SS_Q_A_4_08_26_2.pdf
PDF 102 KB Posted
- Attached to
- CT SWITCHGEAR REPLACEMENT STAMPEDE PP Federal contract opportunity
- Solicitation number
- 140R2026R0007
About this file
This is a Sources Sought amendment providing clarifications on a powerplant electrical switchgear replacement project. The amendment extends the Sources Sought due date to 5:00 PM PDT on April 15, 2026, and answers four key questions regarding project scope and requirements.
The work involves removing and replacing four existing subpanels (DCA, DCB, D1A, and DCC) at a powerplant facility with 480VAC switchgear and below, though the facility operates two 4160VAC generating units. The DCA subpanel serves as the main station service distribution for the entire facility. The contractor must supply backup generator power as deemed necessary to maintain operations during the replacement work. Regular working hours are 7:30 AM to 4:00 PM, Monday through Friday, with any work outside these hours requiring two-week advance coordination with the Contracting Officer's Representative. Additionally, the contractor is responsible for providing restroom facilities and hand wash stations throughout the contract period. No 24-hour management is required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sources_Sought_Notice_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The purpose of this Sources Sought amendment is to provide answers to the following questions and extend the Sources Sought due date to 5PM PDT on April 15, 2026.
1) Does the work involve a high voltage substation?
The workplace is located at a powerplant with two 4160VAC generating units. However, the work involves replacing switchgear with 480VAC and under.
2) Verifying the work includes replacement of existing subpanels?
Correct, the work involves removing and replacing sub panels DCA, DCB, D1A, and
DCC.
3) Would the work involve supplying backup generator power?
Yes. The DCA subpanel is the main station service distribution for the entire facility. The contractor will be required to supply whatever backup generator power they deem necessary to complete the work.
4) Would the work require 24 hr. management?
No. Regular working hours are between 7:30AM and 4:00PM, Monday through Friday.
Work hours outside of normal business hours shall be coordinated with the COR two weeks in advance.
In addition to needing to provide backup power during this contract, the contractor will also be required to provide restroom facilities and hand wash stations.