(x)

15-223-SOL-00055

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

JEFFERSON AR 72079

HFT-323

3900 NCTR ROAD

Nick Sartain OAGS - Field Operations Branch

FDA/OO/OFBA/OAGS/DAP

HFT-323

JEFFERSON AR 72079

3900 NCTR ROAD

OAGS - Field Operations Branch

FDA/OO/OFBA/OAGS/DAP

07/22/20152

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/30/2015

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to provide answers to questions submitted.

1. Would you please clarify whether the submittal of proposed hourly rates (listed in

Paragraph B-3. Page 8 of 39) for all 5 years of the contract are indeed being requested and are an expected or required component of the offeror's submittal package? This would mean that these rates fall under submittal item 2 (any supplemental data which is pertinent to this acquisition.).

Response: The proposed labor categories and hourly rates for all 5 years are required with the offeror's proposal. The hourly rates shall be completely separate from SF-330 submissions and no pricing information should be included with the SF-330. Keep in mind

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

15-223-SOL-00055/2

that the labor categories listed in Section B-3 is not an exhaustive list but rather a guide to what disciples may be needed for this contract.

2. I am in the process of collecting and preparing the final response for our office. In the Solicitation, it calls for the submission of

"the SF330 (submitted for prime firm and each key sub consultant)". What I am trying to ascertain is if the Government desires one consolidated SF

330 with information, resumes, etc. (Parts 1 and

2) for all team members or whether each Prime and

Sub Consultant should submit a separate complete

SF330 placed together in one booklet?

Response: The offeror should submit a consolidated SF-330 with information, resumes, etc. for all team members.

3. The solicitation calls for the submission of "four (4) original (hard copy) and one (1) electronic copy on CD". Of the four original copies, is each required to have an original

"wet" signature or can we submit forms which contain a scanned original signature?

Response: Four original "wet" signatures are required.

4. Is there a specific location where you desire the Key Personnel to be identified? We were considering placing the Key Personnel listing on the Organizational Chart and identifying them on their individual resume. Will this be sufficient?

Response: Include Key Personnel information in

Section E and G of the SF-330. Including key personnel in the organization chart and identifying on each individual resume is acceptable.

5. Is there a minimum or maximum amount of PPQs required for the prime contractor?

Response: The Government needs to receive a minimum of one completed questionnaire by the offeror's references in order for the Government to complete the recent and relevant past performance evaluation. Receiving only one completed PPQ form may negatively affect the

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

15-223-SOL-00055/2

offeror's past performance evaluation.

6. Is NCTR to be included for PPQs as a past client? If the prime contractor has relevant past projects with NCTR does the prime contractor need to submit the PPQ to NCTR for an evaluation per project?

Response: Yes, an evaluation should be submitted for past projects at NCTR at either the contract or task order level.

7. There are six title positions listed in G-3, is the list meant to be considered exhaustive?

Response: This is not an exhaustive list but rather what the Government believes are key personnel essential for work performance for this contract. An offeror may propose more key personnel than those listed in G-3 which correlates to the firm's SF-330 submission.

Last day for questions is COB July 23, 2015.