This is a Performance Work Statement (PWS) for maintenance and repair services under a Blanket Purchase Agreement (BPA) for SonTek and YSI water quality monitoring equipment. The contract is issued by the Department of the Interior, Bureau of Reclamation (Solicitation Number 140R3026Q0130) and covers an ordering period from October 1, 2026, through September 30, 2031.

The contractor shall provide all necessary personnel, facilities, equipment, and materials to maintain and repair nine specific models of SonTek brand acoustic Doppler current profilers, velocimeters, and flow meters, as well as YSI brand water quality meters including the Pro Swap, Pro DSS, and Pro30 handheld models. Devices will be shipped to the contractor's repair facility, and the contractor must complete repairs and return all items to the Blythe Hydrographic Office in Blythe, California within 60 business days of receipt. Prior to repair initiation, the contractor must submit cost estimates for government review and approval. The Quality Assurance Surveillance Plan requires repairs to be performed according to industry standards and best practices, with timeliness and quality measured by completion date comparison and technical staff review. All invoicing shall comply with DOI electronic invoicing requirements and FAR clause 52.212-04(g).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1-RFQ No. 140R3026Q0130 Page 1 of 2

PERFORMANCE WORK STATEMENT (PWS)

SonTek/YSI BPA

1.0 INTRODUCTION:

1.1 The Contractor shall provide all necessary and qualified personnel, facilities, equipment, transportation and materials required to provide maintenance and repairs, SonTek brand Meters and YSI brand water quality equipment in accordance with the equipment’s and manufacture’s recommendations. The Contractor shall ensure that good business and management practices are followed in performing the ordered services, such that the Government receives the greatest value for the services provided.

2.0 SCOPE:

TYPES OF SERVICES: This requirement shall cover requirements for maintenance and repair services for SonTek brand and flow displays monitoring meters provided by the Government, see items listed below, but not limited to only items on list. The Government may request quotes for additional models if current models become obsolete or new models are released.

The extent of the repairs needed is unknown and the contractor shall inspect and repair meters and displays in accordance with the equipment’s manufacture recommendations.

Line Item
Manufacturer
Model
Part Number
Description
1
YSI
Pro Swap
610152-30
Water Quality Meter
2
YSI
Pro DSS
626902
Water Quality Meter
3
YSI
Pro30 handheld
6050030
Conductivity Meter
4
SonTek
M9
M9
Acoustic Doppler Current Profiler
5
SonTek
S5
S5
Acoustic Doppler Current Profiler
6
SonTek
Flow Tracker 2
FT2-2D
Acoustic Doppler Velocimeter
7
SonTek
IQPlus
SON-IQP
Acoustic Doppler Flow Meter
8
SonTek
SL500
SL500-232
Acoustic Doppler Flow Meter
9
SonTek
SL15003G
SL1500-3G
Acoustic Doppler Flow Meter

3.0 PRODUCTS: Reclamation will be responsible for issuing BPA calls for required services as needed. The Contractor shall provide the parts and maintenance or services to Bureau of Reclamation (Reclamation).c4.0 LOCATION OF DELIVERY: Items shall be delivered to sent to the following location:

Office
Address
Blythe Hydrographic Office
US Bureau of Reclamation

Blythe Hydrographic Office 1064 E Hobsonway Blythe, CA 92225

5.0 GENERAL REQUIREMENTS: The required services to maintain and repair SonTek and YSI devices will be shipped to the Contractor(s) repair facility. The devices shall be repaired and returned within 60 business days of receipt from Reclamation. Once the item(s) to be repaired have been received and evaluated, the cost for the repair will be reviewed by Reclamation prior to acceptance. Once accepted and repaired, the item(s) shall be shipped back to the Reclamation facility address in section 4.

6.0 ORDERING PERIOD: October 1, 2026, to September 30, 2031

7.0 INVOICES: All invoicing shall be in accordance with clause DOI-AAAP-0028 Electronic Invoicing and Payment Requirements – Invoice Processing Payment Platform (IPP) and 52.212-04(g),

8.0. QUALITY ASSURANCE SURVEILLANCE PLAN: The plan is one evaluation method the government uses to perform surveillance to determine whether the Contractor meets the standards of performance as defined in the PWS. The absence of a QASP for any contract requirement, however, shall not detract from its enforceability or limit the rights or remedies of the government under any other provision of the contract in determining the quality of the Contractor performance.

(Continued on Next Page)

PERFORMANCE REQUIREMENTS SUMMARY

Performance Requirement Summary (PRS)
Paragraph No.
Acceptable Quality Level
Means of Measurement
Repair and return devices with all documentation/certification within 60 days
2.0 SCOPE
a. Timeliness – Repairs are provided in a timely manner

b. Quality – Repairs are performed according to industry standards and best practices.

Comparison of the completion date to need date

Reclamation technical staff review of completed repair