This document is a Request for Proposals (RFP) for the Norman Fire Break Clearing and Fencing project at Lake Thunderbird State Park in Norman, Oklahoma. The solicitation is being issued by the Department of the Interior Bureau of Reclamation.
The RFP requires the contractor to provide clearing and fencing services to create a fire break at the specified location. The scope of work includes vegetation clearing, fence installation, and related activities. Proposals are due by a specific date, and the contract is expected to be awarded shortly after. Pricing information, set-aside requirements, and other relevant terms are detailed in the RFP. The document provides an overview of the project objectives and requirements, and contains instructions for submitting proposals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140R6024R0017_Amd_0001.pdf | ||
| 140R6024R0017_Amendment_No__0001_0001.pdf | ||
| Sol_140R6024R0017.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior Bureau of Reclamation Missouri Basin and Arkansas-Rio Grande-Texas Gulf Regions Billings, Montana August 2024
Request for Proposal Solicitation No. 140R6024R0017
Norman Fire Break Clearing and Fencing
Lake Thunderbird State Park Norman Project, Oklahoma
Forward – 1
Norman Fire Break Clearing and Fencing
FORWARD
Work is located at Lake Thunderbird. Lake Thunderbird is approximately 15 miles east of Norman on S.H. 9 in Cleveland County, Oklahoma.
Principle components of work include: (1) Surveying; (2) Demolition of existing fencing; (3) Mechanically clearing firebreak; (4) Constructing new 5-strand barbed wire fence; (5) Constructing steel corner posts and H-braces; (6) Constructing steel post and cable fencing.
POINT OF CONTACT – The Contract Specialist for this requirement is Mr. Howard Heflin.
All questions and correspondence concerning this solicitation shall be directed to him via email at hheflin@usbr.gov.
METHOD OF PROCUREMENT – This requirement is solicited as a Request for Proposal (RFP) using the Federal Acquisition Regulation (FAR) subpart 19.8 – Contracting with the Small Business Administration (The 8(a) Program), and FAR part 15 – Contracting by Negotiation.
ORGANIZED SITE VISIT – An organized site visit shall be coordinated with the Contracting Officer Representative (COR), Cody McCrackin at (405) 470-4824 or cmccrackin@usbr.gov.
RECLAMATION SAFETY AND HEALTH STANDARDS (2014 EDITION) – For information regarding Bureau of Reclamation’s publication “Reclamation Safety and Health Standards” (revised in June 2024 unless a later date is noted, at https://www.usbr.gov/safety/rshs/index.html) which is applicable to work under this contract, see clause at “WBR 1452.223-81 – Safety and Health”.
SYSTEM FOR AWARD MANAGEMENT (SAM) – Effective October 2018, all contractors interested in doing business with the Federal Government must be registered in the System for Award Management (SAM) database at the time they submit their offer. Note: Registering in SAM does not constitute an automatic award of any contract or agreement to the registering contractor. SAM is a centralized database for consolidating the Central Contractor Registration (CCR), the Online Representation and Certifications Application (ORCA), and the Excluded Parties List System (EPLS).
Additionally, the contractor’s business and financial information are required for SAM registration and annual confirmation requirements, which must be accomplished through the SAM website at https://sam.gov/. For assistance with registering in SAM, contact the Federal Services Desk at 1-866-606-8220.
mailto:hheflin@usbr.gov mailto:cmccrackin@usbr.gov https://www.usbr.gov/safety/rshs/index.html https://sam.gov/
Forward – 2
INVOICE PROCESSING PLATFORM (IPP) – Payment requests for the anticipated contract or agreement must be submitted electronically through the U.S. Department of Treasury’s “Invoice Processing Platform” (IPP) System via the IPP website at https://www.ipp.gov.
Contractors are required to use the IPP website to access and use IPP for submitting request for payment. Registration assistance can be obtained by contacting the “IPP Production Helpdesk” via email ippgroup@bos.fbr.org or phone 1-866-973-3131. If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor can submit a waiver request in writing to the Contractor Officer with its proposal.
Note: Waivers will be on a case-by-case basis and not automatically granted as determined by the Contract Officer. Please see Paragraph G.3, DOI-AAAP-0028 for more specific information on the process for submitting invoices in IPP.
END OF FORWARD
https://www.ipp.gov/ mailto:ippgroup@bos.fbr.org
Table of Contents
00 01 10 - 1
TABLE OF CONTENTS
PART I – THE SCHEDULE
SECTION A – SOLICITATION, OFFER, AND AWARD: STANDARD FORM 1442
SECTION B – PRICE SCHEDULE
SECTION C – DESCRIPTION / SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 12 Work Restrictions 01 31 19 Project Management and Coordination 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Demolition of Existing Fences 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 71 20 Surveying
DIVISION 31 - EARTHWORK
31 11 00 Clearing
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 31 30 Fencing and Gates
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 01 71 United States Boundary Information
DIVISION 52 - DRAWINGS
52 00 00 Drawings
00 01 10 - 2
SECTION D – NOT USED
SECTION E – INSPECTION AND ACCEPTANCE
E.1 52.246-12 Inspection of Construction
SECTION F – DELIVERIES OR PERFORMANCE
F.1 52.211-10 Commencement, Prosecution, and Completion of Work F.2 52.211-18 Variation in Estimated Quantity F.3 52.236-15 Schedules for Construction Contracts F.4 52.242-14 Suspension of Work
SECTION G – CONTRACT ADMINISTRATION DATA
G.1 1452.201-70 Authorities and Delegations G.2 WBR 1452.201-80 Contracting Officer’s Representative’s Authorities and Limitations G.3 DOI-AAAP 0028 Electronic Invoicing and Payment Requirements – Invoice
Processing Platform (IPP) G.4 DOI-AAAP 0050 Notice to Contractors – Contractor Performance Assessment
Reporting System
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1 MB-1 Schedule of Values
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
I.1 52.252-2 Clauses Incorporated by Reference I.2 52.204-21 Basic Safeguarding of Covered Contractor Information Systems I.3 52.215-8 Order of Precedence – Uniform Contract Format I.4 52.219-14 Limitations on Subcontracting I.5 52.219-17 Section 8(a) Award I.6 52.219-28 Post-Award Small Business Program Rerepresentation I.7 52.222-23 Notice or Requirement for Affirmative Action to Ensure Equal
Employment Opportunity for Construction I.8 52.223-3 ALT I Hazardous Material Identification and Material Safety Data –
Alternate I I.9 52.225-9 Buy American–Construction Materials I.10 52.228-2 Additional Bond Security I.11 52.228-15 Performance and Payment Bonds – Construction I.12 52.232-5 Payments Under Fixed-Price Construction Contracts I.13 52.232-27 Prompt Payment for Construction Contracts I.14 52.232-40 Providing Accelerated Payments to Small Business Subcontractors I.15 52.236-2 Differing Site Conditions I.16 52.236-13 Accident Prevention
00 01 10 - 3
I.17 52.236-21 Specifications and Drawings for Construction I.18 52.243-4 Changes I.19 52.246-21 Warranty of Construction I.20 52.252-6 Authorized Deviations in Clauses I.21 1452.203-70 Restriction on Endorsements – Department of the Interior I.22 1452.204-70 Release of Claims – Department of the Interior I.23 WBR 1452.209-82 Prohibition on Release of Information – Bureau of Reclamation I.24 1452.215-70 Examination of Records by the Department of the Interior I.25 WBR 1452.219-81 Section 8(a) Direct Award – Bureau of Reclamation I.26 WBR 1452.223-80 Asbestos-Free Warranty – Bureau of Reclamation I.27 WBR 1452.223-81 Safety and Health – Bureau of Reclamation I.28 WBR 1452.223-82 Ensuring Adequate COVID-19 Safety Protocols in Federal
Buildings and Federally Controlled Facilities – Bureau of Reclamation
I.29 1452.228-70 Liability Insurance – Department of the Interior I.30 WBR 1452.232-81 Payment for Mobilization and Preparatory Work – Bureau of Reclamation I.31 WBR 1452.236-84 Preservation of Cultural Resources – Bureau of Reclamation I.32 WBR 1452.237-80 Security Requirements – Bureau of Reclamation – Alternate III
ALT III
I.33 WBR 1452.242-80 Postaward Conference – Bureau of Reclamation I.34 WBR 1452.243-80 Modification Proposals – Bureau of Reclamation – Alternate II
ALT II
PART III – DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
Attachment No. 0001…………………………………...General Decision Number OK20240029 Attachment No. 0002……………………………………………...Standard Form 24 – Bid Bond
PART IV – REPRESENTATIONS AND CERTIFICATIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER
STATEMENTS OF OFFERORS
K.1 52.204-8 Annual Representations and Certifications K.2 52.204-24 Representation Regarding Certain Telecommunications and Video
Surveillance Services or Equipment K.3 52.209-7 Information Regarding Responsibility Matters K.4 52.209-13 Violation of Arms Control Treaties or Agreements-Certification
SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
L.1 52.204-7 System for Award Management L.2 52.204-16 Commercial and Government Entity Code Reporting L.3 52.204-22 Alternative Line Item Proposal
00 01 10 - 4
L.4 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29
L.5 52.211-2 Availability of Defense Specifications, Standards and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST)
L.6 52.214-34 Submission of Offers in the English Language L.7 52.214-35 Submission of Offers in U.S. Currency L.8 52.216-1 Type of Contract L.9 52.222-5 Construction Wage Rate Requirements – Secondary Site of the
Work L.10 52.225-10 Notice of Buy American Requirement – Construction Materials L.11 52.228-1 Bid Guarantee L.12 52.228-17 Individual Surety – Pledge of Assets (Bid Guarantee) L.13 1452.233-2 Service of Protest – Department of the Interior (DEVIATION) L.14 52.236-27 Site Visit (Construction) L.15 52.236-28 Preparation of Proposals – Construction L.16 52.252-1 Solicitation Provisions Incorporated by Reference L.17 52.252-5 Authorized Deviations in Provisions L.18 1452.215-71 Use and Disclosure of Proposal Information – Department of the
Interior L.19 WBR 1452.215-81 Proposal Instructions – Bureau of Reclamation L.20 WBR 1452.236-85 Instruction for Mobilization and Preparatory Work Schedule Line
Item – Bureau of Reclamation
SECTION M – EVALUATION FACTORS FOR AWARD
M.1 WBR 1452.215-80 Source Selection Evaluation Procedures – Bureau of Reclamation M.2 WBR 1452.215-85 Evaluation Factors for Award – Lowest Price Technically Acceptable Source Selection Process – Bureau of Reclamation
END OF CONTENTS
SECTION A
SOLICITATION, OFFER, AND AWARD
(STANDARD FORM 1442)
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040654703
Bureau of Reclamation
Missouri Basin Region
Regional Office 2021 4th Avenue North
R60
Billings MT 59101
Bureau of Reclamation
Attn: MB-5000 / Howard Heflin
2021 4th Avenue North Billings MT 59101
Howard Heflin 4062477797
1x 08/30/2024
140R6024R0017
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Norman Fire Break Clearing and Fencing, Lake Thunderbird State Park, Norman Project, Oklahoma
The magnitude of this project is between $250,000 and $500,000.
The North American Industry Classification System (NAICS) code is: 115310 Exception 2 - Fuels Management Services.
The Small Business Size Standard is: $34 Million.
The Product Service Code (PSC) is: F003 - Fire Suppression/Presuppression.
This solicitation is conducted under the authority of 41 U.S.C. 3304(a)(5) for use of other than full and open competition. This authority authorizes a sole source award under the 8(a) Program.
Proposal is to be submitted via email to hheflin@usbr.gov and camaurer@usbr.gov.
Reclamation's email servers limits attachments to 25 MB per email. Therefore, the offeror may need to submit multiple emails to ensure the Contract Specialist and Contracting Officer receive the complete proposal (Volumes 1-3).
The Offeror shall fill out the following:
Taxpayer Identification Number (TIN): _______________
System for Award Management (SAM) Unique Entity Identification (UEI): ______________
Commercial and Government Entity Code (CAGE): _______________
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 250 calendar days and complete it within ________________ ________________ calendar days after receiving
Paragraph F.1.
09/13/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Missouri Basin Region
Regional Office 2021 4th Avenue North
R60
Billings MT 59101
Charlene Maurer
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
and return
(Contractor is not required to sign this document.) Your offer on this
Invoice Processing Platform System US Department of Treasury https://www.ipp.gov
Paragraph G.3 X 5
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140R6024R0017
00010 1 AU $______________Norman Fire Break Clearing and Fencing
Product/Service Code: F003
Product/Service Description: NATURAL
RESOURCES/CONSERVATION- FOREST-RANGE FIRE
SUPPRESSION/PRESUPPRESSION
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SECTION B
THE SCHEDULE
Norman Project, Oklahoma .
Price Schedule B-1
SECTION B - SUPPLIES OR SERVICES AND PRICES / COSTS
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only.
Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN - Contract Line Item Number.
Schedule A – Fire Break Clearing and Fencing
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1 WBR
1452.232-
Mobilization and Preparatory work
For the lump sum of
2 01 71 20 Surveying
For the lump sum of
3 01 56 20 Demolition of Existing Fencing
9,875 LF $ $
4 31 11 00 Mechanical Clearing 20 feet wide (Adjacent to Private Property)
11,760 LF $ $
Price Schedule B-2
5 31 11 00 Mechanical Firebreak Restoration 10 feet wide
11,760 LF $ $
6 32 31 30 5- Strand Barbed Wire Fence 8,475 LF $ $
32 31 30 2-Rail H-Brace 8 EA $ $
32 31 30 3-Rail Corner Post 8 EA $ $
9 32 31 30 Walk-Thru Gate 8 EA $ $
10 32 31 30 Steel Post and Cable Fencing 8,475 LF $ $
TOTAL FOR SCHEDULE A $
END OF SUPPLIES OR SERVICES AND PRICES / COSTS
SECTION C
DESCRIPTION / SPECIFICATIONS
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work required under this contract is located on the south and north sides of Lake
Thunderbird. The reservoir is located east of Norman, Oklahoma on S.H. 9 in Cleveland
County, Oklahoma.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Property boundary surveying.
B. Construct new 5-strand barbed wire fence including T-posts, corner posts, and H-braces.
Clearing areas as necessary to construct new fencing.
C. Construct steel post and cable fencing at designated locations. Clearing areas as necessary to construct new fencing.
D. Locations of features on the drawings are approximate. Exact locations of items to be constructed or installed shall be approved by COR once surveying and clearing work has been completed.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.
1.04 DEFINITIONS
A. When the specifications use a word or term defined in the Federal Acquisition
Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CO: Contracting Officer
Summary of Work
01 11 00 - 2
2. COR: Contracting Officer’s Representative
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
4.03 CONSTRUCTION COMPLETION
A. Construction period is 250 calendar days from the receipt of the Notice to Proceed, for all work. No work is to be performed on weekends or Federal holidays.
END OF SECTION
Norman Project, Oklahoma Solicitation No.
Work Restrictions
01 14 12 - 1
SECTION 01 14 12
WORK RESTRICTIONS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 WORK RESTRICTIONS
A. Work hours:
1. Monday through Friday, 7 am to 7 pm.
2. Additional hours per COR approval. Request in writing and be approved 7 days in advance.
3. Additional days per COR approval. Request in writing and be approved 21 days in advance.
B. Allow public access to Lake Thunderbird State Park throughout construction.
1. Includes use of public roads and campground areas.
2. Maintain public use of all roadways and access to and from campgrounds during construction.
C. All work performed under this contract is accessible via public roads or Federal lands.
D. Contractor shall allow Reclamation 90 days to review the completed boundary survey prior to clearing areas requiring survey. Contractor shall not begin clearing, demolition or fencing areas requiring survey prior to receiving written approval of the survey by
Reclamation.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Project Management and Coordination
01 31 19 - 1
SECTION 01 31 19
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in the prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 31 19-1, Work Plan Summary.
1. Summary of upcoming work and traffic plans for next 60 days.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 PROJECT COORDINATION
A. The following meetings are considered significant, but do not relieve Contractor from the responsibility of other meetings required outside this section.
B. Schedule Update Joint Review Meeting:
1. Meet weekly with COR to review work, progress made, difficulties in performing work, and resolution necessary to meet specifications requirements.
2. Meetings include review of construction program work and updating of progress reports.
Project Management and Coordination
01 31 19 - 2
C. Work Plan Summary:
1. Prepare written monthly summary of work plans. Provide summary to COR at least 7 days before the start of the month
D. After survey and clearing has been completed, Contractor shall stake locations for new fencing, H-Braces, Corner Braces, Gates, Pipe Rail Fencing, and Post and Cable Fencing in accordance with Section 32 31 30 – Barbed Wire Fencing, Steel Post and Cable
Fencing, and Gates. Once staking is complete, Contractor shall contact COR a minimum of seven days prior to starting fence construction to schedule an on-site meeting to review all fence locations. Contractor shall not construct new fencing prior to receiving written approval from COR.
3.02 STAGING AREAS
A. Contractor may store materials and equipment within cleared firebreaks. Other unsecured staging areas may be available upon request to COR.
B. United States shall not be liable for damage to or theft of contractor materials or equipment.
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and
Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
C. Samples Submittals:
1. Label with complete manufacturer’s product and color identification.
2. Include type and quantity of materials specified in the referenced section in each
“set” of samples.
3. Samples: Representative of product to be installed.
01 33 00 - 2
4. Label each sample, sample kit with contract number and title.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
F. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe pdf on CD or DVD discs.
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
G. Samples and Color Selection Submittals:
1. Label with complete manufacturer's product and color identification.
2. Include type and quantity of materials specified in the referenced section in each
“set” of samples.
3. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.
4. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.
01 33 00 - 3
5. Label each sample, sample kit, set of color chips, or color chart with contract number and title.
6. The Government will select architectural color and pattern after product approval.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit number of sets specified in “Sets to be sent to:” columns in Table 01 33 00A - List of Submittals.
1. Electronic submittals:
a. In Portable Document Format (.pdf).
b. Include RSN transmittal letter.
c. Do not include Personally Identifiable Information (PII) in electronic submittals.
d. Submittal method (size based):
1) Government can receive e-mails up to 10 MB. Receipt of e-mails exceeding 10 MB (extra-large) may be possible. E-mailing of extra-large electronic submittals may occur only after size limit for transmittal of extra-large email has been verified.
2) Electronic media for submittals too large for e-mail: CD or DVD.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 7 days after receiving comments, unless otherwise directed.
01 33 00 - 4
4. Requirements for initial submittals apply to resubmittals.
F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to extent that:
a. Approval was required under contract,
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR
52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Submittal response:
1. Response letter will indicate whether submittal is approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
01 33 00 - 5
1.07 TRANSMITTAL
A. Addresses for codes receiving paper copy submittals listed in Table 01 33 00A - List of Submittals:
1. CO, Bureau of Reclamation, Attention GP-5000 P.O. Box 36900, Billings, MT
59107-6900; Physical Address: 2021 4th Avenue North, Billings, MT 59101.
2. COR, Bureau of Reclamation, Attention OK-McCrackin, Oklahoma-Texas Area
Office, Oklahoma City Field Office, 5924 NW 2nd Street, Suite 200, Oklahoma City, OK 73127-6514.
B. E-mail address for electronic submittals listed in Table 01 33 00A – List of Submittals:
cmccrackin@usbr.gov.
1. Submit electronic submittals that are too large for e-mail along with paper copy.
C. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to COR, unless otherwise specified.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 33 00 - 6
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Responsible code
Sets to be sent: **
CO COR
1 Performance and Payment Bonds - Construction 52.228-15
Performance and Payment Bonds
Within 10 calendar days after award
CO 1
electronic
2 Additional Bond Security 52.228-2
Evidence of Increase in Bond Security
Within 10 calendar days after modifications increasing contract value
CO 1
electronic
3 Insurance-Work on a Government Installation 1452.228-70
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work
CO 1
electronic
4 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1
electronic
5 Equal Opportunity 52.222-26
Information required by Executive Order
112246 (SF-100)
Within 30 days following award
CO 1
electronic
6 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certification that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
CO 1
electronic
7 Schedule of Values
MB-1
Required for lump-sum items in the Bid Schedule
Submitted and approved before any payment other than bonds and insurance
CO 1
electronic
8 DOI-AAAP-0028
Electronic Invoicing and Payment Requirements (IPP)
DRAFT Invoice before entering into IPP
10 Days Prior to Payment Request
CO 1
electron ic
9 Release of Claims 1452.204-70
Release of Claims (DI-137) against the Government
After completion of the work and prior to final payment
CO 1
01 33 00 - 7
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Responsible code
Sets to be sent: **
CO COR
10 Labor Standards Data 52.222-11
1) List of subcontractors
2) Statement and acknowledgement Form (SF-1413) for each subcontract
Within 14 days after award of contract
COR 1
electronic
11 Payrolls and Basic Records 52.222-8
Copies of all payrolls Weekly for each week of contract performance
COR 1
electronic electronic
12 WBR 1452.237-80
Alt III – Security Requirements – Bureau of Reclamation – Alternate III
List of contractor and subcontractor employees
At least 10 days prior to arriving at worksite
COR 0 1
electronic
13 WBR 1452.237-80
Alt III – Security Requirements – Bureau of Reclamation – Alternate III
List of vehicles and equipment to be brought onsite
At least 10 days prior to arriving at worksite
COR 0 1
electronic
01 31 19-1 Project Management Work Plan Summary At least 60 days prior to starting work
COR 0 1
electronic
01 35 10-1 Safety Data Sheets Complete LHM and
SDS
At least 14 days before jobsite delivery of hazardous material
COR 0 1
electronic
01 35 10-2 Safety Data Sheets Updated LHM and
SDS
At least 14 days before jobsite delivery of hazardous material not previously listed
COR 0 1
electronic
01 35 20-1 Safety and Health Safety Program Submitted and accepted before commencing onsite work. See Section 3 of RSHS
COR 0 1
electronic
01 35 20-2 Safety and Health Monthly Accident Summary Report
First day of every month
COR 0 1
electronic
01 35 30-1 Contractors Onsite Safety Personnel
Resume At least 28 days before starting onsite work
COR 0 1
electronic
01 35 30-2 Contractors Onsite Safety Personnel
Safety Inspection Reports
Weekly COR 0 1
01 33 00 - 8
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Responsible code
Sets to be sent: **
CO COR
01 55 20-1 Traffic Control Traffic Control Plan At least 35 days before affecting public traffic
COR 0 1
electronic
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
At least 28 days before starting onsite work
COR 0 1
electronic
01 57 20-1 Environmental Controls
Fire Prevention Plan At least 28 days before starting onsite work
COR 0 1
electronic
01 57 30-1 Water Pollution Control
Water Quality Management Plan
At least 28 days before delivery or storage of oil
COR 0 1
electronic
01 57 30-2 Water Pollution Control
Pollution Prevention Plan
At least 28 days before delivery or storage of oil
COR 0 1
electronic
01 57 30-3 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
At least 28 days before delivery or storage of oil
COR 0 1
electronic
01 71 20-1 Surveying Surveying Plan At least 35 days before beginning survey work; At least 35 days before personnel change
COR 0 1
electronic
01 71 20-2 Surveying Resume At least 35 days before beginning survey work; At least 35 days before personnel change
COR 0 1
electronic
32 31 30-1 Fencing and Gate Certification At least 28 days prior to procuring
COR 0 1
electronic
32 31 30-2 Fencing and Gate Certification At least 28 days prior to procuring
COR 0 1
electronic
32 31 30-3 Fencing and Gate Certification At least 28 days prior to procuring
COR 0 1
electronic
32 31 30-4 Fencing and Gate Certification At least 28 days prior to procuring
COR 0 1
Safety Data Sheets
01 35 10 - 1
SECTION 01 35 10
SAFETY DATA SHEETS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials
B. MSDS: Material Safety Data Sheet.
1.03 APPLICATION
A. For the purposes of this contract, the definition of “materials delivered under this contract” in the clause at FAR 52.223-3, Hazardous Material Identification and Material
Safety Data - Alternate 1, includes materials delivered to the Government, materials incorporated into the work, and materials used by the Contractor during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and MSDS.
C. RSN 01 35 10-2, Updated LHM and MSDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material
Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on the original or previously updated LHM and MSDS before receipt of updated LHM and MSDS by the
Contracting Officer.
PART 2 PRODUCTS
Safety Data Sheets
01 35 10 - 2
PART 3 EXECUTION
Safety and Health
01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards.
Available on the Internet at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
2. FIST 1-1-12 Hazardous Energy Control Program.
Available on the Internet at:
www.usbr.gov/power/data/fist_pub.html
B. Occupational Safety and Health Administration (OSHA)
1. 29 CFR Part 1910 Occupational Safety and Health Standards
2. 29 CFR Part 1926 Safety and Health Regulations for
Construction. Available on the Internet at www.osha.gov
C. American Conference of Governmental Industrial Hygienists (ACGIH)
1. Threshold Limit Values (TLVs). Available at www.acgih.org
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 20-1, Safety program:
1. Submit a comprehensive, job-specific safety and health program in accordance with Section 01 33 00 - Submittals and in accordance with the requirements of
Section 3.3 of the Reclamation Safety and Health Standards (RSHS) and these specifications.
2. The Safety Program will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B of the RSHS, a http://www.osha.gov/ http://www.acgih.org/
01 35 20 - 2 comprehensive narrative for each applicable item in the outline and program elements contained in these specifications.
3. Generic company safety programs are not acceptable. The Safety Program must be site specific for this contract.
4. The Contractor’s Safety Program must be submitted and accepted by Reclamation prior to commencing onsite work, including mobilization.
5. The Safety Program Statement of Responsibility must state that “the contractor is responsible for ensuring that all work will be in compliance with Reclamation
Safety and Health Standards and these specifications.”
C. RSN 01 35 20-2, Monthly accident summary report:
1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.
2. Submit on the first day of every month.
1.04 SAFETY AND HEALTH
A. Comply with RSHS, local safety programs, and any other referenced safety and health standards. Perform work in accordance with the specific safety program elements and referenced standards.
B. Provide and maintain a work environment and procedures that will:
1. Safeguard the public, Government personnel, and Contractor employees from
Contractor operations and activities that are unsanitary, hazardous, or dangerous to health and safety.
C. For each operation requiring the use of heavy equipment, in addition to the use of backup alarms and high visibility vests, include in the Job Hazard Analysis specific steps to ensure the protection of onsite personnel (internal traffic control) from the hazards of being struck by or caught between moving equipment while working around such equipment. Possible methods of controlling said hazards may include radio communications, backup cameras and/or proximity devices, designated observers, etc.
Provide all appropriate safety barricades, signs, and warnings.
D. Comply specifically with all requirements contained in RSHS Section 3 - Contractor
Requirements.
E. Investigate and report all accidents, incidents and near misses in accordance with RSHS
Section 3.7.
F. When the Contractor fails or refuses to promptly correct a compliance directive, the
Contracting Officer may issue an order to stop all or any part of the work.
1. When satisfactory corrective action is taken, an order to resume work will be issued.
01 35 20 - 3
2. The Contractor shall not be entitled to extension of time or to claim for damage or to additional compensation by reason of ether the directive or the stop order.
3. Failure of the Contracting Officer to order discontinuance of any or all of the
Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
G. Disputes regarding safety and health issues will be settled in accordance with RSHS
Section 3.
H. The Contractor shall be responsible for providing medical and emergency assistance in a timely manner that is consistent with recognized emergency protocols.
1. In instances where local emergency responders are not readily available, the responsibility to provide emergency services shall default back to the Contractor.
I. The Contractor shall be responsible for insuring that Subcontractors comply with the requirements set forth in this specification, written programs, the regulatory standards and the industry standards incorporated by reference in the RSHS and OSHA standards.
J. Where there is conflict between the standards, the more stringent or restrictive shall be utilized.
K. The Contractor shall fully participate in the Contractor Safety Program Review meeting, according to RSHS Section 3.4.1. The Contractor Safety Program Review meeting will take place before the start of construction.
1. Include subcontractor management representatives.
2. The Safety Personnel shall be present, in order to discuss in detail the Safety
Program and Plans.
3. The COR, the Contractor's principal onsite representative, and designated members of respective staffs must participate in the Price Scheduled monthly safety meeting (JPSM) according to RSHS Section 3.4.2.
L. The minimum work crew at any time on the construction site shall consist of no less than two (2) people.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Contractor’s Onsite Safety Personnel
01 35 30 - 1
SECTION 01 35 30
CONTRACTOR’S ONSITE SAFETY PERSONNEL
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 30-1, Resume:
1. Contractor’s Onsite Safety Representative
C. RSN 01 35 30-2, Safety Inspection Reports:
1. List noted deficiencies, their abatement dates, and follow-up action for jobsite activities.
2. Base inspection report on findings of jobsite walk-through with Government personnel.
1.03 QUALIFICATIONS
A. Contractor’s Onsite Safety Representative:
1. Competent supervisory employee with appropriate level of safety related training and experience.
1.04 APPLICATION
A. Designate an employee as the Contractor’s Onsite Safety Representative prior to start of construction.
B. Contractor’s Onsite Safety Representative authorities, duties, and responsibilities:
1. Review and approve the Contractor’s Safety Program prior to submittal.
2. Responsible for effectively implementing the Contractor’s Safety Program
3. Full authorization to correct unsafe acts on the spot.
4. Prepare safety inspection reports.
5. Onsite during construction activities.
Contractor’s Onsite Safety Personnel
01 35 30 - 2
1.05 QUALITY ASSURANCE
A. Contractor’s Onsite Safety Representative:
1. The effectiveness of the Contractor’s Onsite Safety Representative in prosecuting the safety program will be subject to continued review and approval by the CO.
2. Should the Contractor’s safety effort be considered inadequate, the CO has the option to require the Contractor to employ a qualified Safety Professional.
B. Safety Program:
1. The effectiveness of the Contractor’s Safety Program will be subject to continued review and approval by the CO.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Reference Standards
01 42 10 - 1
SECTION 01 42 10
REFERENCE STANDARDS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Referenced editions of standard specifications, codes, and manuals form a part of this specification to the extent referenced.
B. These specifications take precedence when conflicting requirements occur between specifications and referenced standard.
1.03 JOBSITE REFERENCE STANDARDS
A. Maintain at fabrication site, a copy of referenced standard specifications, codes, and manuals required for work in progress at fabrication site. Make available for use by the
Government.
B. Maintain onsite, a copy of referenced standard specifications, codes, and manuals required for onsite work in progress. Make available for use by the Government.
1.04 AVAILABILITY
A. Code of Federal Regulation (CFR):
1. Available online, authorized by the National Archives and Records
Administration (NARA) and the Government Printing Office (GPO), at www.gpoaccess.gov/cfr/index.html.
B. Federal Specifications, Standards, and Commercial Item Descriptions; and Military
Specifications:
1. Copies of Federal Specifications, Standards, and Commercial Item Descriptions may be obtained from GSA Federal Supply Service, see the provision at FAR
52.211-1, Availability of Specifications Listed in the GSA Index of Federal
Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29.
2. Copies of Military Specifications may be obtained from Department of Defense, see the provision at FAR 52.211-2, Availability of Specifications, Standards, and
Data Item Descriptions Listed in the Acquisition Streamlining and
Standardization Information System (ASSIST).
01 42 10 - 2
C. Bureau of Reclamation Documents:
1. Reclamation Safety and Health Standards (RSHS), 2009 edition, may be downloaded at http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
a. Hard copies of RSHS, stock number 024-003-00204-6, may be purchased from The Superintendent of Documents at the U.S. Government Printing
Office (GPO), phone number (202) 512-1800.
1) GPO online bookstore:
http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber=
024-003-00204-6.
2. Bureau of Reclamation Standard Specifications are designated with an M-number. Copies of individual standards may be obtained from Bureau of
Reclamation, Attn 86-68170, PO Box 25007, Denver CO 80225-0007. Specify which standard(s) is needed when requesting a copy.
3. Bureau of Reclamation manuals and other publications including significant scientific, technical, and engineering works are available from the National
Technical Information Service (NTIS). Information regarding availability and pricing may be obtained by contacting NTIS at the following address:
United States Department of Commerce
National Technical Information Service
5285 Port Royal Road
Springfield, Virginia 22161
Telephone: (703)487-4650 or 1-800-553-6847
D. Industrial and Governmental Documents:
1. When a reference has a joint designation (e.g. ANSI/IEEE) these specifications generally cite the proponent organization (e.g. IEEE).
2. Addresses for obtaining industrial and governmental (other than Federal and
Bureau of Reclamation specifications and standards) specifications, standards, and codes are listed in Table 01 42 10A - Addresses for Specifications, Standards, and Codes.
http://www.usbr.gov/ssle/safety/RSHS/rshs.htm http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber=024-003-00204-6 http://bookstore.gpo.gov/actions/GetPublication.do?stocknumber=024-003-00204-6
01 42 10 - 3
Table 01 42 10A - Addresses for Specifications, Standards, and Codes
Acronym Name and Address Telephone
AASHTO American Association of State Highway and
Transportation Officials
444 North Capitol St., NW, Suite 249
Washington, DC 20001 www.aashto.org
(202) 624-5800
(800) 231-3475
AGC Associated General Contractors of America
333 John Carlyle Street, Suite 200
Alexandria VA 22314 www.agc.org
(703) 548-3118
AISC American Institute of Steel Construction
One East Wacker Dr., Suite 3100
Chicago, IL 60601-2001 www.aisc.org
(312) 670-2400
ANSI American National Standards Institute
1819 L. Street, N.W.
Washington, DC 20036 www.ansi.org
(202) 293-8020
APA/EWA APA-The Engineered Wood Association
P.O. Box 11700
Tacoma, WA 98411-0700 www.apawood.org
(253) 565-6600
ASME American Society of Mechanical Engineers
3 Park Ave.
New York, NY 10016-5990 www.asme.org
(800) 843-2763
ASTM ASTM International
PO Box C700
100 Barr Harbor Dr.
West Conshohocken, PA 19428-2959 www.astm.org
(610) 832-9585
AWS American Welding Society
550 NW LeJeune Rd.
Miami, FL 33126 www.amweld.org
(800) 443-9353
(305) 443-9353 http://www.aashto.org/ http://www.agc.org/ http://www.aisc.org/ http://www.ansi.org/ http://www.apawood.org/ http://www.asme.org/ http://www.astm.org/ http://www.amweld.org/
01 42 10 - 4
Table 01 42 10A - Addresses for Specifications, Standards, and Codes
Acronym Name and Address Telephone
CLFMI Chain Link Fence Manufacturers Institute
9891 Broken Land Pkwy, Suite 300
Columbia, MD 21046 www.chainlinkinfo.org
(301) 596-2583
IEEE Institute of Electrical and Electronics Engineers
3 Park Ave.,17th Floor
New York, NY 10016-5997 www.ieee.org
(212) 419-7900
NACE NACE International
1440 South Creek Drive
Houston, TX 77084 www.nace.org
(281) 228-6200
NEMA National Electrical Manufacturers Association
1300 N 17th St., Suite 1847
Rosslyn, VA 22209 www.nema.org
(703) 841-3200
NFPA National Fire Protection Association
One…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .