Amendment_No__0002_Package_0002.pdf
PDF 246 KB Posted
- Attached to
- HEAT EXCHANGER IDIQ Federal contract opportunity
- Solicitation number
- 140R3023R0013
About this file
This amendment modifies the statement of work for a solicitation seeking offers for the manufacture of surface air coolers. The solicitation is issued by the Bureau of Reclamation under number 140R3023R0013.
The amendment changes the requirement for Delivery Order 1 by replacing the specifications with revised specifications. It also changes the project record deliverable from a set of DWG files to as-built prints. Offerors must acknowledge receipt of this amendment by the due date of September 15, 2023 at 4:00pm PDT in order to be considered for award. The amendment provides revised specifications for the manufacture of twenty surface air coolers of various types and sizes for use at the Davis Power Plant. It details requirements for tubes, fins, coatings, testing, and deliverables.
Offerors must submit proposals in response to the amended solicitation and revised specifications by the due date in order to be considered for award under this contract opportunity for the manufacture of surface air coolers for the Bureau of Reclamation's Davis Power Plant.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R3023R0013_Amd_0002.pdf | ||
| Amendment_No__0001_Package_0001.pdf | ||
| Sol_140R3023R0013_Amd_0001.pdf | ||
| 140R3023R0013_RFP_Final.pdf | ||
| Sol_140R3023R0013.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R3023R0013 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Boulder City NV 89005
R30
500 Fir Street Regional Office Lower Colorado Region Bureau of Reclamation
09/06/20230002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/28/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project Title: Heat Exchanger Recondition and Supply - IDIQ
Purpose of Amendment: The purpose of this modification is to change the requirement for
Delivery Order 1.
Description of Changes:
1. SOW Delivery Order 1 is changed as follows:
a. Table 1 - List of Submittals, Project Record is changed from set of DWG files to as-built prints.
b. Replace the Specs for Delivery Order 1 with Revised Specs for Delivery Order 1.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Virginia Toledo
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R3023R0013/0002
Receipt of Proposals: The date for receipt of proposals remains September 15, 2023, at 4 p.m.
local time. Proposals shall be emailed to vtoledo@usbr.gov with Solicitation No.
140R3023R0013 on the Subject Line.
Acknowledgement: See block 11 above regarding how to acknowledge this amendment. The acknowledgement must be received at the place designated for the receipt of offers. COMMERCIAL
ITEM (see Block 9 of the
Solicitation/Contract/Order for Commercial Items, Standard Form 1449).
Bid Modification: See block 11 above if you have submitted your bid and now desire to modify it or withdraw it.
Period of Performance: 10/01/2023 to 09/30/2028
**SUBMIT YOUR PROPOSALS TO VIRGINIA TOLEDO VIA
EMAIL AT VTOLEDO@USBR.GOV NO LATER THAN SEPTEMBER
15, 2023 @ 4PM PDT
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment 0002 Revised Specs
MANUFACTURE SURFACE AIR COOLERS
DAVIS POWER PLANT
FOREWARD
The Bureau of Reclamation (Reclamation), Lower Colorado Region, has a requirement for the manufacture surface air coolers at the Davis Power Plant.
Davis Dam spans the Colorado River between Arizona and Nevada near Laughlin, Nevada and Bullhead City, Arizona. The Davis Power Plant is on the Colorado River, immediately downstream from Davis Dam near the town of Bullhead City, AZ.
1.2 Scope of Work
The work performed under this contract includes manufacture of surface air coolers, delivery to and testing at the Davis Power Plant
1.2.1 Overview
1. Surface Air Cooler Common Specifications
A. Unless otherwise specified, each heat exchanger must be designed with points to attach lifting eyes for lifting and handling
B. If a proposed heat exchanger differs from the design criteria offered, the Offeror must submit marked copies of drawings clearly indicating the changes.
C. Headers and Water Boxes
1) Fabricated from carbon steel and same configuration as existing coolers.
2) Constructed with removable cover plates to permit access to all tubes for cleaning and inspection purposes without disturbing the water pipe connections.
3) An air-release valve shall be provided at the top of each cooler.
4) One water box will be provided with MPT suitable for connecting to the cooling-water piping either in a left- or right-hand position.
5) Location of connections shown on print apply to pass arrangements having both connections on the same end of coil.
D. The exterior metal surfaces, support frame, and water boxes will be primed, and finish coated.
1) Protection of adjacent surfaces and equipment. - Items or surfaces not required to be painted or coated, but which are adjacent to surfaces to be cleaned and coated, shall be protected against contamination and damage during the cleaning and coating operations. The contractor will install removable bolts in threaded holes before priming to ensure the internal threads remain clean. Newly coated items shall not be moved until the coating is dry through.
2) Damage caused by the Contractor. - Any items or surfaces which are, in the Contracting Officer's Representative’s opinion, damaged or contaminated by the Contractor's operations shall be returned to their original condition by and at the expense of the Contractor.
3) Temporary or permanent welding for the convenience of the Contractor shall not be done on areas where the welding will damage paint or other protective coatings unless the areas of coatings which would be damaged thereby are accessible for repairing and inspection. If such welding is approved by the Government, the Contractor must repair it to acceptable condition.
4) Primer Coat
a) The provided coating must be Sherwin-Williams DTM
Waterborne Acrylic Primer/Finish Coating, Series B66W1, an equivalent alternate product, or a superior product. The Offeror must provide documentation with their proposal establishing the proposed coating as equivalent or superior to the specified coating. Required documentation includes, but is not limited to, data sheets and SDSs.
b) The surface preparation and coating application must be as described in the coating’s information sheets.
c) The primer will be gray in color.
d) The contractor must apply one or more coats with a minimum 3-mil dry film thickness, unless provided documentation establishes better performance with another specification
5) Finish Coat
a) The coating must be Sherwin-Williams DTM Waterborne Gloss
Acrylic Coating, B66-100 Series, an equivalent alternate product, or a superior product. The Offeror must provide documentation with their proposal establishing the proposed coating as equivalent or superior to the specified coating. Required documentation includes, but is not limited to, data sheets and SDSs.
b) The surface preparation and coating application must be as described in the product’s information sheets.
c) The finish must be white in color.
d) The contractor must apply two or more coats with a minimum 3-mil dry film thickness per coat, unless provided documentation establishes better performance with another specification
6) The Contractor must send the COR the following information for approval before any coating work is commenced:
a) Coating systems identification
b) Product information sheets
c) Planned surface preparation
d) The contractor must supply Safety Data Sheets for all paints and chemicals applied to the heat exchangers.
E. Furnish and install new gaskets and hardware
1) All hardware (washers, nuts, bolts, and studs) replaced with new. ASTM specs per specification.
2) 60 durometer neoprene gaskets from one continuous piece of gasket material. The contractor must apply the gaskets to ensure the gaskets will seal with no seeping. The contractor must not splice or overlap gaskets.
3) The contractor must stamp each heat exchanger with individual identification including date/month/year of mfg. with permanent stamps.
F. The contractor must return the completed heat exchangers F.O.B. to Davis Dam Maintenance Yard Warehouse.
1) The contractor must pack, load, secure, and transport the heat exchangers.
2) The contractor will be responsible for any damage that may occur in the handling and transportation of the heat exchangers.
3) The Government will make a forklift and/or crane with an operator available for unloading the heat exchangers during regular warehouse hours at no charge to the contractor. The contractor must request use of the Government’s forklift and/or crane at least 72 hours prior to scheduled delivery times. This request must be sent to the COR identified following award.
4) Davis Dam shipping and receiving hours are from 7:00 A.M. to 4:30 P.M., AZ. Time, Monday through Thursday.
G. The Contractor must perform pressure tests at the Davis Dam facility prior to final acceptance.
1) The Contractor must hydrostatically test each heat exchanger to 60 psi for a minimum of 30 minutes or until inspection for a potential leak has been completed by Government personnel.
2) Minimum of Two heat exchangers will be tested simultaneously.
3) The contractor must provide all regulating valves, pressure gauges, and necessary connection pieces to complete the testing.
4) The contractor must submit documentation for each test.
5) Upon request, the Government will provide the following utilities at no charge to the contractor:
a) Water
b) Compressed air
c) Electricity
H. Documentation
1) Provide one (1) set of As-built prints.
2. The contractor will fabricate four (4) vertical generator air housing surface air coolers with four (4) pass design counterflow. Refer to Print P-8244228 Generator Surface Air Cooler
A. Cooling tubes
1) 164 straight tubes, six-foot eight-inches (6'-8"), (203.2 cm) in length with an outside diameter of 0.75 inches. (1.9 cm) and a nominal wall thickness of 0.049 inches. (0.124 cm). The cooling fins are 0.012 inch. (0.03 cm) thick and have an installed outside diameter of 1.5 inches (3.81 cm), with eight (8) fins per inch of tube length.
2) Cooling tubes will be Cupro-nickel 90/10 (90% Cu, 10% Ni), ASTM B359, C70600. The tube thickness will be equal to or greater than the equivalent nominal size type K copper tube. The contractor will attach the tubes to the tube sheets in a manner as to be free from any leakage. The contractor will provide tubes with copper fins, 0.015 inch thick. The copper fins will be tension-wound and fastened securely to the tube by solder dipping. The molten solder will be a lead-free material.
3) Prior to ordering the tubing, it will be the responsibility of the contractor to verify the exact length necessary, the portion of tube to be finned, and the location of the tube support collars.
4) Prior to placing the fins on the tubes, each tube will be hydrostatically pressure- tested to a pressure of 250 PSIG for a minimum of 5 minutes. The contractor will reject tubes that leak or cannot maintain the pressure.
3. The contractor will fabricate two (2) horizontal ventilation surface air coolers (C1) with six
(6) pass design. Refer to print CC-1/6
A. Cooling tubes
1) 108 straight tubes, six-foot (6'), (180.88 cm) in length with an outside diameter of 0.625 inches. (1.597 cm) and a nominal wall thickness of 0.049 inches. (0.124 cm). The cooling fins are 0.012 inch. (0.03 cm) thick and have an installed outside diameter of 1.5 inches (3.81 cm), with eight (8) fins per inch of tube length.
2) Cooling tubes will be Cupro-nickel 90/10 (90% Cu, 10% Ni), ASTM B359, C70600. The tube thickness will be equal to or greater than the equivalent nominal size type K copper tube. The contractor will attach the tubes to the tube sheets in a manner as to be free from any leakage. The contractor will provide tubes with copper fins, 0.015 inch thick. The copper fins will be tension-wound and fastened securely to the tube by solder dipping. The molten solder will be a lead-free material.
3) Prior to ordering the tubing, it will be the responsibility of the contractor to verify the exact length necessary, the portion of tube to be finned, and the location of the tube support collars.
4) Prior to placing the fins on the tubes, each tube will be hydrostatically pressure- tested to a pressure of 250 PSIG for a minimum of 5 minutes. The contractor will reject tubes that leak or cannot maintain the pressure.
4. The contractor will fabricate Six (6) horizontal ventilation surface air coolers (C2) with eight
(8) pass design. Refer to print CC-2.
1) 192 straight tubes, four-foot (4'), (121.92 cm) in length with an outside diameter of 0.625 inches. (1.597 cm) and a nominal wall thickness of 0.049 inches. (0.124 cm). The cooling fins are 0.012 inch. (0.03 cm) thick and have an installed outside diameter of 1.5 inches (3.81 cm), with eight (8) fins per inch of tube length.
C70600. The tube thickness will be equal to or greater than the equivalent nominal size type K copper tube. The contractor will attach the tubes to the tube sheets in a manner as to be free from any leakage. The contractor will provide tubes with copper fins, 0.015 inch thick. The copper fins will be tension-wound and fastened securely to the tube by solder dipping. The molten solder will be a lead-free material.
3) Prior to ordering the tubing, it will be the responsibility of the contractor to verify the exact length necessary, the portion of tube to be finned, and the location of the tube support collars.
4) Prior to placing the fins on the tubes, each tube will be hydrostatically pressure- tested to a pressure of 250 PSIG for a minimum of 5 minutes. The contractor will reject tubes that leak or cannot maintain the pressure.
5) Location of connections shown on print apply to pass arrangements having both connections on the same end of coil.
5. The contractor will fabricate 2 (two) horizontal ventilation surface air coolers (C3) with six
(6) pass design counterflow. Refer to CC-3
A. Cooling tubes
1) 144 straight tubes, three-foot (3'), (91.44 cm) in length with an outside diameter of 0.625 inches. (1.597 cm) and a nominal wall thickness of 0.049 inches. (0.124 cm). The cooling fins are 0.012 inch. (0.03 cm) thick and have an installed outside diameter of 1.5 inches (3.81 cm), with eight (8) fins per inch of tube length.
2) Cooling tubes will be Cupro-nickel 90/10 (90% Cu, 10% Ni), ASTM B359, C70600. The tube thickness will be equal to or greater than the equivalent nominal size type K copper tube. The contractor will attach the tubes to the tube sheets in a manner as to be free from any leakage. The contractor will provide tubes with copper fins, 0.015 inch thick. The copper fins will be tension-wound and fastened securely to the tube by solder dipping. The molten solder will be a lead-free material.
3) Prior to ordering the tubing, it will be the responsibility of the contractor to verify the exact length necessary, the portion of tube to be finned, and the location of the tube support collars.
4) Prior to placing the fins on the tubes, each tube will be hydrostatically pressure- tested to a pressure of 250 PSIG for a minimum of 5 minutes. The contractor will reject tubes that leak or cannot maintain the pressure.
6. The contractor will fabricate 2 (two) horizontal ventilation surface air coolers (C4) with eight
(8) pass design. Refer to print CC-4.
1) 144 straight tubes, four-foot (4'), (121.92 cm) in length with an outside diameter of 0.625 inches. (1.597 cm) and a nominal wall thickness of 0.049 inches. (0.124 cm). The cooling fins are 0.012 inch. (0.03 cm) thick and have an installed outside diameter of 1.5 inches (3.81 cm), with eight (8) fins per inch of tube length.
tube sheets in a manner as to be free from any leakage. The contractor will provide tubes with copper fins, 0.015 inch thick. The copper fins will be tension-wound and fastened securely to the tube by solder dipping. The molten solder will be a lead-free material.
3) Prior to ordering the tubing, it will be the responsibility of the contractor to verify the exact length necessary, the portion of tube to be finned, and the location of the tube support collars.
4) Prior to placing the fins on the tubes, each tube will be hydrostatically pressure- tested to a pressure of 250 PSIG for a minimum of 5 minutes. The contractor will reject tubes that leak or cannot maintain the pressure.
7. The contractor will fabricate two (2) horizontal ventilation surface air coolers (C5) with four
(4) pass design. Refer to print CC-5.
1) 108 straight tubes, six-foot (6'), (180.88 cm) in length with an outside diameter of 0.625 inches. (1.597 cm) and a nominal wall thickness of 0.049 inches. (0.124 cm). The cooling fins are 0.012 inch. (0.03 cm) thick and have an installed outside diameter of 1.5 inches (3.81 cm), with eight (8) fins per inch of tube length.
2) Cooling tubes will be Cupro-nickel 90/10 (90% Cu, 10% Ni), ASTM B359, C70600. The tube thickness will be equal to or greater than the equivalent nominal size type K copper tube. The contractor will attach the tubes to the tube sheets in a manner as to be free from any leakage. The contractor will provide tubes with copper fins, 0.015 inch thick. The copper fins will be tension-wound and fastened securely to the tube by solder dipping. The molten solder will be a lead-free material.
3) Prior to ordering the tubing, it will be the responsibility of the contractor to verify the exact length necessary, the portion of tube to be finned, and the location of the tube support collars.
4) Prior to placing the fins on the tubes, each tube will be hydrostatically pressure- tested to a pressure of 250 PSIG for a minimum of 5 minutes. The contractor will reject tubes that leak or cannot maintain the pressure.
8. The contractor will fabricate Five (5) horizontal exciter surface air coolers (EC1) with four
(4) pass design. Refer to print CC-EC1.
1) 72 straight tubes, six-foot two-inches (6'-2"), (187.96 cm) in length with an outside diameter of 0.625 inches. (1.597 cm) and a nominal wall thickness of 0.049 inches. (0.124 cm). The cooling fins are 0.012 inch. (0.03 cm) thick and have an installed outside diameter of 1.5 inches (3.81 cm), with eight (8) fins per inch of tube length.
2) Cooling tubes will be Cupro-nickel 90/10 (90% Cu, 10% Ni), ASTM B359, tube sheets in a manner as to be free from any leakage. The contractor will provide tubes with copper fins, 0.015 inch thick. The copper fins will be tension-wound and fastened securely to the tube by solder dipping. The molten solder will be a lead-free material.
3) Prior to ordering the tubing, it will be the responsibility of the contractor to verify the exact length necessary, the portion of tube to be finned, and the location of the tube support collars.
4) Prior to placing the fins on the tubes, each tube will be hydrostatically pressure- tested to a pressure of 250 PSIG for a minimum of 5 minutes. The contractor will reject tubes that leak or cannot maintain the pressure.
9. Submittal Requirements – As detailed in the base contract, the Contractor must furnish, for approval, the submittals identified in Table 1.
Table 1 – List of Submittals
RSN
Provision, clause, or paragraph
Submittals Required
No. of sets sent to: (Contracting
Officer: CO) (Contracting
Due date/deliv ery time
C COR
2 1.H.6 Coating systems identification
Product information sheets
Planned surface preparation S f t D t
15 days prior to applying primer, paint, or chemicals
3 1.M.4 Hydrostatic pressure test for reassembled air coolers after delivery to site
Within 7 days of testing and prior to final acceptance
Project Record
Project Record
Set of As-built prints
0 1
Within 7 days after delivery
1) Address - The Contractor must provide one copy each of the submittals required by Table 1 (List of Submittals) to the following Government employees. Submittals shall be delivered by e-mail. TBD at time of Award
Contracting Officer (CO) e-mail:
Contracting Officer’s Representative (COR) e-mail:
2) Cost - All costs of furnishing submittals shall be at the Contractor’s expense and shall be included in the price bid schedule for other items of work.
10. Drawings/Specifications
A. P-8244228 Generator Surface Air Cooler B. CC-1/6 Horizontal ventilation surface air coolers C. CC-2 Horizontal ventilation surface air coolers D. CC-3 Horizontal ventilation surface air coolers E. CC-4 Horizontal ventilation surface air coolers F. CC-5 Horizontal ventilation surface air coolers G. CC-EC1 Horizontal exciter surface air coolers
File details come from the government source that posted it. Updated .