Site_Visit_Date_change_and_questions_1_Amendment_1_0001.pdf
PDF 113 KB Posted
- Attached to
- AVC Boone Reach 2 Federal contract opportunity
- Solicitation number
- 140R6023R0011
About this file
This document provides an amendment to solicitation number 140R6023R0011 for the AVC Boone Reach 2 project. The amendment announces a change to the site visit date and time, now scheduled for June 14, 2023 at 9am MST at the Southeastern Colorado Water Conservancy District office in Pueblo, Colorado. It also answers a question about the estimated completion date by referring readers to block 11 of the Standard Form 1442 and section I, paragraph I.17 for the period of performance. The solicitation is for the Department of the Interior Bureau of Reclamation for construction services related to the AVC Boone Reach 2 project.
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit Change and Questions from Solicitation No. 140R6023R0011 Amendment No. 0001
L.7 52.236-27 SITE VISIT CONSTRUCTION ALT I FEBRUARY 1995
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for – June 14, 2023 at 9am MST
(c) Participants will meet at – Southeastern Colorado Water Conservancy District
31717 United Ave Pueblo, CO 81001
(End of Provision)
1. Do you know what the estimated Completion date is?
Answer: Refer to Standard Form 1442, block 11 for period of performance and Section I, Paragraph I.17, FAR 52.211-10 Commencement, Prosecution and Completion of Work.
File details come from the government source that posted it. Updated .