140R4021Q0071 – EBHD Rehab – Water Tank Inspections

Combined Synopsis/Solicitation Questions and Answers as of 8/5/2021

1. Can you tell us if all of the tanks can be emptied and available for inspection at the same time?

ANSWER: The three (3) steel tanks can be emptied and inspected on the same day. The steel tanks will then be refilled and the concrete tank will be emptied and can be inspected on the following day.