GC_Fluid_Testing_for_Transformers_SOW_-(A)_0001.pdf
PDF 130 KB Posted
- Attached to
- Transformer Fluid Testing for Glen Canyon Power Pl Federal contract opportunity
- Solicitation number
- 140R4024Q0044
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to provide fluid testing services for approximately 40 transformers at the Glen Canyon Power Plant facility. The Bureau of Reclamation (BOR) is seeking a contractor to deliver test kits, conduct fluid analyses, and provide test reports for the transformers, which contain various types of fluids including natural ester, mineral oil, and silicone. The required tests include visual examination, color, dielectric breakdown voltage, dissipation factor, water content, neutralization number, PCB content, interfacial tension, relative density, furan compounds, particle count, corrosive sulfur, and other analyses, as specified by the applicable ASTM test methods. The contractor must have a valid ISO 17025:2017 certificate of accreditation and will be responsible for any retests at no charge to the government if issues arise with shipping the kits or testing the fluid. The contractor must provide the required submittals, including the ISO certificate, sample reports, and estimated timeline to set up the account and start processing the fluid testing.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R4024Q0044_Amd_0001.pdf | ||
| Sol_140R4024Q0044.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Transformers Fluid Testing for
Glen Canyon Power Plant
Amendment 001
Background
The Bureau of Reclamation (BOR), Glen Canyon Field Division (GC) is seeking to procure fluid testing for transformers throughout the Glen Canyon Power Plant facility.
Requirement
GC has requirement for testing fluid in approximately 40 transformers throughout GC power plant. Transformers are filled with one of the following natural ester fluid, mineral oil, or silicone liquid. This testing is done once a year on all fluid filled transformers. Contractor shall provide test kits, fluid analysis, and test reports for each transformer.
Test Kits
The Contractor shall deliver test kits within 5 business days of Reclamations request. Tests kits shall include the needed bottles and syringes to obtain the sample fluids, required forms to be filled out to perform appropriate testing, and all packaging needed to return test to the specified lab. BOR shall pay return postage. Test kits shall be sent to the address below.
Address for Test Kits
Glen Canyon Field Division, 805 Bureau Street, Page, AZ 86040
Attn: Marvin Yellowhair and Audie Blackwell
Testing
Fluid test kits will be sent to the Government by the Contractor. All fluid samples will be collected by Glen Canyon Field Division and returned to the Contractor for analysis.
Required Tests
The required tests listed below shall be ran on each transformer sample. Each test requirement must meet the listed ASTM test method.
Test Type ASTM Test Method Applicable Fluid Type
Visual Examination D1524 All
Color D1500 All
Dielectric Breakdown Voltage D1816 (2mm gap) All
Dissipation Factor D924 (25C or 100C) All
Water Content D1533 All
Neutralization Number D974 All
PCB Content D4059 Mineral Oil
Interfacial Tension D971 All
Relative Density (Specific Gravity) D4052 (15C or 25C) All
Furan Compounds D5837 All
Particle Count D6786 Mineral Oil
Corrosive Sulfur D1275 All
Oxidation Inhibitor D2668 Mineral Oil
Dissolved Gases D3612 All Pour Point ASTM D97 Natural Ester Fluid Viscosity ASTM D445 (40C) All Flash and Fire Point ASTM D92 Natural Ester Fluid
Analysis Reporting
Analysis reports for each transformer shall be provided in graphical as well as tabulated format.
Reporting data to be provided for each individual analysis as well as added with trending graphs to a comprehensive list for each transformer.
Comprehensive data to include graphical and tabulated information with dates associated with each fluid sample. Transformer information to include: manufacturer, serial number, manufactured date, power size (MVA or KVA), high voltage, low voltage, weight, equipment type, impedance, phase/cycle, liquid type, gallons, insulation temperature rise, bank number
(K7A, etc.), associated phase, and facility name. Additional analysis reports to include information on liquid level, sample temperature, and top fluid temperature during sampling.
Analysis results for each fluid sample shall be provided electronically.
Patrick Bald, pbald@usbr.gov
Marvin Yellowhair, myellowhair@usbr.gov mailto:pbald@usbr.gov
Quality Assurance Surveillance Plan (QASP):
All work shall be conducted in accordance with the requirements of this performance work statement and all defined ASTM testing methods. Laboratory must have and maintain a valid ISO 17025:2017 certificate of accreditation throughout performance of this contract.
If there are any issues with shipping the kits or testing of the fluid the contractor will be responsible for the retest at no charge to the Government.
Required Submittals with Quote
Contractor shall provide the following information with their quote.
• ISO Certificate of Accreditation
• Quote shall include an example of reports that are provided with each testing sample to show reports meet the above criteria.
• Estimated time frame to set up account and start processing fluid testing after receipt of award.
Incomplete offerors, that do not contain all the stated solicitation submittal requirements can be found non-responsive and may not be considered for award.