About this file
This is a Scope of Work document for the City of Jackson Community Development Department in Michigan for roofing repairs at 1413 Teneycke Street. The project involves stripping and installing a new roof and new gutters on a program-qualified homeowner's residence. The work is part of a competitive sealed bid process where participants must have completed Sam.gov registration, maintain proper licensing, and obtain all required permits prior to commencing work. The project will be awarded to the qualified bidder submitting the lowest responsive bid. Specific response dates, site visit requirements, bidder's meetings, and contract award timelines should be verified through the solicitation documents and the City of Jackson Community Development Department.
Pricing, set-asides, funding sources, and other financial terms are not detailed within the scope of work document itself. Additional information regarding bid pricing requirements, any small business or minority contractor set-asides, funding mechanisms through the Community Development Department programs, and contract performance terms would be contained in the formal bid solicitation documents and contract terms issued by the City of Jackson.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1413_Teneyck_St._-_Strip_and_Replace_Roof_and_New_Gutters.pdf | ||
| All_Services_Sample_Contract_.docx | DOCX document | |
| CDBG_Additional_Forms.pdf | ||
| Maintenance_and_Guarantee_Bond.pdf | ||
| Labor_and_Material_Payment_Bond.pdf | ||
| Performance_Bond.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Work Write-Up
R05 - ROOF - STRIP AND INSTALL
* EXHIBIT 1 *
Dated: 6/11/2026
CUSTOMER INFORMATION
Laudermilt, brett 1413 Teneyck st, Jackson, MI 49203-1906
PREPARED BY
sharrison@cityofjackson.org
* NOTE *
THE CUSTOMER AND CONTRACTOR MUST SIGN THE BOTTOM OF EACH PAGE ONLY IF
1) THIS WORK WRITE-UP BECOMES PART OF A CONSTRUCTION CONTRACT
2) THE UNDERSIGNED CUSTOMER AND CONTRACTOR HAVE REVIEWED, APPROVED AND AGREED TO THE WORK AND PRICES DESCRIBED IN THIS WORK WRITE-UP
Location: Unassigned
| General Requirements |
| Quantity |
| Units |
| Total |
1 - R05 - ROOF - STRIP AND INSTALL
(Specification ID:1.05000 )
* PERMIT REQUIRED *
Strip existing roof, removing all shingles and felt. Make repairs to the existing roof framing where required to provide adequate strength and a true and level surface. Install 7/16” oriented-strand board sheathing to cover all areas of roof deck. Just before proceeding, sweep roof thoroughly to remove all debris. Install ice shield at all lower roof edges. Ice shield shall extend at least 24" inside the interior surface of the exterior wall line of the building, in accordance with the Michigan Building Code. Install new 15% asphalt saturated felt according to manufacturer's directions. Furnish and install new roofing material of a color as selected by owner, must be architectural style. Installation shall include metal drip and rake edge, two layers of 90# roll valley or metal valley in all valleys. Reflash chimney, plumbing vents, and vertical walls with appropriate neoprene boots and metal step flashing where possible. Install ventilation units sufficient to vent all areas of attic. Ridge venting when used shall cover the full length of the roof ridge. Installation of all materials shall follow manufacturer's printed instructions and G.S. 1.
Contractor is responsible for final measurement.
Remove all Satellite dishes and antenna from the roof, they will not go back up.
East side of the home lower back side there has been some leaking, plan on approx. 100 sq ft of roof decking repair.
Approximately 20 squares on all elevations New roofing material type shall be architectural shingles Manufacturer: __________ Color Name/Number: __________
Contractor's Initials: ____________________ Owner's Initials: __________ Rehab initials_______________
2 - G08 - GUTTERWORK
(Specification ID:1.08000 )
LF
Furnish and install gutter and downspout. Replacements shall match existing as to materials, finish, shape and size. Do not mix galvanized with copper or aluminum. Where replacements are of a complete system or side of a system having no cross connections with sections not to be replaced, used baked pre-enameled aluminum, 5 inch K-type in standard colors. Minimum thickness of aluminum shall be .027 inches for troughs and fittings. Use one or a combination of strap hangers, spike and ferrules or fascia hangers. Space hangers and slip joint connectors per manufacturer's instructions. Maximum spacing of hangers shall be 48 inches OC for galvanized and 30 inches for aluminum. Use only recommended gutter seal and rivets or screws at all joints. All work, whether a complete new system or a partial replacement, shall have the system with a pitch of not less than 1 inch in 16 feet. Divert the water away from the foundation using appropriate extensions and/or concrete splash blocks. All work to conform to code and G.S. 4a.
Contractor responsible for final measurements.
All Downspouts shall be the commercial size.
Approximately __________ linear feet of gutter on __________ elevation(s).
Approximately ___________ linear feet of downspout on ___________ elevation(sn) .
Subtotal for General Requirements
Total
Prepared By: sharrison@cityofjackson.org on 6/11/2026
OWNER ACCEPTS SCOPE OF WORK
I have read the contents of this work write up and received a copy. I fully understand the repairs to be made to my property.
| x_________________________ | __________ | |
| Owner: | Date |
CONTRACTOR ACCEPTS SCOPE OF WORK
I have read the contents of this work write up and agree to perform all work called for in accordance with the bid submitted on __________.
| x_________________________ | __________ | |
| Contractor | Date |
| x____________________________ | __________ | |
| Construction Specialist | Date |
| Prepared By: sharrison@cityofjackson.org on 6/11/2026 |
| 4 of 4 |