This document is a Statement of Work (SOW) for a federal contract to replace the comfort heating boiler located in the Chapel building at the Federal Prison Camp in Bryan, Texas. The SOW outlines the scope of work, which includes replacing the existing boiler with a new non-condensing comfort heating boiler of like output, replacing flu piping, hot water pumps and motors, and other related equipment. The contractor must comply with all applicable local, state, and federal laws, obtain necessary permits, and provide training for Bureau of Prisons employees. The document also includes contractor security and working regulations, such as work hours, delivery and storage of materials, and security clearance requirements.

The related federal contract opportunity is a Request for Quotation (RFQ) for the Boiler Unit Replacement at the Federal Prison Camp in Bryan, Texas. The contract is a firm-fixed price, total small business set-aside with a NAICS code of 238220 and a small business size standard of $19.0 Million. The period of performance is 364 calendar days after receipt of award, with an expectation of supplies being received within 120 days. Quotes are due by 2:00 PM CST on September 18, 2024, and must be submitted electronically via email.

View the file

Other files for this federal contract opportunity

Other files attached to FPC BRYAN- BOILER REPLACEMENT, newest first.
File Type Posted
NCIC form.pdf PDF
Statement of Work1.docx DOCX document
Cover Letter Boiler 8-30-2024.docx DOCX document
15B50424Q00000001 RFQ BOILER.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Approved 12/5/2023 SCRO

STATEMENT OF WORK

REPLACE CHAPEL BOILER

FPC BRYAN - PROJECT 23Z5AR7

I. SPECIFICATIONS:

A. INTRODUCTION

The Federal Bureau of Prisons (FBOP), Federal Prison Camp located at 1100 Ursuline in Bryan, Texas, intends to make a single award to a responsible entity that will provide all necessary equipment, labor, materials, and incidentals to replace the comfort heating boiler located in the Chapel building. All manufacturers’ recommendations will be required to be implemented.

B. SCOPE OF WORK

Chapel Boiler Room

Replace the existing Bryan (model # CL 120-W-100-FDG) 1,200,000 BTU flex tube comfort heating boiler with a new non-condensing comfort heating boiler of like output. Replace all existing flu piping in accordance with the boiler manufacturer recommendations. Remove and replace two existing hot water pump and motor assemblies for hot water circulation throughout the chapel building. Replace all hot water pipe expansion joints, backflow prevention devices and butterfly valves located in the boiler room and add carbon monoxide monitoring inside the mechanical room. Carbon monoxide monitor shall be connected to boiler controls to automatically shut down boiler operations if carbon monoxide levels become unsafe. All work completed shall comply with all applicable local, state and federal laws.

B1. REFERNCE DOCUMENTS

Attached reference drawings/specifications are provided for work requirements and the Contractor’s benefit. Actual equipment installation and existing conditions may vary.

ATTACHMENT A – Existing Boiler ATTACHMENT B – Existing Boiler Side View ATTACHMENT C – Existing Inside Boiler Exhaust ATTACHMENT D – Existing boiler data plate ATTACHMENT E – Existing Boiler Connections A ATTACHMENT F – Existing Boiler Connections B ATTACHMENT G – Existing backflow ATTACHMENT H – Existing Gas Line ATTACHMENT I – Existing Carbon Monoxide Monitor ATTACHMENT J – Pump 1 Location ATTACHMENT K – Pump 2 Location ATTACHMENT L – Existing Boiler Roof Stack Location

C. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS

All installers/technicians shall be qualified and licensed to install, test, and certify the new boiler. Such certification must be verified in writing and submitted to the COR seven (7) days before the project starts.

All seismic zone requirements, environmental compliance, Life Safety, NFPA, ADA-ABA, and Federal, State and Local codes and regulations will be considered during all phases of this project.

Services and materials provided by the contractor will adhere to and shall be consistent with the most current industry standards, the Underwriters Laboratories (UL) and the General and the National Electric Code (NEC).

It is the contractor’s responsibility to obtain permitting, should it be required. Copies of all permits must be submitted to the COR upon receipt from local agency.

D. UTILITIES

The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.

E. TESTING AND ACCEPTANCE

The Contractor shall notify the COR two (2) days prior to the final system testing and certification so that arrangements can be made to have BOP required staff available to observe testing. A complete plan detailing test procedures must be submitted to the Contracting Officers Representative (COR) in advance for final check out and testing of the complete system.

F. HOUSEKEEPING AND MATERIAL DISPOSAL

The contractor awarded the contract will be responsible to ensure the premises are kept clean and free from accumulations of waste materials and rubbish at all times. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work. The Contractor shall be responsible to remove all debris and waste materials from the job site at FPC Bryan upon conclusion and acceptance of the project. These items must be disposed of in accordance with all Federal, State, and local laws. The Contractor is also responsible to conduct all structural repairs, patch walls, paint, repair ceiling etc., associated with the replacement of the Chapel boiler.

G. SUBMITTALS & TRAINING

Submittals:

1. The contractor shall provide written submittals to the COR describing recommended equipment within (15) days from receiving the Notice to proceed for approval.

2. All security clearance paperwork/documentation shall be submitted to the COR a minimum of (14) working day prior to the start of work (see below).

3. The Contractor shall provide to the COR three (3) copies of the Safety Data Sheets (SDS) on all materials and substances that may be used during the course of the project. In the event the material is not approved by the Safety Manager, it shall be the responsibility of the Contractor to locate and procure an alternative product.

4. For security and safety purposes, forty-eight (48) hour advance notice in writing, prior to disruption to the system must be given to the Contracting Officer and COR.

5. Provide complete narrative descriptions of all system operations.

6. The contractor shall provide an Installation Certification of the completed and tested systems that contains an affidavit signed by the contractor and manufacturer’s representative, notarized, certifying that the complete systems meet the contract requirements and is fully operational per the manufacturer's recommendations.

7. Any deviations from this Statement of Work will be considered a Change Order Request and must be authorized through the institution’s Contracting Officer prior to the implementation of the requested change.

8. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractors employees. Damage will be corrected and restored to previous condition at no cost to the Government.

9. It shall be the Contractor’s responsibility for obtaining all measurements and data requirements to comply with manufacturer’s installation recommendations. All installations must be in accordance with product manufacture’s recommendations.

Training:

Upon completion of the installation, testing, and acceptance by the Government, the contractor shall provide the COR a complete hardcopy printout of the system programming including schematics and ladder logic diagram, along with CD-ROM disk copies of the program. CD-ROM disks shall include all manufacturers’ software necessary to perform maintenance and adds. The contractor shall provide operation/maintenance manuals for each piece of equipment/system installed. One copy of any required licensed software and associated manuals shall also be supplied to the institution.

The contractor shall furnish manufacturer’s factory-certified training and provide system certification for two (2) Bureau of Prisons employees, thus enabling them to maintain and repair all equipment and systems. Training shall include operations and maintenance of the boiler control systems and boiler.

II. CONTRACTOR SECURITY/WORKING REGULATIONS

A. Work Hours:

Work Hours for the contractor are 8:00 AM to 3:00 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work and must be approved by the Warden. In the event of any equipment being replaced that would result in downtime of the normal orderly running of the institution, alternate work hours may be authorized in accordance with the time frame stated above.

Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight-hour work day. The Government assumes no responsibility to the Contractor nor to any of his subcontractors for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines.

Contractors should plan for a minimal amount of time accrued for security considerations, i.e., check-in screening, delay due to inmate movements, institution lock-down, institution emergencies, etc. In the event of an institution emergency, the Contractor will be instructed to secure all work, secure and stow all tools, equipment and materials, and the Contractor will be escorted out of the institution. Work will resume once the institution emergency passes.

B. Delivery of Materials:

All materials/equipment required for work on this project is required to be processed by the Contractor and coordinated with the institution COR for temporary storage.

Any related deliveries which are directly shipped to the contractor can be received between the hours of 8:00 a.m. to 2:00 p.m., Monday through Friday, excluding Federal Holidays. At no point will a Bureau of Prisons (BOP) staff member receive or sign for a delivery if the contractor or his representative is not present to verify and accept the delivery.

Under no circumstances will FPC Bryan or its staff be responsible for the acceptance of any Contractor or company deliveries. The contractor shall be responsible for providing their own means of loading and unloading contractor material or equipment.

The contractor shall not use the institution entry/driveway for the loading, unloading, or storage of any materials and equipment. The contractor will not impede/block the driveway at any time during or after the work shift.

C. Storage of Materials and Equipment:

All materials/tools shall be stored in a designated area mutually agreed upon between the COR and the contractor. The storage area will be a secure lockable gang box or similar, size to be determined by the contractor and the COR. If required, the contractor shall provide a securable, single point access storage container, such as a Job or Gang Box that will be left in the agreed upon storage area for the duration of the project. Size of the storage container will be determined by the contractor and the COR. The container will be secured using a padlock protocol with two locks to secure it. One shall be a contractor lock and the other lock provided by the institution. If necessary, a heavy duty chain provided by the contractor may be used to facilitate the locking requirement. All materials and equipment stored within the container will be maintained in a safe an orderly fashion

All tools will be inventoried prior to entering the institution and will be inventoried back in to ensure accurate accountability when exiting the institution at the end of each work day.

Materials cannot be stored at a height that would create a fall hazard. All tools will be inventoried prior to entering the Institution. At the start of each workday all tools will be inventoried out on a daily tool inventory sheet and at the end of the workday all tools will be inventoried back in to ensure accurate accountability of all tools at the end of each workday.

All contractor owned extension cords that will be used during the project, regardless of length, shall be in good condition with no broken outer Insulation. Extension cords are considered a “high risk” tool having a Federal Bureau of Prisons’ tool classification of Double A. All contractor owned extension cords used for this project will be required to exit the institution at the end of every workday for the duration of the project.

All contractor owned ladders approved for use within the institution, regardless of the size, shall be stored in a pre-determined area and secured to a stationary fixture with a heavy link chain and lock which would prevent removal.

D. Security Clearance/Contractor Badges:

The contractor shall provide the COR with all the necessary security clearance documents for all contractors and subcontractor employees accessing the institution and be security cleared for badging within 14 days of receiving the Notice to Proceed, as stated above. Security clearance documents will only be accepted from the prime contractor. If submitted by a sub-contractor, they will be rejected. It is the prime contractor’s responsibility to review security clearance submissions to ensure they are complete.

All contractors and their construction staff awarded the project will be required to attend a four (4) hour orientation and security procedures training. The contractors and any subcontract staff are required to attend. This training must be accomplished prior to any contract or subcontract employee being granted access to federal property to start work.

In the event a contractor or subcontractor employee cannot pass the security clearance process, it will be the contractor’s responsibility to provide another candidate. By law the BOP cannot, and will not, release any information to the contractor concerning the nature of why a contractors or subcontractor employee was not able to pass the security clearance process.

All contractors/subcontractors working at FPC Bryan will be issued and required to wear a picture ID/contractor badge provided by the institution. For security reasons, the badge will be worn in a visible manner as directed by the COR.

All contractors and subcontractor employees will provide a check list of all employees on site each day to the COR, verifying the number of workers on site each day and that all workers are approved to be on site.

E. Safety and Personal Protective Equipment:

All contractors and employees shall have and wear the required personal protective equipment (PPE) prescribed by industry standards at all times while on the job site. It is the responsibility of the contractor to provide all PPE equipment. All ladders regardless of the size shall be stored, and secured to a stationary fixture with a chain and lock in a predetermined area, in a way that they cannot be removed. If ladders are required, immediately consult with the COR to ensure that he or she can make timely notification to appropriate institution staff. All extension cords regardless of length shall be in good condition with no broken outer insulation and will be secured in a locked construction gang box. Should a system require Lock-out/Tag-out, the system will be required to have both Contractor and FPC Bryan locks on the isolation point to prevent shock. All Lock-out/Tag-out procedures will be in compliance with the institution Lock-out program.

F. Additional Considerations:

1. Contractors will NOT be allowed to bring cell phones, cameras or two way pagers into FPC Bryan. The Facilities Department maintains a digital camera that will be utilized by BOP staff to document the project work. The Contractor may request copies of these documentation photos for record keeping.

2. Contractor will be permitted to wear jeans in the institution, however, shorts, green or khaki-color clothing will not be allowed. The clothes will be proper and suitable for the services that are being provided.

3. Lunches will be consumed at the work site. Contractor shall ensure they have everything they need for their lunch when they check-in first thing in the morning.

4. Federal smoking policy on Federal property states that smoking is only allowed in outdoor designated areas. This policy will be strictly enforced.

END STATEMENT OF WORK

ATTACHMENT A – Existing Boiler

ATTACHMENT B – Existing Boiler Side View

ATTACHMENT C – Existing Inside Boiler Exhaust

ATTACHMENT D – Existing boiler data plate

ATTACHMENT E – Existing Boiler Connections A

ATTACHMENT F – Existing Boiler Connections B

ATTACHMENT G – Existing backflow

ATTACHMENT H – Existing Gas Line

ATTACHMENT I – Existing Carbon Monoxide Monitor

ATTACHMENT J – Pump 1 Location

ATTACHMENT K – Pump 2 Location

ATTACHMENT L – Existing Boiler Roof Stack Location image3.jpeg image4.jpeg image5.jpeg image6.jpeg image7.jpeg image8.jpeg image9.jpeg image10.jpeg image11.jpeg image12.jpeg image1.jpeg image2.jpeg image13.png