This is a Performance Work Statement (PWS) for elevator inspection and certification services at three federal facilities operated by the Bureau of Reclamation's Central California Area Office. The contract requires a Qualified Elevator Inspector (QEI) to provide independent third-party inspections of elevators located at Folsom Dam, Folsom Powerplant, and New Melones Powerplant in accordance with ASME A17.1, A17.2, and QEI-1 standards. The contractor must furnish all labor, supervision, equipment, and materials to conduct periodic 6-month inspections, annual Category 1 inspections, and a Category 5 inspection every 5 years. The QEI will witness testing performed by the existing maintenance contractor (Elevator Technology Inc.) and provide written reports within seven business days of each inspection. The contract period consists of a base year (12/15/2026–12/14/2027) and four option years, with inspections scheduled twice annually at approximately six-month intervals.

Key deliverables include a contractor safety program and Job Hazard Analyses (JHAs) due within 14 calendar days of contract award, QEI certification documentation, inspection reports, elevator certificates for placement in elevators, and deficiency recommendations. The contractor must comply with Reclamation Safety and Health Standards (RSHS), OSHA requirements, and FIST 1-1 (Hazardous Energy Control Program) standards. Work is performed at two locations: New Melones Powerplant in Jamestown, California, and Folsom Dam/Powerplant in Folsom, California, during normal business hours (Monday–Friday, 7:00 a.m.–3:30 p.m. Pacific Time) on non-federal holidays. The three elevators include two Montgomery Elevators at Folsom facilities (P-1 and P-2) and one Elevator Industries unit at New Melones (P-3), all electric passenger elevators with capacities ranging from 1,200 to 10,000 pounds. The Quality Assurance Surveillance Plan requires 100 percent compliance with safety standards, timely completion of all inspections within scheduled intervals, and accurate and complete inspection reporting.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement (PWS)

Central California Area Office

Elevator Inspection and Certification Services at

Folsom and New Melones Powerplants and Folsom Dam

1.0 Background

Elevator inspection and certification services are needed for three elevators located at Folsom Dam, Folsom Powerplant and New Melones Powerplant. ASME Code A17.1, A17.2 and QEI-1 require that third party qualified individuals inspect the elevators independent of individuals performing maintenance. Currently, Elevator Technology Inc. is under contract to provide monthly inspection, maintenance, and testing services of the elevators, but it is a conflictive interest for Elevator Technology Inc. to provide/perform third party independent inspections of the same elevators they maintain. The Qualified Elevator Inspector (QEI) shall inspect and witness the testing done by Elevator Technology Inc. Currently, the three elevators have valid certificates and have been routinely inspected since 2021.

1.1 Definitions

ASME: American Society of Mechanical Engineers FIST: Facilities Instructions, Standards and Techniques (Reclamation) CO: Contracting Officer COR: Contracting Officer’s Representative QEI: Qualified Elevator Inspector

2.0 Scope

Regular inspections are required to ensure the safe operation of the elevators that personnel utilize every day. Services are to provide Qualified Elevator Inspector(s) (QEIs), other personnel/labor as necessary, tools, equipment and transportation to inspect and certify the Folsom Dam, Folsom Powerplant and New Melones Powerplant elevators in accordance with ASME A17.1, A17.2 and other applicable ASME requirements. Inspection intervals are every 6 months and consist of a Periodic 6-month inspection, and an annual Category 1 inspection unless a Category 5 inspection (every 5 years) is due. The Category 5 inspection when due would supplant the annual inspection interval. The last Category 5 inspection was performed in July of 2025. Actual testing as related to the Category 1 and 5 inspections is done by others, and currently this will be accomplished by Elevator Technology Inc. personnel. The QEI will witness the testing performed by Elevator Technology Inc. and would provide an inspection report as related to the specific testing and any appropriate recommendations per the code. The Periodic (routine) 6-month inspection performed by the QEI does not require Elevator Technology Inc. to be present. In all cases, the QEI must provide a report outlining the inspection, testing, deficiencies, and recommendations. The COR shall coordinate the planned testing activity with Elevator Technology Inc. and the QEI Contractor regarding the Category 1 and 5 testing to ensure witnessing by the QEI. The COR shall coordinate all activities and make the elevator available for inspection/testing. The COR shall coordinate Elevator Technology Inc. and the QEI’s schedule to ensure witnessing.

3.0 Tasks and Deliverables

Contractor shall furnish all labor, supervision, equipment, and materials in performing the work described in this PWS and as applicable by any approved submittals. The items/deliverables that follow are effectively submittal/technical requirements to be provided by/complied with by the Contractor. Submittals can be accomplished via email submission. Obtain Approval/Acceptance regarding the requirements in sections 3.1 and 3.2 below within 14 calendar days following contract award.

3.1 SAFETY PROGRAM AND JHAS

Contractor shall follow Reclamation Safety and Health Standards (RSHS) while conducting all work on Reclamation property. The Contractor shall submit a written safety program and JHAs as outlined in Section 3 and 4 of the RSHS for review and acceptance by Reclamation. Also, see requirements in Section 6.0.

3.2 Contractor Key Personnel and Qualifications

Also see Section 5.4. Contractor shall have current Qualified Elevator Inspector Certification (QEI) from an accredited institution.

3.3 Inspection Services and Reports

Provide inspection services as outlined in the schedule below in accordance with ASME 17.1,

17.2 and other applicable ASME requirements. Provide a report within seven business days following an inspection compliant with ASME requirements. Provide/place elevator certificates in elevators. The COR shall coordinate all activities and make the elevator available for inspection/testing. The COR shall coordinate Elevator Technology Inc. and the QEI’s schedule to ensure witnessing.

4.0 Period of Performance (POP) and Schedule

The period of performance and schedule shall be a base year and four option years as follows:

POP Inspection 1 Inspection 2

Base Year: 12/15/2026-12/14/2027 Category 1 6 month Periodic

Option Year 1: 12/15/2027-12/14/2028 Category 1 6 month Periodic

Option Year 2: 12/15/2028-12/14/2029 Category 1 6 month Periodic

Option Year 3: 12/15/2029-12/14/2030 Category 5 6 month Periodic

Option Year 4: 12/15/2030-12/14/2031 Category 1 6 month Periodic

Note: Inspections will occur twice annually and approximately 6 months apart. However, the inspection sequence can be reversed in a given year. This means that Inspection 2 can be accomplished before Inspection 1 as it may be more advantageous to do so based on discussions with the contractor and the needs of the Government. An inspection cannot be scheduled in a given year that was never planned for that year.

5.0 Recognized Holidays

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veterans Day Memorial Day Thanksgiving Day Juneteenth Christmas Day Independence Day

The Bureau of Reclamation observes all federally recognized holidays, and the facility is not open for normal operation on those days. No work shall occur during Federal holidays unless there are emergency repairs that have been authorized by the CO.

5.1 Hours of Operations

Normal business hours are Monday through Friday, 7:00 a.m. to 3:30 p.m. Pacific Time except Federal holidays. The contractor is responsible for performing work as defined in this PWS during normal business hours except when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.

5.2 Place of Performance

New Melones Powerplant Folsom Dam and Powerplant 16805 Peoria Flat Road 7794 Folsom Dam Road Jamestown, CA 95327 Folsom, CA 95630

5.3 Security

The solicitation and resulting contract may delineate any applicable specific Contractor security requirements. As such, Contractor personnel performing work under this contract shall meet the security requirements at the time of award and must maintain the level of security required for the life of the contract. The Contractor shall coordinate access for personnel, materials, and equipment with the COR prior to mobilization on site. The COR will escort Contractor personnel as necessary and will be at the work site any time the Contractor is on site.

5.4 Contractor Company and Personnel Experience

The work shall be accomplished by firm and personnel with direct experience in providing the services described herein.

5.5 Protection of Existing Facilities and Environment

The contractor shall repair, clean, or remediate any damages caused to Government property at their expense. Clean and remove any debris from the work site.

6.0 Site Safety and Job Hazard Analyses (JHAs)

The contractor shall be responsible for ensuring safety at all times on site in compliance with OSHA and Reclamation Safety and Health Standards (RSHS) whichever is more stringent.

(https://www.usbr.gov/ssle/safety/RSHS/rshs.html) At a minimum, a Job Hazardous Analysis (JHA) shall be written and discussed with all parties present prior to any work beginning on site.

See Sections 3 and 4 of the RSHS for specific requirements. Each participant shall sign the JHA, and the COR shall make and distribute copies.

6.1 Work within and adjacent external features associated with New Melones Dam, Power Plant, and Switchyard:

These facilities are subject to Facility Instruction Standards and Techniques 1-1, (FIST 1-1), Hazardous Energy Control Program (HECP), (https://www.usbr.gov/power/data/fist_pub.html).

Effectively, FIST 1-1 outlines the safety and lockout – tag out procedures associated with any hazardous energy as a result of a repair action in the above facilities. Administratively, a Special Work Permit under HECP must be issued before any work can proceed under a clearance within a Reclamation powerplant for example. The Special Work Permit is equivalent to a Notice to Proceed and the COR will provide all coordination and issue the Special Work Permit to the contractor. See above link for more information.

7.0 Government-Furnished Property and Access

https://www.usbr.gov/ssle/safety/RSHS/rshs.html

No Government Furnished Property is authorized. Restroom facilities are available for the contractor’s use as needed, but no potable water is available.

8.0 Applicable Publications/Standards

1. Work shall comply with all applicable local, state, and federal laws/regulations/codes, industry standard practices, and device/equipment manufacturer instructions and specifications. If standards or codes conflict, the contractor shall comply with the more stringent of the standards or codes.

2. Reclamation Safety and Health Standards (RSHS), (latest version):

https://www.usbr.gov/ssle/safety/RSHS/rshs.html

3. FIST 1-1, Hazardous Energy Control Program (HECP), https://www.usbr.gov/power/data/fist_pub.html

4. FIST 2-10 – Maintenance, Inspection and Testing of Electric and Hydraulic Elevators

5. ASME A17.1 – “Safety Code for Elevators and Escalators”

6. ASME A17.2 - “Inspectors' Manual for Elevators and Escalators”

7. ASME A17.3 – “Safety Code for Existing Elevators and Escalators”

8. ASME QEI-1 – “Standard for the Qualification of Elevator Inspectors”

9.0 Description and Location of Elevators

Designation: P-1 Manufacturer: Montgomery Elevator Type: Electric Location: Folsom Dam, Folsom, CA Capacity: 10,000 pounds or 65 passengers Year Installed: 1955, alterations in 2005 Speed: 300 feet per minute Number of stops and openings: 8 stops, 8 openings Service: Passenger Usage: Used regularly by employees to move tools and equipment.

Designation: P-2 Manufacturer: Montgomery Elevator Type: Electric Location: Folsom Power Plant, Folsom, CA Capacity: 10,000 pounds or 65 passengers Year Installed: 1955, alterations in 2006 Speed: 150 feet per minute Number of stops and openings: 6 stops, 6 openings

Service: Passenger Usage: Used regularly by employees to move tools and equipment.

Designation: P-3 Manufacturer: Elevator Industries Type: Electric Location: New Melones Power Plant, Jamestown, CA Capacity: 1,200 pounds or 8 passengers Year Installed: 1979, alterations in 2004 Speed: 100 feet per minute Number of stops and openings: 5 stops, 5 openings Service: Passenger Usage: Used by employees and to move tools and equipment.

10.0 Deliverables

Deliverable PWS Reference Due Date Recipient

Contractor Safety Program

3.1 Within 14 calendar

days after contract award

COR

Job Hazard Analyses (JHAs)

3.1, 6.0 Prior to commencement of on-site work

COR

QEI Certification Documentation

3.2 Within 14 calendar

days after contract award

COR

Category 1, Category 5, and Periodic Inspection Reports

3.3 Within 7 business

days following each inspection

COR

Elevator Certificates 3.3 Following successful inspection and certification

COR / Elevator Location

Inspection Deficiency Recommendations

3.3 Included with

inspection report

COR

11.0 Quality Assurance Surveillance Plan

The Quality Assurance Surveillance Plan is one evaluation method the government uses to monitor contractor performance to determine whether the Contractor meets the standards of performance as defined in the PWS. The absence of a QASP for any contract requirement, however, shall not detract from its enforceability or limit the rights or remedies of the government under any other provision of the contract in determining the quality of the Contractor performance.

Performance Requirements Summary (PRS)

Timeliness is required for all tasks within their applicable contractual timeframes, 100 percent of the time. The following performance measures apply to elevator inspections and associated deliverables.

Performance requirement

Performance standard / acceptable quality level (AQL) Method of surveillance

Safety compliance

Zero on-site safety incidents or violations of applicable OSHA, RSHS, and HECP requirements.

Direct observation of on-site activities and review of safety documentation and incident reports; 100% surveillance of on-site inspection activities.

Initial submittals

Submit 100% of required initial submittals within 14 calendar days following contract award. Submittals shall be complete and conform to PWS requirements.

Review all required submittals for receipt date, completeness, and compliance; coordinate review comments and document approval or acceptance status.

Timely completion of elevator inspections

Complete 100% of required inspections within the inspection intervals, scheduled dates, and completion deadlines established in the PWS or otherwise authorized under the contract.

Document actual completion dates and

Review the inspection schedule and completion records for every required inspection; compare required and actual completion dates

Performance requirement

Performance standard / acceptable quality level (AQL) Method of surveillance promptly notify the COR of any condition that may affect timely completion.

and document missed deadlines.

Timely submission of inspection reports

Submit 100% of inspection reports and associated documentation within the reporting timeframes established in the PWS.

Track receipt dates for all required reports and compare them with contractual submission deadlines.

Accuracy and completeness of inspection reports

100% of reports shall accurately identify the facility and elevator inspected, inspection date, inspection scope, required test results, findings, and deficiencies, as required by the

PWS.

Review 100% of reports for required content, internal consistency, and agreement with supporting inspection and test records.