire

15B61120B00000001 Page 4 of 30

Section 2 - Commodity or Services Schedule

SCHEDULE OF SUPPLIES/SERVICES

CONTINUATION SHEET

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 Install Gun Locker at FDC SeaTac in accordance with solicitation 15B61120B00000001

Firm Fixed Price

PSC: Y1GA

1 JB $________ $_________________

The successful contractor shall be responsible for all applicable federal, state and local taxes . No tax exemption certificate will be issued by the Federal Bureau of Prisons.

15B61120B00000001 Page 5 of 30

Section 3 - Special Contract Requirements

Clauses By Full Text

FAO-0007 Payment Services

(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form; however, it shall contain si milar information as the AIA Form G-702. The Contracting Officer will approve the amount of payment by signing and forwarding th e application and certificate as follows: Original to Accounting; Copy for Contract Award File.

(b) All small business contractors are required to self-certify on all invoices their small business status.

FAO-0006 Contractor Use of Premises

Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding F ederal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the pr oject, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance appro val of the Contracting Officer.

NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional fac ility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal in stitution routines. The procedures and institutional entrance/exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.

Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introducti on of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.

Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.

Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Con tractor shall be located in an area approved by the COR.

Safety and Accident Prevention In performing work under this contract the contractor shall:

(a) Conform to the specific safety requirements established by this contract;

(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contrac t;

(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and acc ident prevention purposes.

FAO-0008 Request for Final Inspection

15B61120B00000001 Page 6 of 30

The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written not ice of the date on which the work will be fully completed and ready for the Government’s final inspection.

FAO-0012 Progress Meetings

The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.

(a) At a minimum, the attendees shall include but is not limited to:

(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administrator/Mana ger, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).

(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufa cturers, Suppliers, etc.).

(b) The meeting should include, but is not limited to issues such as:

Administrative Contracting Officer:

(1) Old business from previous progress meeting(s);

(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);

(3) Review of payments made to date and review/approve current payment request;

(4) Status of modification proposal requests;

(5) Discuss new business.

COR:

(1) Status of escort coverage;

(2) Review gate or sallyport entrance/exit issues;

(3) Discuss other delays contractor may be experiencing;

(4) Discuss performance/quality issues.

Contractor:

(1) Review/discuss updated progress schedule;

(2) Provide 30 day outlook;

(3) Discuss other issues affecting performance.

FAO-0010 Assignment of Contract Administration Office and Functions

Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 B ack. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 4 2.302(b) to the extent that those functions apply to the contract.

FAO-0013 Contract Closeout Procedures (for construction contracts exceeding $150,000)

Contract Closeout must be completed within six (6) months of physical completion of the work.

Prior to payment of final invoice:

15B61120B00000001 Page 7 of 30

The contractor shall submit the following documents:

(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);

(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);

(3) All as-built drawings/shop drawings, if applicable;

(4) Contractor’s final invoice;

(5) Release of Claims (GSA Form 1142);

(6) Consent of Surety to Final Payment (AIA Document G707);

(7) Letter establishing warranty dates;

(8) Complete list of subcontractors with telephone numbers and points of contact;

(9) Guarantees and warranties;

(10) All balance and test reports;

(11) All operation/maintenance manuals;

(12) All permits and certifications.

AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.

GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).

52.24-403-70 Notice of Contractor Personnel Security Requirements (OCT 2005)

Compliance with Homeland Security Presidential Directive-12 (HSPD-12) and Federal Information Processing Standard Publication

201 (FIPS 201) 1 entitled "Personal Identification Verification (PIV) for Federal Employees and Contractors," Phase I.

1. Long-Term Contractor Personnel:

In order to be compliant with HSPD-12/PIV I, the following investigative requirements must be met for each new long-term 2 contract or employee whose background investigation (BI) process begins on or after October 27, 2005:

a. Contractor Personnel must present two forms of identification in original form prior to badge issuance (acceptable documents are listed in Form I-9, OMB No. 1615-0047, "Employment Eligibility Verification," and at least one document must be a valid State or Federal government-issued picture ID);

b. Contractor Personnel must appear in person at least once before a DOJ official who is responsible for checking the identification documents. This identity proofing must be completed sometime during the clearance process but prior to badge issuance and must be documented by the DOJ official;

c. Contractor Personnel must undergo a BI commensurate with the designated risk level associated with the duties of each position. O utlined below are the minimum BI requirements for each risk level:

* High Risk - Background Investigation (5 year scope)

* Moderate Risk - Limited Background Investigation (LBI) or Minimum Background Investigation (MBI)

* Low Risk - National Agency Check with Inquiries (NACI) investigation

d. The pre-appointment BI waiver requirements for all position sensitivity levels are a:

1) Favorable review of the security questionnaire form;

2) Favorable fingerprint results;

3) Favorable credit report, if required;3

4) Waiver request memorandum, including both the Office of Personnel Management schedule date and position sensitivity/risk level;

and

5) Favorable review of the National Agency Check (NAC) 4 portion of the applicable BI that is determined by position sensitivity/risk level.

15B61120B00000001 Page 8 of 30

A badge may be issued following approval of the above waiver requirements.

If the NAC is not received within five days of OPM's scheduling date, the badge can be issued based on a favorable review of the Sec urity Questionnaire and the Federal Bureau of Investigation Criminal History Check (i.e., fingerprint check results).

e. Badge re-validation will occur once the investigation is completed and favorably adjudicated. If the BI results so justify, badges is sued under these procedures will be suspended or revoked.

2. Short-Term Contractor Personnel:

It is the policy of the DOJ that short-term contractors having access to DOJ information systems and/or DOJ facilities or space for six months or fewer are subject to the identity proofing requirements listed in items 1a. and 1b. above. The pre-appointment waiver requ irements for short-term contractors are:

a. Favorable review of the security questionnaire form;

b. Favorable fingerprint results;

c. Favorable credit report, if required;5 and

d. Waiver request memorandum indicating both the position sensitivity/risk level and the duration of the appointment. The commen surate BI does not need to be initiated.

A badge may be issued following approval of the above waiver requirements and the badge will expire six months from the date of issuance. This process can only be used once for a short-term contractor in a twelve month period. This will ensure that any consecu tive short-term appointments are subject to the full PIV-I identity proofing process.

For example, if a contractor employee requires daily access for a three or four-week period, this contractor would be cleared accord ing to the above short-term requirements. However, if a second request is submitted for the same contractor employee within a twelve -month period for the purpose of extending the initial contract or for employment under a totally different contract for another three or four-week period, this contractor would now be considered "long-term" and must be cleared according to the long-term requirements as stated in this interim policy.

3. Intermittent Contractors:

An exception to the above-mentioned short-term requirements would be intermittent contractors.

a. For purposes of this policy, "intermittent" is defined as those contractor employees needing access to DOJ information systems and/ or DOJ facilities or space for a maximum of one day per week, regardless of the duration of the required intermittent access. For exam ple, the water delivery contractor that delivers water one time each week and is working on a one-year contract.

b. Contractors requiring intermittent access should follow the Department's escort policy. Please reference the August 11, 2004, and January 29, 2001, Department Security Officer policy memoranda that conveys the requirements for contractor facility escorted acces s.

c. Due to extenuating circumstances, if a component requests unescorted access or DOJ IT system access for an intermittent contracto r, the same pre-employment background investigation waiver requirements that apply to short-term contractors are required.

d. If an intermittent contractor is approved for unescorted access, the contractor will only be issued a daily badge. The daily badge will be issued upon entrance into a DOJ facility or space and must be returned upon exiting the same facility or space.

e. If an intermittent contractor is approved for unescorted access, the approval will not exceed one year. If the intermittent contractor requires unescorted access beyond one year, the contractor will need to be re-approved each year.

4. An individual transferring from another department or agency shall not be re-adjudicated provided the individual has a current (w ithin the last five years), favorably adjudicated BI meeting HSPD-12 and DOJ's BI requirements.

5. The DOJ's current escorted contractor policy remains unchanged by this acquisition notice.

Notes:

1. FIPS 201 is available at: www.csrc.nist.gov/publications/fips/fips201/FIPS-201-022505.pdf

2. Under HSPD-12, long-term contractors are contractors having access to DOJ information systems and/or DOJ facilities or space for six months or longer. The PIV-I identity proofing process, including initiation and adjudication of the required background inve stigation, is required for all new long-term contractors regardless of whether it is the current practice to issue a badge. The second p hase of HSPD-12 implementation (PIV-II) requires badge issuance to all affected long-term contractors.

3. For contractors in position sensitivity/risk levels above level 1, a favorable review of a credit check is required as part of the pre-ap pointment waiver package.

4. In order to avoid a delay in the hiring process, components should request an Advance NAC Report when initiating investigations t o OPM. Per OPM ' s instructions, to obtain an Advance NAC Report, a Code " 3" must be placed in block " B " of the " Agency Use Only " section of the investigative form. This report is available for all case types.

5.For contractors in position sensitivity/risk levels above level 1, a favorable review of a credit check is required as part of the pre-app ointment waiver package.

[End of Clause]

52.218-000 CONTINUING CONTRACT PERFORMANCE DURING A PANDEMIC INFLUENZA OR OTHER NATIONAL EMERGENCY (May 2008)

15B61120B00000001 Page 9 of 30

During a Pandemic or other emergency we understand that our contractor workforce will experience the same high levels of absente eism as our federal employees. Although the Excusable Delays and Termination for Default clauses used in Government contracts list epidemics and quarantine restrictions among the reasons to excuse delays in contract performance, we expect our contractors to make a reasonable effort to keep performance at an acceptable level during emergency periods.

The Office of Personnel Management (OPM) has provided guidance to federal managers and employees on the kinds of actions to be taken to ensure the continuity of operations during emergency periods. This guidance is also applicable to our contract workforce. Co ntractors are expected to have reasonable policies in place for continuing work performance, particularly those performing mission c ritical services, during a pandemic influenza or other emergency situation.

The types of actions a federal contractor should reasonably take to help ensure performance are:

* Encourage employees to get inoculations or follow other preventive measures as advised by the public health service.

* Cross-train workers as backup for all positions performing critical services. This is particularly important for work such as guard services where telework is not an option.

* Implement telework to the greatest extent possible in the workgroup so systems are in place to support succe ssful remote work in an emergency.

* Communicate expectations to all employees regarding their roles and responsibilities in relation to remote work in the event of a pandemic health crisis or other emergency.

* Establish communication processes to notify employees of activation of this plan.

* Integrate pandemic health crisis response expectations into telework agreements.

* With the employee, assess requirements for working at home (supplies and equipment needed for an extende d telework period). Security concerns should be considered in making equipment choices; agencies or contract ors may wish to avoid use of employees' personal computers and provide them with PCs or laptops as appro priate.

* Determine how all employees who may telework will communicate with one another and with management to accomplish work.

* Practice telework regularly to ensure effectiveness.

* Make it clear that in emergency situations, employees must perform all duties assigned by management, even i f they are outside usual or customary duties.

* Identify how time and attendance will be maintained.

It is the contractor's responsibility to advise the Government Contracting Officer if they anticipate not being able to perform and to w ork with the Department to fill gaps as necessary. This means direct communication with the Contracting Officer or in his/her absence, another responsible person in the contracting office via telephone or email messages acknowledging the contractor's notification. The incumbent contractor is responsible for assisting the Department in estimating the adverse impacts of nonperformance and to work di ligently with the Department to develop a strategy for maintaining the continuity of operations.

The Department does reserve the right in such emergency situations to use Federal employees, employees of other agencies, contract s upport from other existing contractors, or to enter into new contracts for critical support services. Any new contracting efforts would be acquired following the guidance in the Office of federal Procurement Policy issuance "Emergency Acquisitions", May, 2007 and Subpart 18.2. Emergency Acquisition Flexibilities, of the Federal Acquisition Regulations.

[End of Clause]

2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (June 1996)

(a) "Unsafe condition" as used in this clause means the actual or potential exposure of contractor or Government employees to a haza rdous material as defined in Federal Standard No. 313, and any revisions thereto during the term of this contract, or any other material or working condition designated by the Contracting Officer's Technical Representative (COTR) as potentially hazardous and requiring safety controls.

(b) The Occupational Safety and Health Administration (OSHA) is responsible for issuing and administering regulations that require c ontractors to apprise its employees of all hazards to which they may be exposed in the course of their employment; proper conditions and precautions for safe use and exposure; and related symptoms and emergency treatment in the event of exposure.

(c) Prior to commencement of work, contractors are required to inspect for and report to the contracting officer or designee the presenc e of, or suspected presence of, any unsafe condition including asbestos or other hazardous materials or working conditions in areas in which they will be working.

(d) If during the performance of the work under this contract, the contractor or any of its employees, or subcontractor employees, d iscovers the existence of an unsafe condition, the contractor shall immediately notify the contracting officer, or designee, (with written notice provided not later than three (3) working days thereafter) of the existence of an unsafe condition. Such notice shall include the contractor's recommendations for the protection and the safety of Government, contractor and subcontractor personnel and property th at may be exposed to the unsafe condition.

15B61120B00000001 Page 10 of 30

(e) When the Government receives notice of an unsafe condition from the contractor, the parties will agree on a course of action to mitigate the effects of that condition and, if necessary, the contract will be amended. Failure to agree on a course of action will cons titute a dispute under the Disputes clause of this contract.

(f) Nothing contained in this clause shall relieve the contractor or subcontractors from complying with applicable Federal, State, and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with hazardous material including but not limited to the use, disturbance, or disposal of such material.

(End of Clause)

52.21-603-70 Contracting Officer's Representative (COR) (June 2012)

(a)Kenneth Muma ,Engineering Technician , FDC Seatac,(206) 870-1003, is hereby designated as the Contracting Officer's Represen tative (COR) under this contract.

(b) The COR is responsible, as applicable, for: receiving all deliverables, inspecting and accepting the supplies or services provide he reunder in accordance with the terms and conditions of this contract; providing direction to the contractor which clarifies the contract or effort, fills in details or otherwise serves to accomplish the contractual Scope of Work; evaluating performance; and certifying all invoices/vouchers for acceptance of the supplies or services furnished for payment.

(c) The COR does not have the authority to alter the contractor's obligations under the contract, and/or modify any of the expressed ter ms, conditions, specifications, or cost of the agreement. If as a result of technical discussions it is desirable to alter/change contractual obligations or the Scope of Work, the Contracting Officer shall issue such changes.

52.27-103-72 DOJ CONTRACTOR RESIDENCY REQUIREMENT BUREAU OF PRISONS (JUNE 2004)

For three of the five years immediately prior to submission of an offer/bid/quote, or prior to performance under a contract or commi tment, individuals or contractor employees providing services must have:

1. Legally resided in the United States (U.S.);

2. worked for the U.S. overseas in a Federal or military capacity; or

3. been a dependent of a Federal or military employee serving overseas.

If the individual is not a U.S. citizen, they must be from a country allied with the U.S. The following website provides current informa tion regarding allied countries: http://www.opm.gov/employ/html/citizen.htm By signing this contract or commitment document, or by commencing performance, the contractor agrees to this restriction.

[End of Clause]

FAO-0001 Bonds

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or suretie s acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Offi cer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows; a Performance Bond (Standa rd Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the o riginal contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $30,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selec ted alternatives (FAR 28.102-1(b)(1)):

15B61120B00000001 Page 11 of 30

(1) A Payment Bond;

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, pa yment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they cl aim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepar ed by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Sur ety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract l ocation, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and informat ion required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

FAO-0003 Required Insurance

See FAR 52.228-5, Insurance - Work on a Government Installation.

The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the

Schedule or elsewhere in the contract.

TYPE AMOUNT

(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000

The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and f or occupational disease with a minimum liability of $100,000.

(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:

PER ACCIDENT OR

OCCURRENCE FOR BODILY INJURY $500,000

This insurance shall include contractor's protective and contractual liability.

15B61120B00000001 Page 12 of 30

(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:

PER PERSON $200,000

PER OCCURRENCE FOR BODILY INJURY $500,000

PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000

FAO-0004 Pre-Construction Conference

(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, C ontroller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other inte rested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcon tractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.

Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered.

The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.

(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative fo r determination.

FAO-0005 Submittals

Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.

The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and gen eral practices.

(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous wor k related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.

(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specifications to the COR for tra nsmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.

(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the speci fications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.

(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any fur ther samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.

(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Appr oval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as i ntended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes

15B61120B00000001 Page 13 of 30 no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly funct ioning product or system.

15B61120B00000001 Page 14 of 30

Section 4 - Contract Clauses

Clauses By Reference

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

Clause Title Fill-ins (if applicable)

52.246-12 Inspection of Construction (Aug 1996)

52.222-3 Convict Labor (June 2003)

52.222-1 Notice to the Government of Labor Disputes (Feb 1997)

52.222-8 Payrolls and Basic Records (Aug 2018)

52.222-6 Construction Wage Rate Requirements (Aug 2018)

52.204-21 Basic Safeguarding of Covered Contractor Information Systems (June

2016)

52.222-7 Withholding of Funds (May 2014)

52.222-11 Subcontracts (Labor Standards) (May 2014)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(Jun 2020)

52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)

52.222-12 Contract Termination - Debarment (May 2014)

52.222-21 Prohibition of Segregated Facilities (Apr 2015)

52.204-2 Alt II Security Requirements (Aug 1996) - Alternate II (Apr 1984)

52.204-13 System for Award Management Maintenance (Oct 2018)

52.222-15 Certification of Eligibility (May 2014)

52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020)

52.222-10 Compliance with Copeland Act Requirements (Feb 1988)

52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (May 2014)

15B61120B00000001 Page 15 of 30

Clause Title Fill-ins (if applicable)

52.222-35 Equal Opportunity for Veterans (Jun 2020)

52.209-6 Protecting the Government's Interest When Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment (Jun

2020)

52.219-28 Post-Award Small Business Program Rerepresentation (May 2020)

52.219-6 Notice of Total Small Business Set-Aside (Mar 2020)

52.223-2 Affirmative Procurement of Biobased Products Under Service and

Construction Contracts (Sep 2013)

52.222-26 Equal Opportunity (Sept 2016)

52.222-14 Disputes Concerning Labor Standards (Feb 1988)

52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)

52.223-20 Aerosols (Jun 2016)

52.222-37 Employment Reports on Veterans (Jun 2020)

52.222-27 Affirmative Action Compliance Requirements for Construction (Apr

2015)

52.225-13 Restrictions on Certain Foreign Purchases (June 2008)

52.228-11 Pledges of Assets (Aug 2018)

52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and

Construction Contracts (Aug 2018)

52.229-3 Federal, State and Local Taxes (Feb 2013)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving

(Jun 2020)

52.227-1 Authorization and Consent (Jun 2020)

52.232-5 Payments under Fixed-Price Construction Contracts (May 2014)

52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991)

52.222-55 Minimum Wages Under Executive Order 13658 (Dec 2015)

52.228-2 Additional Bond Security (Oct 1997)

15B61120B00000001 Page 16 of 30

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement

(Jun 2020)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

(Dec 2013)

52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

52.222-50 Combating Trafficking in Persons (Jan 2019)

52.232-17 Interest (May 2014)

52.228-5 Insurance-Work on a Government Installation (Jan 1997)

52.233-3 Protest after Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.232-33 Payment by Electronic Funds Transfer-System for Award Management

(Oct 2018)

52.232-23 Assignment of Claims (May 2014)

52.223-15 Energy Efficiency in Energy-Consuming Products (May 2020)

52.236-7 Permits and Responsibilities (Nov 1991)

52.236-8 Other Contracts (Apr 1984)

52.236-10 Operations and Storage Areas (Apr 1984)

52.243-5 Changes and Changed Conditions (Apr 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (Apr 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984)

52.236-5 Material and Workmanship (Apr 1984)

52.236-6 Superintendence by the Contractor (Apr 1984)

52.236-17 Layout of Work (Apr 1984)

52.236-13 Accident Prevention (Nov 1991)

52.236-26 Preconstruction Conference (Feb 1995)

52.246-21 Warranty of Construction (Mar 1994)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

52.236-2 Differing Site Conditions (Apr 1984)

52.248-3 Value Engineering-Construction (Oct 2015)

15B61120B00000001 Page 17 of 30

52.236-14 Availability and Use of Utility Services (Apr 1984)

52.236-12 Cleaning Up (Apr 1984)

52.253-1 Computer Generated Forms (Jan 1991)

52.222-9 Apprentices and Trainees (July 2005)

52.244-6 Subcontracts for Commercial Items (Jun 2020)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short

Form) (Apr 1984)

52.242-14 Suspension of Work (Apr 1984)

52.236-11 Use and Possession Prior to Completion (Apr 1984)

FAO-0016 Equitable Adjustments: Waiver and Release of Claims

52.204-18 Commercial and Government Entity Code Maintenance (Jul 2016)

Clauses By Full Text

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 [Contracting Officer insert number] calendar d ays after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work re ady for use not later than 190 calendar days.* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calen dar date.

(End of clause)

52.211-12 Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $903.35 [Contracting Officer insert amount] for each calendar day of delay until the work is compl eted or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is com pleted. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.228-13 Alternative Payment Protections (July 2000)

(a) The Contractor…