Sol_140R3025Q0103_Amd_0001.pdf
PDF 124 KB Posted
- Attached to
- E21 PRCA PIPELINE & ELECTRICAL COMPONENT
- Solicitation number
- 140R3025Q0103
About this file
This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a project involving pump, pipeline, and electrical components, issued by the Bureau of Reclamation's Lower Colorado Region. The amendment, numbered 0001 and effective 08/06/2025, provides responses to two specific questions from potential quoters: confirming that the HDPE pipe will use SDR 32.5, and specifying that branch saddles are for installing 2-inch air relief valves with 2" NPT threads. The quote submission deadline remains unchanged at 1500 PM PST on 08/29/2025, and potential quoters must acknowledge the amendment according to the instructions in Block 11 of the document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140R3025Q0103_Amd_0002.pdf | ||
| 140R3025Q0103-Combined_Synopsis_Solicitation.pdf | ||
| Sol_140R3025Q0103.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R3025Q0103 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Boulder City NV 89005
R30
500 Fir Street Regional Office Lower Colorado Region Bureau of Reclamation
08/06/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/06/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PROJECT TITLE: Pump, Pipeline, and Electrical Components
PURPOSE OF AMENDMENT: The purpose of this amendment is to provide responses to questions from potential quoters.
See Page 2 of 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Aimee Amador
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation No. 140R3025Q0103 Page 2 of 2 Amendment 0001 Questions & Answers
PURPOSE OF AMENDMENT: The purpose of this amendment is to provide responses to questions from potential quoters.
RECEIPT OF QUOTES: The date and time for receipt of quotes is NOT extended; the date and time for receipt of quotes is 1500 (hour) PM PST 08/29/2025 (date).
ACKNOWLEDGEMENT: See Block 11 above regarding how to acknowledge this amendment. The acknowledgement must be received at the place designated for the receipt of offers prior to the hour and date specified in the solicitation.
Questions and Responses:
Question-1:
¿To quote I will need to know what SDR they are looking for as I don¿t see it reference anywhere within either document?¿
Answer-1: The SDR for the HDPE pipe will be DR 32.5.
Question-2:
¿The electrofusion branch saddle I will need to know what they are reducing to?¿
Answer-2: The branch saddles will be for the installation of the 2-inch air relief valves with 2¿ NPT threads.
No new questions will be accepted.