Abstract Complete.pdf
PDF 28 KB Posted
- Attached to
- REPLACE BOILERS AT MCC SAN DIEGO
- Solicitation number
- 15B61021B00000002
About this file
This document contains an abstract of offers and related federal contract opportunity notice for replacing boilers at the Metropolitan Correctional Center in San Diego, California. The Federal Bureau of Prisons is soliciting firms to furnish all equipment, materials, and labor to demolish three existing steam boilers, two steam to domestic hot water heat exchangers, and one steam to heating hot water heat exchanger. New work will include installing three hot water boilers, one heating hot water to domestic hot water heat exchanger, a new domestic hot water storage tank, and temporary boilers and associated components to provide domestic hot water and heating during construction. The performance period is 378 calendar days from notice to proceed. This is a 100% small business set-aside for firms with a size standard of $16.5 million or less in the NAICS code 238220. The estimated value is between $1-5 million. The solicitation is available solely through the Contract Opportunities website and secure documents will require a SAM registration and MPIN. The response due date is not provided.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF
PAGES
4. ISSUING OFFICE
5. PROJECT TITLE
6. NUMBER OF AMENDMENTS ISSUED
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
SIGNATURE DATE SIGNED
7B. DESCRIPTION OF OFFERED ITEM 7C. EST.
QUANTITY
D.
UNIT
E. UNIT
PRICE
F. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
A. HIRED LABOR
B. REASONABLE CONTRACT
(Without Profit)
C. REASONABLE CONTRACT
(Including Profit)
9. OFFERS
NO. 1 NO. 2
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)
7A.
ITEM
NO.
FIELD ACQUISITION OFFICE
US ARMED FORCES RESERVE COMPLEX
346 MARINE FORCES DRIVE
GRAND PRAIRIE, TX 75051
MCC SAN DIEGO - REPLACE BOILERS
1 Replace Boilers JB1 0.00 1,922,100.001,922,100.00 1,650,000.00 1,650,000.00
15B61021B00000002 1 2
JEFF KERCHEVAL, CONTRACTING OFFICER
NBT Construction and Supply LLC Ahrens Mechanical
Bid Bond - 20% Bid Bond - 20%
00001,00002,00003 00001,00002,00003
JEFFREY KERCHEVAL Digitally signed by JEFFREY
KERCHEVAL
Date: 2021.03.24 14:32:44 -05'00'
03/24/202102/02/2021
03/24/2021
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER PAGE OF
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)2. PROJECT TITLE
NO.: NO.: NO.: NO.:
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
15B61021B00000002
MCC SAN DIEGO - REPLACE
BOILERS
Bid Bond - 20% Bid Bond - 20%
00001,00002,00003 00001,00002,00003
1 JB 1,991,737.00 1,991,737.00 1,845,000.00 1,845,000.00
2 2
3 4
DuWright Construction Inc. Spectrum Services Group, Inc.
File details come from the government source that posted it. Updated .