- Construction of Three Water Wells Federal contract opportunity
- Solicitation number
- 14-235-SOL-00009
About this file
Solicitation Body
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attach__2_F_ _M_Goals.pdf | ||
| Attach__3_Submittals.pdf | ||
| SF_1442.pdf | ||
| Attach__1_Wages.pdf | ||
| Attach__4_Exhibits.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
14-235-SOL-00009 Page 4 of 65
SECTION B
PRICE SCHEDULE
T. McDonald, R. Mason, and Grindstone Rancheria Shasta, Tehama, and Glenn Counties
Project CA 11-B71
The following Price Schedule is based on estimated quantities required to meet the specifications. The total extended prices shall be used for quote evaluation purposes only. The actual amount to be paid by the Government under the contract shall be computed on the actual quantities installed at the unit prices awarded.
ITEM DESCRIPTION QTY UNIT
UNIT
PRICE
TOTAL
PRICE
1 Mob./Demob. - TP 02670
50-100 Mile Radius from Redding, CA 3 EA
2 Well Drilling (6" Casing) - TP 02670 760 FT
3 Well Grouting - TP 02670 90 FT
4 6" Steel Well Casing - TP 02670 760 FT
5 6" Perforated Steel Well Casing - TP 02670 40 FT
6 Filter Packing - TP 02670 100 FT
7 Well Development - TP 02670 6 HR
8 Test Pumping - TP 02670
A. 15 gpm to 50 gpm 16 HR
B. Recovery Measurements 8 HR
9 Well Disinfection/Water Analysis - TP 02670 2 EA
10 Pitless Adapter - TP 02670 2 EA
11 Submersible Pump - TP 15450
14-235-SOL-00009 Page 4 of 65
14-235-SOL-00009 Page 5 of 65
1 Hp 1 EA
12 1-1/4 Inch Sch. 120 PVC
A. Drop Pipe/Sub. Cable - TP 15450
B. With #12 Wire 460 FT
13 Well House Building (4' x 6') - TP 15450 1 LS
14 Pressure System - TP 15450 1 LS
15 Water Service Line & Valve - TP 15450
A. 1 1/4 inch - PE 160 FT
B. 1 inch - PE 5 FT
16 Frost Free Yard Hydrant - TP 15450 1 EA
17 Buried Electrical Cables - TP 16100
With #12 Wires 250 FT
18 Permits and/or Other Fees 2 EA **
** Reimbursed at actual cost
TOTAL
14-235-SOL-00009 Page 5 of 65
14-235-SOL-00009 Page 6 of 65
SECTION C
SPECIAL PROVISIONS
C.1 SCOPE OF WORK
The work to be done under this contract consists of furnishing all labor, materials, equipment, and supervision necessary to construct individual water wells, individual water systems and other required appurtenances in accordance with the attached drawings and specifications.
Work is to be performed at or near Indian residences located in Shasta, Tehama, and Glenn Counties, California. Two water well systems, and one test well will be installed.
The individual water wells will consist of a drilled and cased well with sanitary seal, a submersible well pump, drop pipe, water service line to the house, a pressure tank and well controls. The test well consists of a drilled and cased well, pump testing, and capping.
C.2 SITE CONDITIONS
The Contractor shall determine actual site conditions with regard to surface vegetation and other miscellaneous obstacles to construction. The Contractor shall perform, at no additional cost, all necessary clearing, grubbing, and disposal of these and other obstacles in order to do work required by the contract.
Locations, materials, and sizes of any utilities shown are approximate only and are not meant to be a complete representation of all utilities actually present. The Contractor shall determine exact locations and details from the responsible utility authority.
C.3 CONTRACT DOCUMENTS
A maximum of 3 sets of contract drawings and specifications will be furnished without charge to the Contractor at award of this contract, except applicable publications incorporated by reference which will be furnished on request at the cost of reproduction.
C.4 DAYS OF WORK
Normal work days are Monday through Friday with 10 work hours allowed per day. The Contractor shall submit the intended work schedule to the Project Engineer for approval.
Construction work shall not be normally permitted on Saturdays, Sundays, or Federal holidays.
The Contractor may submit a written request to the Project Engineer for permission to work on any Saturday, Sunday, Federal holiday or in excess of 10 hours per day. Written approval from the Contracting Officer must be obtained before the Contractor may work on any such day.
14-235-SOL-00009 Page 6 of 65
14-235-SOL-00009 Page 7 of 65
C.5 LAWS AND PERMITS AFFECTING WORK
The Contractor shall at all times observe and comply with Federal, State, City, and County laws, Tribal ordinances and regulations which in any manner affect the conduct of the work; and all such orders and decrees as exist at the present and which may be enacted later by legislative bodies or tribunals having legal jurisdiction or authority over the work. All other required permits, certificates and licenses shall be obtained by and at the expense of the Contractor. No pleas of misunderstanding or ignorance thereof will be considered. The Contractor shall be wholly responsible for any claim or liability arising from or based on the violation of any such law, ordinance, regulation, order or decree.
C.6 RIGHTS-OF-WAY
The Government shall obtain all rights-of-way and easements necessary to install facilities located specifically by the plans and specifications.
C.7 MAINTENANCE OF UTILITIES AND SITE FACILITIES
The Contractor is responsible to determine the exact location of any and all utilities not specifically located on the plans and to protect them from damage during construction. Should any utility be damaged or disturbed, the Contractor shall immediately notify the Project Engineer and the owner of the damaged utility. Any and all damage that results from work under the contract shall be promptly repaired at the expense of the Contractor.
During the progress of work, the Contractor shall protect all existing vegetation, structures, sidewalks, streets, mailboxes, ditches, culverts, signposts, fences, driveways, and similar items.
If the Contractor must remove or disturb these facilities, provision shall be made to maintain a temporary facility serving the same purpose as that which it was intended to replace. Destruction of vegetation shall be kept to a minimum. Upon completion of the work, the Contractor shall restore all such facilities to a condition at least equal to that existing prior to construction. The Contractor shall not obstruct access to the site.
The Contractor shall perform his work at all times in a manner to ensure minimal obstruction to traffic and minimal inconvenience to the general public.
C.8 CONTRACT SUBMITTAL REQUIREMENTS
The Contractor shall furnish material submittals, design submittals, shop drawings, test reports, and as-built drawings in accordance with the requirements detailed in the Contract Submittal Requirements section.
C.9 CLEANUP AND FINISH GRADING
The Contractor shall restore all areas disturbed by construction to a condition at least equal to that existing prior to construction. Excess construction materials, equipment, tools, waste excavation, and rubbish shall be removed. Excavated areas shall be finish graded to provide
14-235-SOL-00009 Page 7 of 65
14-235-SOL-00009 Page 8 of 65 drainage as required by the drawings and specifications, or in the absence of specific requirements, to provide drainage away from the facilities constructed and to provide drainage away from excavated areas and installed facilities. Where a lawn is disturbed, the Contractor shall place a generous amount of grass seed to the disturbed area following final grading.
C.10 MEASUREMENT AND PAYMENT
As the line item quantities are estimates, the Contractor will be paid full compensation based upon the actual quantities utilized/completed and verified by the Project Engineer. The price paid for the completed item of work shall include full compensation for furnishing all labor, materials, tools, equipment, and performing all work required by the provisions of the contract to furnish and install the items of work, completed in place. In all cases, the finished product shall be a complete, operational system or component. The price for the completed item of work shall also include all applicable state and local sales or other taxes.
C.11 TECHNICAL PROVISIONS
Section Number Title Page
02110 Site Clearing 8
02200 Excavating, Trenching, and Backfilling 10
02670 Water Wells 19
03300 Cast-in-place Concrete 29
15450 Individual Water System 31
16100 Individual Electrical Requirements 39
14-235-SOL-00009 Page 8 of 65
14-235-SOL-00009 Page 9 of 65
SECTION 02110
SITE CLEARING
PART 1 – GENERAL
1.1 SECTION INCLUDES
A. This section includes protection of facilities, clearing site of incidental surface debris, grass, trees, and other plant life in preparation for site or excavation work.
1.2 UNIT PRICE - MEASUREMENT AND PAYMENT
A. There is no separate payment for work under this section. Merge work required with pay items defined within the Measurement and Payment portion of other Sections of this contract.
1.3 RELATED SECTIONS
A. Section 02200 - Excavating, Trenching and Backfilling
PART 2 – PRODUCTS
NONE
PART 3 – EXECUTION
3.1 PROTECTION
A. Locate, identify, and protect existing facilities (remaining), from damage.
B. Identify and protect trees, plant growth, and features designated to remain as final landscaping.
C. Protect bench marks from damage or displacement.
3.2 CLEARING
A. Clear only those areas required for access to site and execution of Work.
B. Remove structures and debris per drawings.
14-235-SOL-00009 Page 9 of 65
14-235-SOL-00009 Page 10 of 65
3.3 REMOVAL
A. Remove brush, trees, and other debris and dispose of off-site.
3.4 TOPSOIL EXCAVATION
A. Excavate topsoil from areas to be further excavated or re-graded.
B. Stockpile topsoil in designated area.
1. Protect from erosion.
2. Remove excess topsoil from site.
END OF SECTION 02110
14-235-SOL-00009 Page 10 of 65
14-235-SOL-00009 Page 11 of 65
SECTION 02200
EXCAVATING, TRENCHING AND BACKFILLING
A. This Section includes regulatory requirements, protection, imported pipe embedment, excavation, backfilling, compaction, quality control, and restoration.
A. Work required under this section shall be merged with pay item defined within the Measurement and Payment portion of other sections of this contract. Imported Pipe Embedment, Imported Structural Fill and Cement Slurry Fill are exceptions.
B. Imported Pipe Embedment: Paid by the cubic yard, measured to the nearest 0.1 yd3. Includes delivery, protection, placement, compaction of imported pipe embedment. Quantity of embedment measured for payment shall not exceed the quantity derived from calculating compacted, in-place volume, as shown on plans, drawings or specifications.
C. Imported Structural Fill: Paid by the cubic yard, measured to the nearest 0.1 yd3.
Includes delivery, protection, placement, compaction of imported structural fill.
Quantity of fill measured for payment shall not exceed the quantity derived from calculating compacted, in-place volume, as shown on plans, drawings or specifications.
D. Cement Slurry Fill: Paid by the cubic yard, measured to the nearest 0.1 yd3.
Includes delivery, protection and placement of concrete slurry fill. Quantity of fill measured for payment shall not exceed the quantity derived from calculating, in-place volume, as shown on plans, drawings or specifications.
A. Section 02110 – Site Clearing
B. Section 15450 – Individual Water System
1.4 REFERENCES
A. ASTM D698 - Test Methods for Moisture-Density Relations of Soils and Soil-Aggregate Mixtures, Using 5.5 lb (2.5 Kg) Rammer and 12 inch (300 mm) Drop.
14-235-SOL-00009 Page 11 of 65
14-235-SOL-00009 Page 12 of 65
B. ASTM D1556 - Test Method for Density of Soil in Place by the Sand-Cone
Method.
C. ASTM D1557 - Test Methods for Moisture-Density Relations of Soils and
Soil-Aggregate Mixtures Using 10 lb (4.5 Kg) Rammer and 18 inch (450 mm) Drop.
D. ASTM D2922 - Test Methods for Density of Soil and Soil-Aggregate in Place by
Nuclear Methods (Shallow Depth).
E. ASTM D3017 - Test Methods for Moisture Content of Soil and Soil-Aggregate
Mixtures.
F. ASTM C136 - Method for Sieve Analysis of Fine and Coarse Aggregates.
G. ASTM D2321 - Recommended Practice for Underground Installation of Flexible
Thermoplastic Sewer Pipe.
H. State of California, Department of Transportation, Latest Edition of the Standard
Specifications.
1.5 REGULATORY REQUIREMENTS
A. Contractor to obtain permits from authorities prior to construction. Contractor to comply with the requirements of the permits.
B. In accordance with the requirements of Section 6705 of the Labor Code of the
State of California, submit a detailed plan to the Engineer before excavation, showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of any trench or trenches 5 feet or more in depth.
C. Submit the permits and excavation plan to the Project Engineer prior to start of excavation.
1.6 DEFINITIONS
A. Utility: Any buried pipe, duct, conduit, or cable.
B. Structure: Foundation, slab, manhole, septic tank, cleanout, catch basin, or culvert.
C. Solid Rock: Large continuous masses of igneous, metamorphic, or sedimentary rock, which in the opinion of the Project Engineer cannot be excavated without drilling and blasting.
14-235-SOL-00009 Page 12 of 65
14-235-SOL-00009 Page 13 of 65
D. Loose Rock: Boulders and other detached stones, with a minimum volume of 1/2 cubic yard.
1.7 FIELD MEASUREMENTS
A. Verify that survey benchmarks, control points, and intended elevations are as shown on drawings.
1.8 PROTECTION
A. Barricade open excavations.
B. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.
C. Provide safe conditions for workers and passers-by.
2.1 IMPORTED PIPE EMBEDMENT
A. Use crushed stone or gravel that is free of shale, clay, friable material, and debris.
Grade in accordance with ASTM C136, within the following limits:
Sieve Size Percent Passing 1 in 100 3/4 in 90 to 100 3/8 in 20 to 55
no. 4 0 to 10
no. 8 0 to 5
2.2 IMPORTED STRUCTURAL FILL
A. Use imported soil (if required) that has angular fragments and a low expansion index (less than 30 per ASTM D 4829). Use imported fill that complies with the requirements of Caltrans Class 3 Aggregate Subbase:
3 in 100 2 in 90 to 100
no. 4 50 to 100
no. 200 15 to 40
14-235-SOL-00009 Page 13 of 65
14-235-SOL-00009 Page 14 of 65
2.3 DRAINAGE ROCK
2 in 100 ¾ in 35 to 70
no. 4 0 to 5
2.4 CEMENT SLURRY FILL
A. Slurry cement backfill shall consist of a fluid, workable mixture of aggregate, cement and water that will flow without segregation of the aggregate while being placed.
B. Water used for mixture shall be free from oil, salts and other impurities which would have an adverse effect on the quality of the backfill material.
C. Not less than 188 lbs of cement shall be used for each cubic yard of material produced.
D. The aggregate shall be commercial quality concrete sand or material meeting the following gradation:
1 1/2 “ 100 1” 80 to 100 3/4” 60 to 100 3/8” 50 to 100 No. 4 40 to 80 No. 100 10 to 40
3.1 PREPARATION
A. Notify Underground Service Alert (800) 227-2600 in Northern and Central California and (800) 422-4133 in Southern California prior to excavation.
Comply with their notice requirements.
B. Identify required lines, levels, contours, and datum locations.
C. Protect plant life, lawns, rock outcropping, and other features remaining as final landscaping.
D. Protect benchmarks, existing structures, fences, and paving from excavating equipment and vehicular traffic.
14-235-SOL-00009 Page 14 of 65
14-235-SOL-00009 Page 15 of 65
E. Maintain and protect utilities and structures which are to remain.
3.2 EXCAVATION
A. Use open cut method on all excavation unless otherwise shown on the drawings, required by permit, or approved in writing by the Project Engineer.
B. Stockpile excavated material in designated area on site, and remove excess material from site.
C. Grade top perimeter of excavation to prevent surface water from entering.
3.3 CLASSIFICATION OF EXCAVATION
A. All excavation with equipment commonly used in the industry is classified as common excavation.
B. All material drilled or blasted for removal is classified as rock excavation. All rock excavation must be approved by the Project Engineer. In addition, the Project Engineer prior to rock excavation to determine pay measurement.
3.4 TRENCH EXCAVATION
A. Cut trenches sufficiently wide to enable installation and inspection. Remove water or materials that interfere with work.
B. Maintain trench sides as vertical as possible--between 12 inches and 24 inches wider than the outside diameter of the pipe barrel--below pipe level.
C. Excavate trench width above the pipe as wide as necessary for shoring, sheeting, and installation.
D. Center trench excavation on pipe alignment for a minimum clearance of 6 inches on each side of the pipe.
E. Hand trim for bell and spigot pipe joints. Remove loose matter.
F. Restore over-excavated areas. If the trench bottom is over-excavated below the intended grade, fill over-excavation with imported pipe embedment and compact to density equivalent to the in situ material.
G. Remove lumped subsoil, boulders, and rock up to ½ yd3 (measured by volume).
14-235-SOL-00009 Page 15 of 65
14-235-SOL-00009 Page 16 of 65
H. Excavate for additional trench depth when soil prevents adequate pipe support.
Refill addition with imported pipe embedment. Remove large rock, boulders, and large stones to provide 3 inches of soil cushion on all sides of the pipe and pipe accessories.
I. Length of trench that may be left open at any one time is 100 yards. Do not leave trench open overnight.
J. Stockpile excavated material in designated area on site, and remove excess material from site.
3.5 STRUCTURE EXCAVATION
A. Excavate for structures down to the levels indicated on the drawings. Excavate as large as necessary to accommodate the work forms. Comply with all safety regulations.
B. Excavate a sufficient distance from walls and footings to provide forming except where concrete for walls or footings is directly against excavated surfaces.
C. Do not excavate below depths indicated in the drawings. Restore over-excavated areas to proper elevation by filling with imported structural fill. Do not interfere with 45 degree bearing splay of foundations.
D. Hand trim the bottom of the excavation to prevent disturbing the soil below the required depth.
3.6 BACKFILLING
A. Use care to prevent disturbance or damage to utilities or structures in trench.
B. Maintain optimum moisture content to attain required compaction density.
C. Remove surplus fill materials from site.
D. Leave fill material stockpile areas free of excess fill materials.
3.7 TRENCH BACKFILLING
A. Use excavated soil as embedment unless Project Engineer determines it unsuitable. Unsuitable material is defined as incapable of being compacted to specified density with optimum moisture content, solid or loose rock, lump material larger than 1 inch, organic matter, or debris.
14-235-SOL-00009 Page 16 of 65
14-235-SOL-00009 Page 17 of 65
B. Use excavated soil as final backfill unless Project Engineer determines it unsuitable. Unsuitable final backfill material is solid or loose rock larger than 6 inches or lumps larger than 3 inches. Do not use organic matter or debris.
C. Backfill pipe embedment material in uniform layers on all sides of the pipe in lifts not to exceed 6 inches.
D. Use the following methods when placing final backfill material unless otherwise required by permits or authority.
Compact Not to Exceed (In loose measure) Roadways 6 inches thick Rights-of-way and outside roadway 12 inches thick Unimproved surfaces 24 inches thick
3.8 STRUCTURE BACKFILLING
A. Place structure fill material in uniform layers on all sides of the structure 6 inches thick.
B. Do not fill structure material until the structure footing or other portions of the structure have been inspected
C. Use excavated soil as final backfill material unless Project Engineer determines it unsuitable. Unsuitable final backfill material is solid or loose rock larger than 6 inches or lumps larger than 3 inches. Do not use organic matter or debris.
3.9 CEMENT SLURRY BACKFILLING
A. Maintain a minimum of 6 inches clear distance between the outside of pipe and the side of the excavation for pipes 42” in diameter and smaller.
B. Compacted earth plugs or other suitable system shall be placed as the ends of the trench to receive slurry backfill to completely contain the slurry in the trench.
C. Place cement within 1 hour after mixing.
D. Place in a uniform manner that will prevent voids in, or segregation of, the backfill, and will not float or shift the pipe.
E. Backfilling over or placing any material over the slurry cement backfill shall not commence until 4 hours after the slurry has been placed, except that when concrete sand is used for the aggregate and the in-place material is free draining, back filling may commence as soon as the surface water is gone.
14-235-SOL-00009 Page 17 of 65
14-235-SOL-00009 Page 18 of 65
F. Cement Slurry Backfill shall not be used where it will be in contact with aluminum and aluminum coated materials.
3.10 COMPACTION
A. Compact final backfill to the percentage of maximum density determined by ASTM D1557 unless otherwise specified by permit or authority.
Percent of Maximum Density Initial Final
Location Bedding Haunching Backfill Backfill
Roadways, Improved Surfaces 90 90 95 95
Roadway Rights-of-Way Outside of Roadway 90 90 90 90 Prism
Unimproved Surfaces, Fields, Etc. 90 90 80 80
Backfill Around Structures 95 95 95 95
3.11 FIELD QUALITY CONTROL
A. The Project Engineer may acquire the services of a certified soils testing laboratory to perform baseline Modified Proctor density tests in accordance with ASTM D1557 or latest revision:
1. Tests to be performed at locations specified by Project Engineer.
2. Test results from tests prior to construction will be made available to the contractor.
3. Testing is not at the contractor’s expense unless a compaction test has failed.
B. Compaction testing will be determined at the Project Engineer's discretion.
C. If work does not meet specified requirements, remove, replace, and retest. All re-testing is at the contractor’s expense.
14-235-SOL-00009 Page 18 of 65
14-235-SOL-00009 Page 19 of 65
3.12 PROTECTION OF FINISHED WORK
A. If vehicular traffic has altered finished work, reshape and re-compact fills.
3.13 SIDEWALK, CURB AND GUTTER RESTORATION:
A. Restore the all sidewalks, curbs, and gutters to their original condition. Comply with the standards and construction requirements of the local authority.
B. Machine compact backfill under the sidewalk as follows:
1. Cut the existing curb or sidewalk to a neat line.
2. Match the depth of base course material with that present under adjacent curbs or sidewalks.
3. Match to the existing concrete walk in width, thickness, slope, and finish, but not less than 4 inches in thickness.
4. Use wire mesh reinforcement; 6 inch by 6 inch.
END OF SECTION 02200
14-235-SOL-00009 Page 19 of 65
14-235-SOL-00009 Page 20 of 65
SECTION 02670
WATER WELLS
A. General and Performance Requirements
B. Drilling and well construction
C. Test pumping
D. Well disinfection and water analyses
A. MOBILIZATION AND DEMOBILIZATION is paid by the unit as specified in the bid schedule, and includes: Site clearing and access, all set-up, take-down, and transportation costs of drilling equipment to and from each well site, test hole or well deepening site. Multiple drilling attempts on the same site will not constitute a new unit.
B. WELL DRILLING is paid by the vertical foot of well depth and includes:
Drilling, formation sampling, and related items not specifically paid for in other bid items.
C. WELL GROUTING is paid by the vertical foot and includes: Materials, placement of grout in the annular space between the well casing, and drilled hole.
D. STEEL WELL CASING is paid by the vertical foot of casing depth and includes:
Casing, drive shoes, and other incidentals required for complete installation. No payment shall be made for surface casing of a larger diameter used as a temporary construction aid.
E. PVC WELL CASING is paid by the vertical foot of casing depth and includes:
PVC casing, connection to PVC slotted casing if required and other incidentals required for complete installation.
F. PERFORATED STEEL CASING is paid by the vertical foot of slotted casing installed as stated in the bid schedule and includes: Slotted casing and other incidentals required for a complete installation.
14-235-SOL-00009 Page 20 of 65
14-235-SOL-00009 Page 21 of 65
G. STAINLESS STEEL WELL SCREEN is paid by the vertical foot of screen length and includes: Screen, sieve analysis, seals, couplings, riser pipe and other incidentals required for installation of the well screen.
H. PVC SLOTTED CASING is paid by the vertical foot of slotted casing installed as stated in the bid schedule and includes: Slotted casing, connection to PVC casing and other incidentals required for a complete installation.
I. FILTER PACKING is paid by the vertical foot as stated in the bid schedule and includes: Underreaming, filter material, placement of filter material in the annular space between the well screen or casing and the drilled hole, and other related work.
J. WELL DEVELOPMENT BY SURGING is paid by the hour as stated in the bid schedule and if approved by the Project Engineer. Time required for hauling water, rigging up, running tools, and other preparatory and disassembly work is not included in the basis for payment. Neither bailing nor pumping will be considered development.
K. TEST PUMPING is paid by the hour and includes: All necessary equipment, tools, labor, measuring instruments, pumping equipment complete with ample power source, controls and appurtenances, recovery measurements, and discharge piping.
L. WELL DISINFECTION AND WATER ANALYSES is paid by the unit and includes: Disinfection, supplies, labor, equipment, sampling, laboratory fees, and incidentals.
M. STANDBY TIME is paid by the hour as stated in the bid schedule for time contractor is delayed by the Indian Health Service and will only qualify for payment if proper notification to the Project Engineer has been given. (This Specification 3.3.A) Standby time will not be paid for contractor caused delays such as maintenance or failure of equipment.
N. WELL ABANDONMENT is paid by the cubic yard as stated in the bid schedule and includes demolition of above grade structures as specified on the drawings, all necessary materials, equipment, tools, labor, and other related work necessary to complete the well abandonment in accordance with state or locally applicable codes.
O. PITLESS UNIT is paid by the unit as stated in the bid schedule and includes all necessary equipment, tools, labor, shall also include sanitary well cap and related work necessary for the unit installation. Community wells shall include a screened vent.
14-235-SOL-00009 Page 21 of 65
14-235-SOL-00009 Page 22 of 65
P. PITLESS ADAPTER is paid by the unit as stated in the bid schedule and includes all necessary equipment, tools, labor, shall also include sanitary well cap and related work necessary for the adapter installation. Community wells shall include a screened vent.
A. 02110 - Site Clearing
B. 15450 – Individual Water System
A. AWWA A100 - Standard for Water Wells.
B. AWWA B301 - Standard for Liquid Chlorine.
C. California Well Standards
1.5 SYSTEM DESCRIPTION
A. Water well with the following characteristics:
1. The well shall be drilled by conventional mud rotary, air rotary, or down-the hole method. Equipment used shall be in good condition and capable of drilling to a depth of 500 feet.
2. Drill cased well at locations staked by the Project Engineer or as shown in the drawings.
3. Drill no deeper than directed by the Project Engineer. If a satisfactory yield is obtained at a lesser depth, the drilling shall be terminated and the well developed at the depth.
4. Casing Diameter Size: 6" and 8" inside diameter. Depth determined by geologic conditions.
5. Grout Seal: The annular space to be grouted should be not less than a nominal 2" in radius. The length of grout seal (including any surface seals) should be whatever is necessary to prevent the entrance of surface water or undesirable subsurface water into the well. The length of seal must not be less than the minimum specified in the state or locally applicable construction codes.
14-235-SOL-00009 Page 22 of 65
14-235-SOL-00009 Page 23 of 65
1.6 PERFORMANCE REQUIREMENTS
A. Water well capable of producing:
1. Individual home: Minimum 8 gallons of water per minute.
2. Community well: Well yield determined by geologic conditions and the Project Engineer.
B. Maximum Sand Suspended in Delivered Water: 5 ppm.
1.7 SUBMITTALS AT PROJECT CLOSEOUT
A. Accurately record locations of well, depth, subsoil strata, and drilling difficulties encountered on IHS well log (form attached).
B. Submit signed copy of driller's logbook statements.
C. Approved and completed county well drilling permit, if applicable.
D. Test pumping data on IHS form (form attached)
1.8 QUALITY ASSURANCE
A. Perform Work in accordance with AWWA A100 AND water well standards:
State of California.
B. Submit proof of California Class C-57 license to perform this work.
2.1 MATERIALS
A. Steel Well Casing: ASTM A53B, 0.25" for community wells or minimum 0.188” for individual wells wall thickness black steel pipe, Type E (electrical resistance) or S (seamless).
B. Drive Shoes: Heat-treated SAE 1040 steel ring or equivalent.
C. Surface Grout Seal material: 50 feet minimum for community well and 20 feet minimum for individual well.
14-235-SOL-00009 Page 23 of 65
14-235-SOL-00009 Page 24 of 65
Dry Bentonite
a. Largest chips shall be less than 1/5 the radial thickness of the annular space.
b. Mix according to manufacturer’s specifications.
c. CETCO bentonite grout or approved equal.
d. May be placed directly into annular space below water level.
Wet Bentonite
a. Baroid's Aquagel or approved equal. This type of bentonite shall not be applied dry.
D. Perforated Steel Well Casing: machined slots in a uniform pattern of spacing and rows. Slot Patterns to provide the required open area and flow rate.
E. Stainless Steel Well Screen: ANSI Type 304 stainless steel. Continuous slot;
outer windings welded to longitudinal bars. The riser pipe shall be stainless steel ASTM Type A312.
F. PVC Slotted Casing: ASTM F480, Type 1, Schedule 40 pipe; machined slots in a uniform pattern of spacing and rows. Slot Patterns to provide the required open area and flow rate. Fittings: Schedule 40 PVC ASTM F480 certa-lok mechanical restrained or equal system. CertainTeed (800) 233-8990 or approved equal.
G. PVC Well Casing: ASTM F480, Type1, Schedule 40 pipe. Fittings: Schedule 40
PVC ASTM F480 certa-lok mechanical restrained or equal system. CertainTeed
(800) 233-8990 or approved equal.
H. Filter Packing: The filter material shall consist of clean, well-rounded grains that are smooth and uniform. The material shall be mostly siliceous with not more than 5 percent calcareous material by weight. The specific gravity of the filter pack material shall be 2.5 or greater.
I. Drilling Fluids: Water-based or natural drilling fluids.
J. Chemicals: AWWA B301, Liquid Chlorine.
K. Sanitary Well Seal: Compression type with drop pipe opening and 2 additional threaded openings for Non-Pitless wells. Goulds AW Series or equal.
L. Pitless Unit: Baker-Monitor PS Model or equal.
M. Pitless Adapter: MAASS Model J “weld-on” Pitless Adapter or equal.
14-235-SOL-00009 Page 24 of 65
14-235-SOL-00009 Page 25 of 65
3.1 WELL CONSTRUCTION
A. Disinfect all tools and equipment prior to lowering into well to prevent contamination.
B. The method of drilling will be left to the discretion of the Contractor. The equipment used shall be in good repair and be capable of drilling in unconsolidated and consolidated formations.
C. Drill concentric well shaft to diameters and depths as required.
D. Place well casing immediately after drilling. Set firmly in place.
E. Clean shaft bottom of loose material.
F. Allow inspection of casing prior to placement of Surface Seal.
G. Place Surface Grout Seal to depth at a minimum depth of 20 feet for individual domestic well and minimum of 50 feet for community water supply wells and a minimum thickness of 2 inches. If required, additional grouting shall be approved and specified by the Project Engineer. The method of grouting must be approved by the Project Engineer prior to the commencement of grouting. The method must force the grout under pressure from the bottom of the space to be grouted towards the top surface or the pitless unit in a single operation.
H. No drilling, test pumping or other work in the well will be permitted within 72 hours after completion of grouting. If type 3 grout is used this period may be reduced to 48 hours.
I. A 4" thick concrete cap will be installed on top of the grout seal for structural strength and to ensure runoff drains away from the well casing.
J. Maintain well opening and casing free of contaminating materials.
K. Maintain 10 ppm Cl residual on any drilling fluid.
L. Cut off shaft top 20-24 inches above grade. Do not permit metal cuttings to enter casing.
M. Size, locate and install well screens or slotted pipe according to AWWA A100.
14-235-SOL-00009 Page 25 of 65
14-235-SOL-00009 Page 26 of 65
N. Screen sections are joined by welded or threaded connections. If joints are to be welded, the welding rod must be made of material suitable for joining corrosion resistant materials. Where dissimilar metals are joined, a dielectric coupling shall be used. Slotted pipe are joined per specified fittings, this specification.
O. A suitable length of riser pipe should be used on top of the screen or slotted section.
P. Use one of the following methods for well development: Surge plunger, compressed air, or high velocity water jetting. Pumping is not considered well development.
Q. Use of liners when unstable formations exist in an open hole shall be approved by the Project Engineer. Terminate the liner 5 feet below the top of the casing unless otherwise approved by the Project Engineer. Slotted PVC pipe will be connected to the PVC liner and be located opposite to the water-bearing formation.
R. The grading of the filter pack material shall be selected by the Contractor based on the formation samples and the driller's log.
S. Before emplacement, the filter pack material should be treated with a chlorine solution having 50-mg/l free-chlorine residual.
T. The filter pack shall be introduced uniformly and continuously to minimize or eliminate hydraulic segregation and bridging. The filter pack shall be placed by gravity through a tremie pipe. The filter pack shall extend at least 25 percent of the screen length above the top of the screen and riser pipe.
U. Weld cap on top of casing at completion. Remove cap when installing water system.
3.2 TOLERANCES
A. The maximum variation from plumb not to exceed 2/3 of casing diameter per 100 feet of well depth.
B. The alignment must be satisfactory for the successful installation and operation of the permanent pumping equipment.
3.3 TEST PUMPING
A. Notify Project Engineer 3 days prior to test pumping.
B. Discharge shall be measured with an accurate totalizing meter and stopwatch.
Discharge shall be maintained within plus or minus 5 percent of the designated rate by means of a gate valve or throttling device.
14-235-SOL-00009 Page 26 of 65
14-235-SOL-00009 Page 27 of 65
C. Discharged water shall be pumped from the discharged line to the nearest surface-water body, storm sewer or ditch to prevent recirculation of discharged water into the aquifer being tested as approved by the Project Engineer.
D. Run pumping for a minimum of 4 hours for an individual well. Pumping time over the specified minimums requires Project Engineer approval.
E. Test pumping for community wells will be performed according to the following schedule for a minimum of 12 hours:
Predominant Aquifer Material Minimum Pumping Time, hours
Silt and Clay Aquifer 170 Fine Sand 30 Medium sand and coarser materials 12
Running the test beyond these times requires Project Engineer approval.
F. Measure and record the drawdown and time of reading the test pump form according to the following schedule:
1. First 10 minutes--drawdown recorded every 1 minute
2. Next 55 minutes--drawdown recorded every 5 minutes.
3. Next 2 hours--draw down recorded every 15 minutes.
4. Final hours--drawdown recorded every 30 minutes.
G. Immediately upon completion of the test pumping, take recovery measurements and record them on the Aquifer Test Data form (form attached). The recovery readings to be measured according to the following schedule:
1. First 5 minutes--recovery readings every 1-minute.
2. Next 55 minutes--recovery reading every 5 minutes.
3. Final hours--recovery reading every 15 minutes.
H. Recovery readings for an individual home well are for two hours or until the water level recovers to within 1 foot of the static water level, whichever comes first.
I. Recovery readings for a community well shall be measured until the water level recovers to within 1 inch of the static water level or as determined by the Project Engineer.
14-235-SOL-00009 Page 27 of 65
14-235-SOL-00009 Page 28 of 65
3.4 WELL DISINFECTION AND WATER QUALITY TESTING
A. Inject and circulate a chlorine solution into well so that the chlorine concentration is at least 50 ppm.
B. Maintain disinfectant in well for 24 hours.
C. DO NOT use undissolved granular HTH for disinfection.
D. Positive bacteriological results require repeated well disinfection and samples retaken until negative results are obtained. Contractor shall notify Project Engineer of positive bacteriological results within 24 hours.
E. Collect water samples during the last hour of the pump test. The date, time and temperature of each sample are then recorded. The Contractor is responsible for the following chemical tests:
For INDIVIDUAL Wells:
arsenic barium cadmium chromium copper lead mercury nitrate as nitrogen selenium silver fluoride iron manganese chloride sulfates pH alkalinity corrosivity carbonate hardness total hardness coliform bacteria total dissolved solids antimony
For COMMUNITY Wells:
Total Coliform, - if Total Coliform positive, test for Fecal Coliform
Radionuclides, - Adjusted Alpha (Excl. Radon & U), Combined Radium 226/228, Uranium (combined)
Asbestos, Copper, Lead, Nitrate as Nitrogen, Nitrite as Nitrogen, Antimony, Arsenic, Barium, Beryllium, Cadmium, Chromium, Cyanide, Fluoride, Mercury, Selenium, Sodium, Thallium
Pesticides and SOCs 2,4,5-TP (Silvex), 2,4-D, Alachlor, Atrazine, Benzo(a)pyrene, Carbofuran, Chlordane, Dalapon, Di (2-ethylhexyl) adipate, Di (2-ethylhexyl) phthalate, Dibromochloropropane (DBCP), Dinoseb, Dioxin (2,3,7,8-TCDD), Diquat, Endothall, Endrin, Ethylene Dibromide, Glyphosate, Heptachlor, Heptachlor epoxide, Hexachlorobenzene, Hexachlorocyclopentadiene, Lindane, 14-235-SOL-00009 Page 28 of 65
14-235-SOL-00009 Page 29 of 65
Methoxychlor, Oxamyl [Vydate], PCBs [Polychlorinated biphenyls], Pentachlorophenol, Picloram, Simazine, Toxaphene
VOCs 1,1,1-Trichloroethane, 1,1,2-Trichloroethane, 1,1- Dichloroethylene, 1,2,4-Trichlorobenzene, 1,2-Dichloroethane, 1,2-Dichloropropane, Benzene, Carbon Tetrachloride, Chlorobenzene, cis-1,2-Dichloroethylene, Dichloromethane, Ethylbenzene, o-Dichlorobenzene, p-Dichlorobenzene, Styrene, Tetrachloroethylene, Toluene, trans-1,2-Dichloroethylene, Trichloroethylene, Vinyl Chloride, Xylenes
F. Collect water samples and submit them to an EPA certified laboratory. Conform to all lab-sampling requirements.
G. Contractor will furnish sample containers.
3.5 ABANDONMENT
A. Abandon wells when there is insufficient capacity, unsatisfactory water quality, poor alignment, loss of tools, or other unforeseen problems.
B. Adhere to state and local health department and any other locally applicable rules and regulations for well abandonment.
C. Well abandonment due to contamination, poor alignment, loss of tools, or any other cause attributable to the Contractor, will be conducted at the Contractor's expense.
3.6 CLEANING
A. Restore the well site to its original condition. Remove all underbrush or trees damaged during the drilling operation per Section 02110 (Site Clearing). Remove or bury all drill tailings to restore surface profile to its original condition.
END OF SECTION 02670
14-235-SOL-00009 Page 29 of 65
14-235-SOL-00009 Page 30 of 65
SECTION 03300
CAST-IN-PLACE CONCRETE
A. Cast-in-place concrete thrust block.
A. There is no separate payment for work under this section. Merge work required with pay items defined within the Measurement and Payment portions of other Sections of this contract.
1.3 REFERENCES
A. ACI 304 - Recommended Practice for Measuring, Mixing, Transporting and Placing Concrete.
B. ASTM C94 - Ready-Mixed Concrete.
2.1 CONCRETE MATERIALS
A. Cement: ASTM C150, Type I - Normal
B. Fine and Coarse Aggregates: ASTM C33.
C. Water: Clean (not detrimental to concrete).
2.2 ADMIXTURES
A. Air Entrainment: ASTM C260.
2.3 CONCRETE MIX
A. Mix and deliver concrete in accordance with ASTM C94, Alternative No. 3.
14-235-SOL-00009 Page 30 of 65
14-235-SOL-00009 Page 31 of 65
B. Provide concrete to the following criteria:
UNIT Measurement
Compressive Strength (28 day) 4000 psi
3.1 EXAMINATION
A. Verify that anchors, seats, plates, reinforcement and other items to be cast into concrete are accurately placed and positioned securely and will not cause hardship in placing concrete.
3.2 PREPARATION
A. Thoroughly compact concrete bearing area to a minimum depth of 6 inches.
3.3 PLACING CONCRETE
A. Place thrust blocking, as detailed in the drawings, at bends, tees, crosses, and fire hydrants. Pour concrete mix for thrust blocking in-place.
B. Use solid, undisturbed earth at the sides and bottom of the trench excavation for bearing concrete blocking. Shape blocking to avoid obstruction to block weep holes or access to the joints and pipe fittings.
3.4 CURING AND PROTECTION
A. Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, and mechanical injury.
END OF SECTION 03300
14-235-SOL-00009 Page 31 of 65
14-235-SOL-00009 Page 32 of 65
SECTION 15450
INDIVIDUAL WATER SYSTEM
A. Submersible well pump
B. Drop pipe and sanitary well seal
C. Well house building
D. Thermostat controlled heater
E. Disinfection and testing
F. Pressure system
G. Filter Assembly & Installation
H. Water storage tank
I. Water service line and valve
J. Frost-Free yard hydrant
1.2 RELATED SECTIONS
A. Section 02200 - Excavating, Trenching and Backfilling.
B. Section 02670 - Individual Water Well.
C. Section 03300 – Cast-in-Place Concrete
D. Section 16100 - Electrical Requirements.
1.3 UNIT PRICE - MEASUREMENT AND PAYMENT
A. SUBMERSIBLE PUMP: By the unit for the specified submersible pump as indicated in the bid schedule and includes: Material & installation of submersible pump, pump control box, and all other electrical appurtenances.
14-235-SOL-00009 Page 32 of 65
14-235-SOL-00009 Page 33 of 65
B. DROP PIPE and SUBMERSIBLE CABLE: By the vertical foot of drop length as indicated in the bid schedule and includes: Drop pipe, couplings, submersible cable, electrical wiring & connections, check valves, and adapters.
C. WELL HOUSE BUILDING 4’ x 6’: By the whole unit as stated in the bid schedule and includes: Materials to manufacture and for installation of well house. Including concrete slab and pipe penetrations, welded wire reinforcing, framing, sheathing, water proofing underlayment, thermostat controlled heater, insulation, siding, priming and painting, and all other appurtenances and
D. PRESSURE SYSTEM: By the unit as stated in the bid schedule and includes:
Materials and installation of the pressure system, pressure tank, unions, pressure switch, gate valve, hose bib with vacuum/backflow preventer, check valve, pressure gauge, plumbing, conduit/cable, circuit breaker load center, pump protection, lightning arrestor, receptacle, sanitary well cap/seal, buried electrical conduit/cable two feet beyond the edge of well slab), trenching, backfilling, and all other fittings and incidentals.
E. FILTER ASSY/INSTALLATION: By each whole unit, as indicated in the bid schedule and includes: Material, installation and connection of filter assy including drain pipe tie-in with air gap, two isolation gate valves, filter strainer, 25/1 micron filter, water service tie-in, setup, and all other appurtenances and
F. WATER STORAGE TANK: By the gallon as stated in the bid schedule and includes: Materials and installation of the water storage tank. Price shall include the tank, tank pad excavation, gravel base ring, gravel, conduit (from top of tank to buried electrical connection), electrical junction box, float switch, magnetic contactor, gate valves, check valve, plumbing, foam insulation, and all miscellaneous water service and electrical appurtenances, record drawings, and site cleanup.
G. WATER SERVICE LINE and VALVE: By the linear foot as stated in the bid schedule and includes: Trench excavation, hand trimming, pipe, fittings, tie-in to pressure enclosure system, house connection including in-line shutoff valve offset five feet from edge of house, water line warning tape, backfilling, record drawings, and site cleanup.
H. FROST-FREE YARD HYDRANT: By the unit as stated in the bid schedule and includes: Materials and installation of yard hydrant. Price shall include tie-in to service line, hydrant, gravel, and all other fittings and incidentals.
14-235-SOL-00009 Page 33 of 65
14-235-SOL-00009 Page 34 of 65
1.4 OPERATION AND MAINTENANCE DATA
A. Include typed report in a 3-ring binder with divider tabs containing:
Operation and Maintenance Requirements Trouble Shooting Checklist Water Quality and Inspection Data Replacement Part Numbers Supplier's Name/Telephone Number/Address Warranty Documentation and Registration Well Log Data and Forms
1.5 QUALITY ASSURANCE
A. Perform Work in accordance with the National Electrical Code.
2.1 SUBMERSIBLE PUMP
A. Manufacturer:
1. Grundfos: Model 5S, 7S or 10S
2. Other acceptable manufacturers offering equivalent products.
B. Performance:
1. Flow: At least 8 gpm dependent on condition of well.
2. Motor: ¾ hp, 1 hp, and 1.5 hp, 230 volts, single phase three wire, 60 Hz., or comparable as site requires.
C. Pump Shaft: Stainless steel, hex or splines.
D. Casing: Stainless steel.
E. Type: Pump and motor are separate, replaceable units.
F. Warranty: Provide a 5 year manufacturer's repair/replacement pump warranty.
Cost of pulling and reinstalling the pump after the expiration of the 1 year warranty is not the responsibility of the Contractor.
2.2 DROP PIPE
A. Type: PVC Schedule 120, threaded drop pipe, meeting ASTM D 1785.
14-235-SOL-00009 Page 34 of 65
14-235-SOL-00009 Page 35 of 65
B. Fittings: Stainless Steel; Must equal or exceed ASTM D 1785 for length of pipe and size/weight of pump.
C. Size: 1-1/4 inch based on water service line diameter and size/weight of pump.
2.3 WELL HOUSE ENCLOSURE
A. Type: “Wood Framed” 4’x6’ building unfinished with interior insulation on concrete slab to enclose the well water pressure system.
1. Manufacturer: Jerry’s Custom Trusses & Sheds, Mariposa, CA.
(209) 966-2326.
2. Model: Well House – 4’ x 6’.
B. Foundation and Pipe Penetrations: Concrete slab with floor pipe penetrations from trenched pipe and electrical.
1. Caste in place concrete 6 feet x 4 feet x 4 inches thick.
2. 6”X6” wire mesh.
C. Thermostat Controlled Heater:
1. Thermostat controlled heater to maintain temperature in the well house building above freezing.
2. Product: Equal to Patton Milk-House Heater, 1500W.
3. Execution: Install per manufacturers specifications.
D. Insulation:
1. Batt or blanket wall insulation with attached vapor barrier.
2. Exterior grade steel door.
3. R-value equal to R-10 or greater for walls and overhead.
4. Gaps sealed with spray foam insulation sealant. Manufacturer: Great Stuff or equal.
5. Other approved equivalent with similar insulation value.
2.4 WATER SERVICE PIPE
A. Polyethylene Pipe: ASTM D2239, IPS size, for 200 psi pressure rating:
1. Manufacturer: West Flex or Driscopipe 5100 Ultra-line.
2. Joints: Non-Flare Compression equal to Ford Pack Joints. Metal inserts are required.
3. Size: 1.0 inch to 1.5 inch based on length of service line.
B. House connection as indicated in the drawings.
14-235-SOL-00009 Page 35 of 65
14-235-SOL-00009 Page 36 of 65
2.5 SANITARY WELL SEAL (Non-Pitless Application)
A. Manufacturer: Goulds AW series or equal.
B. Compression type with central drop pipe opening and 2 additional threaded openings: One threaded opening is used for the electrical connection; the second threaded opening is for a screened air vent directed vertically downward.
2.6 PRESSURE SYSTEM
A. Pressure Tank (86 gallon):
1. Manufacturer: Well-X-Trol WX-252.
2. Precharged.
B. Pressure Switch:
1. Manufacturer: Square D FSG-2 3050 or equal.
2. Pressure setting: 30 psi to 50 psi.
C. Pressure Gauge:
1. Liquid filled 2-1/2 inch diameter dial size.
2. Type: Steel case with ¼ inch NPT.
3. Pressure Range: 0 to 100 psi.
D. Pressure Relief Valve:
1. Manufacturer: Goulds AV12-07 or equal.
2. Pressure setting: 75 psi to 80 psi.
E. Flow Control Valve:
1. Manufacturer: Dole or equal.
2. Pressure rate: 125 psi.
F. Gate Valve:
1. Bronze, O ring stem seal, 125 psi rated.
G. Check Valve:
1. Manufacturer: Flowmatic
14-235-SOL-00009 Page 36 of 65
14-235-SOL-00009 Page 37 of 65
H. Piping:
1. Type: Polyethylene Pipe: ASTM D2239, IPS size, for 200 psi pressure rating
2. Size: 1.0 inch to 1.5 inch.
I. Tank Drain
1. ¾ inch Bronze Boiler Drain with ¾ inch hose threads on outlet.
2.7 FILTER ASSEMBLY
A. Filter Assembly:
1. Manufacturer: MangOX 7000 or approved equal.
2. Active agent: MangOX (formerly called Catalox) which is used for removing iron, hydrogen sulfide, and manganese from water supplies.
3. Capacity: 1.0 cubic feet.
4. Material: NSF certified one piece seamless polyester construction.
5. Piping Connections: 1 inch or 3/4 inch pipe connectors.
2.8 WATER STORAGE TANK
A. Tank:
1. Manufacturer: American Tank Co. (800) 655-9100, or equal.
2. Capacity: As shown on the drawings.
3. Material: One piece, molded without seams from Polyethylene. Must be certified to NSF 61 and/or FDA 21CFR 177.1520 (1) 3.1 and 3.2 for storage of potable water rated.
4. Piping Connections: As shown on the drawings.
5. Manhole: 16" diameter access.
B. Base Gravel:
1. 3/8" round pea gravel.
2. Gravel shall be level and compacted in place.
2.9 FROST-FREE YARD HYDRANT
A. Hydrant:
1. Manufacturer: Simmons
2. Model: Lead free, Deluxe frost-proof yard hydrant 4800LF
14-235-SOL-00009 Page 37 of 65
14-235-SOL-00009 Page 38 of 65
3.1 SUBMERSIBLE AND…