OTV_23Z2AL9_ AddendumToSOW_RepairBoilers2-3_11152023_FAS.pdf

PDF 276 KB Posted

Attached to
FCI Otisville, NY - Boiler Repair 2 & 3
Solicitation number
15B21124PR000016
Issued by

About this file

This addendum to a statement of work concerns repairs to boilers 2 and 3 at the Federal Correctional Institution in Otisville, New York. The Bureau of Prisons seeks a contractor to perform repairs on boiler 3 to place it into service, after which the bureau will take boiler 2 offline for the contractor to complete repairs. The addendum provides revised language regarding the current operational status and observed issues with boilers 2 and 3. It also outlines responsibilities for the bureau to remove boiler 2 from service after boiler 3 repairs are finished, and responsibilities for the contractor to proceed with boiler 2 repairs thereafter. The related federal contract opportunity is solicitation number 15B21124PR000016 to repair boilers 2 and 3 at the Otisville facility.

View the file

Other files

File Type Posted
WageRatesFY24.pdf PDF
PICTURES.pdf PDF
OTV_23Z2AK9_SOW_Boiler2-3_10262023_FA_Approved.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM TO STATEMENT OF WORK (SOW)

REPAIR BOILERS 2 & 3

B&F PROJECT 23Z2AL9: EMG Repair Boilers 1, 2 & 3

FCI OTISVILLE

OTISVILLE, NEW YORK

November 15, 2023

The following changes are made to the SOW:

1. Page 2 of 6, Paragraph 1.01.D.1.a. is changed to read as follows:

Boiler is currently in service.

2. Page 2 of 6, Paragraph 1.01.D.1.b. is changed to read as follows:

Front and rear doors of boilers are closed.

3. Page 2 of 6, Paragraph 1.01.D.1.c. is changed to read as follows:

Boiler tubes showing signs of corrosion and fa gue. Mechanical boiler tube plugs installed in three boiler tubes for boiler to be put into service.

4. Page 2 of 6, Paragraph 1.01.D.1.d. is changed to read as follows:

Front intermediate door insula on patched where it had failed for boiler to be put into service.

5. Page 2 of 6, Paragraph 1.01.D.2.g. is removed.

Remove the following: Rear davit hinge bearings have failed.

6. Page 5 of 6, 2.02, FBOP RESPONSIBILITIES, add Paragraph 2.02.A.5. to read as follows:

FBOP will take Boiler 2 out of service a er Contractor completes all repairs to Boiler 3 and it is placed into service.

7. Page 6 of 6, 2.03 CONTRACTOR RESPONSIBILITIES, add Paragraph 2.03.B.9 to read as follows:

Contractor shall proceed with Boiler 2 repairs a er FBOP takes Boiler 2 out of service.

NERO APPROVAL:

FACILITIES ADMINISTRATOR: _______________________ DATE: ____________

MICHAEL C. BOND

INSTITUTION APPROVAL:

FACILITY MANAGER: _______________________ DATE: ____________

A. CHURCHILL

2023-11-15T12:00:17-0500
AARON CHURCHILL
2023-11-15T17:58:05-0500