Answer to Fire Alarm Questions.docx
DOCX document 14 KB Posted
- Attached to
- Installation of new fire alarm system
- Solicitation number
- 15B51822Q00000013
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) What is the sequence of operation that between the new fire alarm and the existing FCI fire alarm panel ? The new system will be monitor only with pull stations, Audio/Visual signaling and smoke/detection. New system will report to existing annunciation panels in FCI 1 Control Room Console.
2) What is the exact model number and brand of the existing system? Edwards EST-3
3) Is the existing system already set up with pre-programmed monitor points so that the new system could send a contact closure to trigger it in an alarm event if this is part of the operation sequence and if so, do they just want to monitor actual alarm conditions. Each new device on the new installation will need to report to the existing console, located in the FCI 1 Control Room. All devices will be required to report status (I.E. Alarm status , Trouble status, and location)
4) Is there a 24-hour manned location that A.I.C could provide a remote annunciator with full operational controls of the new fire alarm system in lieu of having to tie into the existing proprietary system. There is a 24-hour manned location , which is the FCI 1 Control Room. We want the new system connected to the existing due to
5) Is a bid bond required for this project? Bid Bonds are only required for bids over $150,000.
6) Is a performance and payment bond required for this project if awarded? Payment protection is covered by FAR Clause 52.228-13 on page 7 of the solicitation. There are multiple options, and they need to be provided within 10 days after contract award.
7) Is it possible to be given the Elevation of the highest ground level elevation and the lowest ditch level elevation where the boring will occur? We do not have the capabilities of measuring ground level elevations.
8) Can a drawing or sketch be offered that is to scale so we can get an accurate measurement on the Boring Linear Footage? See Item 9
9) If #8 is not possible, can we be given a linear footage to include and not exceed in our bid? The linear footage of bore is 1,000 lf but not to exceed 1,200 lf