DRAFT_Statement_of_Work-SJC_LR_Excavator_1.pdf
PDF 140 KB Posted
- Attached to
- SJC LONG-REACH EXCAVATOR
- Solicitation number
- 140R4025Q0069
About this file
This Statement of Work (SOW) details the Bureau of Reclamation's requirement for procuring one mid-size long-reach excavator for the Chama Field Division in New Mexico. The excavator must meet specific technical specifications, including a 220 HP engine with EPA Final Tier 4/EU Stage IV emissions standards, 26-foot arm length, 31-foot boom length, and an operating weight of approximately 68,700 pounds. Acceptable manufacturers include Case (CX300C), Caterpillar (330), John Deere (300G LC), and Volvo (EC300), with optional features such as a tilt bucket with hydraulic thumb, AM/FM radio, and HVAC systems.
Key procurement details include delivery within 210 days after contract award to the Chama Field Division, with FOB destination in Chama, New Mexico. The contract requires a five-year warranty, maintenance services for 60 months, and estimated annual operating hours of 320. Vendors must submit various documentation within 21 days of contract award, including a project schedule, manufacturer's excavator characteristics, and a dealer list for repairs and maintenance. The procurement is classified under NAICS code 333120 for Construction Machinery Manufacturing, with the government seeking a comprehensive solution that meets precise operational and technical requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 140R4025Q0069_Sources_Sought_-_SJC_Long_Reach_Excavator_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SJC Long-Reach Excavator
Statement of Work Bureau of Reclamation-Upper Colorado Region-Albuquerque Area Office
Chama Field Division-Procure One Mid-Size Long-Reach Excavator
NAICS code is 333120 Construction Machinery Manufacturing
ABBREVIATIONS, DEFINITIONS, AND ACRONYMS
The Bureau of Reclamation commonly used definitions are listed below:
AAO. - Albuquerque Area Office
BOR. - Bureau of Reclamation (Reclamation)
CFD. - Chama Field Division (Office)
CI. - Cubic Inches
CO. - Contracting Officer
CCA. - Cold Cranking Amps
COR. - Contracting Officer’s Representative
CS. - Contracting Specialist
FAR. - Federal Acquisition Regulation
GPM. - Gallons per Minute
HP. - Horsepower
LB. - Pounds (lb. or lbs.)
MDT. - Mountain Daylight Time
OGR. - Onsite Government Representative
PSI. - Pounds per Square Inch
RSN. - Required Submittal Number
SJCP. - San Juan-Chama Project
UCB. - Upper Colorado Basin
YD3. - Cubic Yards (CY)
FORWARD
The Bureau of Reclamation, Chama Field Division located in Chama, New Mexico has determined a need for the purchase of one mid-size long-reach excavator. The following paragraphs expand on the requirements for the long-reach excavator to be supplied under this procurement.
Long-Reach Excavator Intrinsic Characteristics
The following table list acceptable manufacturers of long-reach excavator which have the intrinsic characteristics as required under these specifications. Please see section entitled
“Substitutions” if providing equipment currently not listed in the table.
Manufacturers Equipment Table or Equal
Manufacturer Model and Description
Case Model No.: CX300C Long Reach Excavator
Caterpillar Model No. 330 Long Reach Excavator
John Deere Model No. 300G LC Long Reach Excavator (GS-30F-0013U)
Volvo Model No. EC300 Long Reach Excavator
Intrinsic characteristics are as follows:
A.) Standard Specifications:
1.) Engine:
a. Non-Highway Emission Standard: EPA Final Tier 4/EU Stage IV or Better
b. Net Rated Power (ISO 9249): 220 HP (±10 HP) at 1,900 RPM
(±25 RPM)
c. Displacement: 400 Cubic Inch (±20 CI)
d. Air Cleaner: Dual-stage dry type with safety element and evacuator value or equal
e. Hydraulics: 2 Variable-displacement axial-piston pumps or equal. Pilot pump is a single gear with a maximum flow rate of 8 gpm
(±1 gpm) and pressure setting of 580 psi
(±20 psi)
2.) Powertrain:
a. Transmission: 2-Speed propel with automatic shift or equal
b. Tracks:
i. Width: 32-Inch
ii. Shoes: Triple Semi-Grousers or better
iii. Adjustment: Hydraulic
iv. Guides and Chain: Center with Sealed and Lubricated or better
3.) Controls:
i. Pilot Levers: Short stroke, low-effort hydraulic pilot controls with shutoff
4.) Cooling:
a. Fan Type: Reversing electronic variable-speed fan drive or equal
b. Engine Coolant Rating: -30 Degrees F or better.
5.) Electrical Systems:
a. Voltage: 12 Volts
b. Alternator Rating: 300 amps, Min.
c. Number of Batteries: 2, minimum with disconnect and jump posts
d. Lighting (LED Upgrade): Per manufacturer’s requirements including a minimum of 2 lights on excavator boom
6.) Arm and Boom Dimensions (Heavy Duty Rated):
a. Arm Length, Minimum: 26-Feet (±2 Feet) Heavy Duty Rated
b. Boom Length, Minimum: 31 Feet (±2 Feet) Heavy Duty Rated
7.) Operating Weight (Heavy Counterweight):
a. Excavator w/ fuel and 32-inch shoes: 68,700 U.S. Pounds (±1,000 Lbs.)
b. Undercarriage Weight: 26,200 U.S. Pounds (±200 Lbs.)
c. Overall Width (32-inch shoes): 11 feet (±3 Inches)
8.) Serviceability:
a. Fuel Tank: 130 Gallons (±20 Gallons)
b. Engine Oil: 5 Gallons (±2 Quarts)
c. Diesel Exhaust Fluid (DEF) Tank: 8 Gallons (±2 Gallons)
d. Hydraulic System: 75 Gallons (±2 Gallons)
9.) Informational:
a. Decals: English and Spanish
b. Manuals (Hardcopy & Electronic): Separate English and Spanish
i. Service: One electronic and One paper copy.
ii. O&M: One electronic and One paper copy.
iii. Parts & Diagrams: One electronic and One paper copy.
iv. Specifications: One electronic and One paper copy.
v. Disassembly/Assembly: One electronic and One paper copy.
vi. Testing and Adjusting: One electronic and One paper copy.
vii. System Operations: One electronic and One paper copy.
viii. Troubleshooting: One electronic and One paper copy.
B.) Optional Features:
1.) Engine Items:
a. Automatic belt-tension device
b. Coolant heater and tank
c. Severe-duty fuel filter
d. Air pre-cleaner
e. Oil-Sampling valve
f. Fuel Shutoff Valve
g. Enclosed fan guard
2.) Upper-Structure:
a. Service handrails
b. Heavy counterweights matching long boom and arm
3.) Front Attachments:
a. Tilt Bucket with hydraulic thumb with side cutters and teeth
b. Attach quick couplers
4.) Operator’s Station:
a. ISO 12117 ROPS
b. AM/FM Radio
c. Adjustable independent-controls position (Levers-to-seat, seat-to-pedals)
d. Power outlet 12 volt with USB
e. HVAC heating and cooling of cab with heated seat with air suspension
f. Seat belt
g. Front windshield wiper with intermittent speeds
h. Gauges are illuminated include DEF
i. Horn, electric
j. Interior light(s)
k. LED Working Lights
C.) Maintenance and Warranty Requirements:
1.) Estimated Annual Operating Hours: 320 Hours
2.) Maintenance Services: 60 Months, at location of equipment
3.) Warranty Period: 60 Months (5-Years)
SUBSTITUTIONS
A.) If equipment or materials required by these specifications become unavailable, because of manufacturer/Government priorities or other causes, substitute equipment or materials may be used.
B.) Offeror shall state in the substitution request the following:
1.) Purpose for substitution.
2.) Describe in detail the equipment or materials being substituted and how they meet or exceed these specifications.
C.) Specifications determination as to whether substitution will be permitted and as to what substitute equipment or materials may be used shall be final and conclusive.
D.) If approved substitute materials are of less value to the Government or involve less cost to the Contractor than specified material, a contract adjustment will be made in favor of the Government. Where the amount involved or the importance of substitution warrants, a deductive modification to the contract will be issued.
E.) No payments more than prices offered in the schedule will be made because of substitution of one equipment type or material for another or because of use of one alternate equipment type or material in place of another.
WORKMANSHIP
A.) Accurately manufacture and fabricate materials in accordance with best modern practices and requirements of these specifications, notwithstanding minor errors or omissions therein.
B.) Package equipment and materials to include provisions which prevent components from damage, loosening, and/or failure from shocks or vibration during shipping.
SUBMITTALS
Submit the following for Government review or approval:
• Prepare in English.
• Label with contract number and title including RSN.
• Measurement Units: US Customary Units.
• Provide a unique transmittal tracking number for each submittal.
• Drawings and sketches shall follow the U.S. National CAD Standard, Version 6.
• Required certifications shall be performed by a registered professional.
• Manufacturer’s certifications shall be signed by authorized representative.
o Manufacturer’s certification for biodiesel fuel including percentage.
o Manufacturer’s certification for emission standards.
o Manufacturer’s certification for use of recycled products.
• Mark clearly all features and options being supplied under this submittal. Strike out all other data.
• Review of submittals:
o Time required: The Government will require a minimum of 14 days to review each submittal or resubmittal, unless otherwise specified.
o Excess Time: Should the Government require additional review time; the CO may extend the contract completion date to allow completion of work. Time extension will be to the extent that the excess review time caused delay to contract completion.
• Submit the following for Government approval or review.
o Submittal Types: A – Action requiring Government approval and
I – Informational requires Government written receipt.
o Submit to Cory Ulibarri (COR) at CUlibarri@usbr.gov one electronic copy for review.
Submittal Table
RSN Required Submittal and Description Due Date or Delivery Time Type
S1
Project Schedule shall include the proposed date and time for delivery and employee equipment orientation
Within 21 days after contract award. A
S2
Manufacturer’s Long-Reach Excavator characterizes shall include the following:
cab/flops, HVAC systems, Product and
Specification Data Sheets with certifications
Within 21 Days after contract award. A
S3
Manufacturer’s recommended dealer list for repairs, maintenance, and warranty work within 180 miles of Chama, New Mexico
Within 21 Days after contract award. A
S4
Manuals: Owner’s, Maintenance, Service, Parts and both hardcopies and electronic format. With final payment I
S5 Manufacturer’s Warranty Information With final payment. I mailto:CUlibarri@usbr.gov
DELIVERY AND SETUP
A. Equipment shall be FOB to Chama Field Division in Chama, New Mexico 87520.
Include all costs for shipping, setup, and orientation for Reclamation’s personnel.
Delivery shall occur within 210 days after contract award. Delivery shall occur Monday through
Friday between 7:30 AM to 3:30 PM MDT, except federal holidays. Notify Ms. Connie
Asuncion, Facility Operations Assistant forty-eight (48) hours prior to delivery of equipment:
Connie Asuncion, Facility Operations Assistant
Bureau of Reclamation
Chama Field Division
193 North Pinon Drive
P.O. Box 426
Chama, New Mexico 87520
(575) 756-2175
CAsuncion@usbr.gov
B. Equipment Operator Orientation: Supply shall provide a minimum one (1) hour of equipment operations and one (1) hour of general service requirements.
SERVICE AND MAINTENANCE
A.) Certified manufacturer servicing center within 180 miles of Chama NM 87520.
B.) Manuals – Repair and Diagnostic with trouble shoot codes and Part ID numbers provided upon delivery. (Hardcopy and Electronic copies)
WARRANTY
Equipment supplied under these contract specifications shall be under warranty where applicable to be free of such defects in workmanship as appears under normal use, service, operation, and when owned by the original purchaser.
A. Minimum Warranty Period: Five (5) years after the Government has accepted equipment or materials at F.O.B. destination.
mailto:CAsuncion@usbr.gov