Meeting_min_PLC_door_Controls_FCI_11-5-2019.pdf

PDF 30 KB Posted

Attached to
Replace Door Controls
Solicitation number
15B40320Q0000001
Issued by

About this file

Meeting Minutes

View the file

Other files

File Type Posted
15B40320Q0000001__P00001.pdf PDF
PLC_QUESTIONS.pdf PDF
fbo_notice_PLC_CONTROLS.pdf PDF
NCIC_form_1.PDF PDF
WAGE_RATE_PLC_INSTALL.pdf PDF
Statement_of_Work_FCI_Englewood_Project_4C8C.pdf PDF
15B40320Q0000001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Justice

Federal Bureau of Prisons

Federal Correctional Institution FCI Englewood, CO 80123

November 5, 2019

MEMORANDUM FOR ALL INTERESTED PARTIES

THRU: R. Brown, Su~ntract Specialist

FROM:

SUBJECT:

R. Infant , Specialist

Pre-Bid Meeting Minutes for 15B40320Q0000001, New PLC Door Controls.

A preconstruction meeting for the above referenced solicitation was held on November 5, 2019 at 9:00 a.m.

Attendees:

Rachel Brown, Supervisory Contract Specialist, Bureau of Prisons Ty Wiegand, Communications Tech, Bureau of Prisons Rochelle Infante,. Contracting Specialist, Bureau of Prisons Troy Kessinger, Corvinus Group Blake Bretz, KUBL Group

Meeting Minutes

Ms. Brown opened up the meeting by advising the contractors that discussions during this meeting would.not alter or change the terms/conditions of the solicitation and that all changes will be made in writing via an amendment to the solicitation by her, ·the issuing contracting officer. Ms. Brown, notified the potential vendors that this would be a supply and install not a construction contract. Ms.

Brown also stated that Service Contract Wage Rates did apply to this contract.

Contractors were advised to read the solicitation in its entirety to ensure that all information is clear in order to ensure that proper proposals are submitted.

Ms. Brown went over the points listed in the agenda i.e. NCIC clearance requirements, Safety, the importance of the contractor meeting OSHA requirements, Medical emergencies, and availability of parking.

The meeting was on site and a walk through of the FCI control center and back gate area was conducted. Vendors stated that they did not need to go to the Trqining Center.

During the walk through of the site Mr. Wiegand showed potential contractors the current control boxes and stated that the project was for the replacement of the controls of up to 12 doors and some analog intercoms.

Potential vendors were reminded that any technical questions must be emailed to Ms. Brown so that responses can be posted publicly.

The meeting was concluded at 9:30 a.m.