This document contains a federal contract opportunity notice and related amendment and questions and answers. The Federal Bureau of Prisons is soliciting bids for a firm-fixed-price construction contract to provide a temporary food service kitchen at the Federal Correctional Complex in Petersburg, Virginia. The anticipated period of performance is 168 calendar days from issuance of the notice to proceed. The project scope includes connecting and routing new utilities, installing chain link security fencing and gates, removing and replacing failed asphalt pavement, and providing utility connections for temporary food service trailers furnished by the owner. The pre-solicitation notice provides details on the location, estimated budget range of $1,000,000 to $5,000,000, NAICS code 236220 with a $39.5 million small business size standard, and plans to issue the solicitation as a 100% small business set-aside on or around January 3, 2020 solely through beta.sam.gov. Amendment 00003 incorporates contractor questions and responses into the solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
00003
BFAO
Jim D. Seratt. Contracting Officer
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 00003 is hereby issued to incorporate the following document into the solicitation:
1) Contractor Questions and BOP Responses (attachment 1).[End of amendment 00003]
BPEX
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
Federal Bureau of Prisons FCC Petersburg 1060 River Road Hopewell, VA 23860
RP# 0095-20
15B11420B00000001
1C6X
1 1
01/24/2020
01/03/2020
IFB15B11420B00000001 – Temporary Food Service Kitchen – FCC Petersburg Questions and Answers – 01/24/2020
Question 1:
In looking through the prints, I see fencing for the laydown area on the overall site plan and around the temporary food service area. As I continue to look at the overall plan, I see some of the permanent security fence that is printed in darker ink than other fence lines in the print which in most cases in the prints I look at means new fence.
I just need to verify whether it truly represents new fence or if it is existing fence.
BOP Response:
Clarification: The fence at the laydown area is new, by Contractor.
Refer to Keynote 5 on Sheet C1.0. The fence around the area that will contain the temporary kitchen trailers, identified by Keynote 4 on Sheet C2.1, is also new, by Contractor. Additional information for these fences is on other drawings in the set. There are no other new fences included in the project.
Question 2:
Drawing E0.3 shows underground conduit run in an undisturbed area outside the area of demolition from the powerhouse roof penetration in route to UPB‐3. Please provide direction on how the conduit is to be installed passing through the fencing and across the road.
BOP Response:
Clarification: Underground conduit is to be run in new concrete duct bank, per Detail 5 on Sheet E3.1, with pull boxes per Detail 3 on Sheet E3.1. Where new utilities run through existing paved areas, remove and repair paving as shown in Detail 1 on Sheet C6.2.
Question 3:
Are we to remove a section of the fence to provide the underground conduit?
BOP Response:
Clarification: It is Contractor’s option to remove and repair a section of fence, or to run the new utility under the existing fence. Any temporary openings in existing fencing require written request to the Owner, not less than 5 days before cutting. No fence is to be cut without the Owner’s written approval.
Question 4:
Are we to close the road and include the road patch?
BOP Response:
Clarification: Yes. Refer to Question 2 above.