Abstract Complete.pdf

PDF 28 KB Posted

Attached to
REPLACE BOILERS AT MCC SAN DIEGO
Solicitation number
15B61021B00000002
Issued by

About this file

This document contains an abstract of offers and related federal contract opportunity notice for replacing boilers at the Metropolitan Correctional Center in San Diego, California. The Federal Bureau of Prisons is soliciting firms to furnish all equipment, materials, and labor to demolish three existing steam boilers, two steam to domestic hot water heat exchangers, and one steam to heating hot water heat exchanger. New work will include installing three hot water boilers, one heating hot water to domestic hot water heat exchanger, a new domestic hot water storage tank, and temporary boilers and associated components to provide domestic hot water and heating during construction. The performance period is 378 calendar days from notice to proceed. This is a 100% small business set-aside for firms with a size standard of $16.5 million or less in the NAICS code 238220. The estimated value is between $1-5 million. The solicitation is available solely through the Contract Opportunities website and secure documents will require a SAM registration and MPIN. The response due date is not provided.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF

PAGES

4. ISSUING OFFICE

5. PROJECT TITLE

6. NUMBER OF AMENDMENTS ISSUED

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

SIGNATURE DATE SIGNED

7B. DESCRIPTION OF OFFERED ITEM 7C. EST.

QUANTITY

D.

UNIT

E. UNIT

PRICE

F. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

8. GOVERNMENT ESTIMATE

(Check A, B or C and complete D, E, and F)

A. HIRED LABOR

B. REASONABLE CONTRACT

(Without Profit)

C. REASONABLE CONTRACT

(Including Profit)

9. OFFERS

NO. 1 NO. 2

A. OFFEROR

B. BID SECURITY (Type and amount)

C. AMENDMENTS ACKNOWLEDGED

A. OFFEROR

B. BID SECURITY (Type and amount)

C. AMENDMENTS ACKNOWLEDGED

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)

7A.

ITEM

NO.

FIELD ACQUISITION OFFICE

US ARMED FORCES RESERVE COMPLEX

346 MARINE FORCES DRIVE

GRAND PRAIRIE, TX 75051

MCC SAN DIEGO - REPLACE BOILERS

1 Replace Boilers JB1 0.00 1,922,100.001,922,100.00 1,650,000.00 1,650,000.00

15B61021B00000002 1 2

JEFF KERCHEVAL, CONTRACTING OFFICER

NBT Construction and Supply LLC Ahrens Mechanical

Bid Bond - 20% Bid Bond - 20%

00001,00002,00003 00001,00002,00003

JEFFREY KERCHEVAL Digitally signed by JEFFREY

KERCHEVAL

Date: 2021.03.24 14:32:44 -05'00'

03/24/202102/02/2021

03/24/2021

ABSTRACT OF OFFERS - CONSTRUCTION

CONTINUATION SHEET

1. SOLICITATION NUMBER PAGE OF

PAGES

INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.

4. OFFERS (Continued)2. PROJECT TITLE

NO.: NO.: NO.: NO.:

A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)

3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED

A.

ITEM

NO.

B.

ESTIMATED

QUANTITY

C.

UNIT D. UNIT

PRICE

E. ESTIMATED

AMOUNT

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

E. ESTIMATED

AMOUNT

D. UNIT

PRICE

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

OPTIONAL FORM 1419A (11-88)

15B61021B00000002

MCC SAN DIEGO - REPLACE

BOILERS

Bid Bond - 20% Bid Bond - 20%

00001,00002,00003 00001,00002,00003

1 JB 1,991,737.00 1,991,737.00 1,845,000.00 1,845,000.00

2 2

3 4

DuWright Construction Inc. Spectrum Services Group, Inc.

File details come from the government source that posted it. Updated .