Start_of_Page_2_Amendment_0005_0005.pdf

PDF 150 KB Posted

Attached to
WY ALCOVA GENERATOR AIR HOUSING COOLERS
Solicitation number
140R6024Q0085
Issued by

About this file

This document is an amendment to Solicitation No. 140R6024Q0085 issued by the U.S. Department of the Interior Bureau of Reclamation. The amendment extends the deadline for proposal submissions to August 26, 2024 at 12 pm MDT and states that the government will not entertain further questions. It also clarifies that spare air coolers will be made available at the site for data gathering after award, field testing after delivery is required even if the new air coolers have been hydrostatically tested prior to delivery, and all proposals will be evaluated according to the statement of work requirements. The solicitation is for the procurement of new generator air housing coolers for the Alcova Powerplant.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 140R6024Q0085 Amendment No. 00005

Description of Changes: The following changes are hereby incorporated into and made a part of this solicitation:

1. Answer the following questions.

2. Extend the date for proposals until August 26, 2024 at 12 pm MDT.

3. The Government will not entertain further questions.

Receipt of Quotes: The hour and date for receipt of the quotes has changed to August 26, 2024 at 12 pm MDT.

Third Party: If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.

Q: Would USBR consider shipping the spare air cooler to the manufacturing facility in order to take a full dimensional inspection?

A: No. Spare Cooler can be made available at the site for data gathering after award.

Q: Is the field testing after delivery really necessary if the new air coolers have been hydrostatically tested at the manufacturing facility prior to delivery?

A: Yes.

Q: Is the supply of a replace-in-kind air coolers (same design) going to be evaluated higher than an alternate design?

A: All proposals will be evaluated according to requirements in specifications in the statement of work.

Q: Is there an incentive for USBR to accelerate manufacturing/delivery of the new air coolers to the Alcova Powerplant?

A: No.

File details come from the government source that posted it. Updated .