This file is a Questions and Answers document for RFQ 140R2026Q0112 for the Klamath Project A Canal, addressing clarifications on proposal submission requirements, pricing, schedule, and technical scope.

Proposal and Pricing Requirements: The technical proposal is limited to 75 pages, excluding key personnel resumes, project experience lists, staffing plans, subcontractor letters of commitment, cover letters, tables of contents, and compliance matrices. Standard font sizes and margins are required; 11x17 pages for schedules are acceptable and count as one page each. Past performance references should total no more than seven, pulled from CPARS or submitted via contractor-created questionnaires; no template is required. This is a labor-hour contract requiring fully burdened labor rates on the price schedule with no applicable Service Contract Labor Standards wage determination. Contractors may add additional labor categories on a separate price schedule if desired. Travel will be reimbursed at actual cost; the price-per-trip estimate on the price schedule is for evaluation purposes only, assuming 2-3 day trips with no more than five travelers. A corrected Price Schedule (v3) has been issued addressing a formula error in Option Period 2.

Schedule, Scope, and Site Information: The period of performance spans approximately 2.5 years: one 12-month base year starting February 1, 2027, one 12-month option year, and one partial option period ending May 31, 2029; these dates are flexible pending award timing. Milestone reports, including the Biological Evaluation and Cultural Resources Report, are due within 18 months of contract award, currently anticipated as August 2028. No site visit is planned. Government-furnished information, including the A Canal appraisal study, engineering assessments, and prior cultural surveys, will not be provided before award; contractors may request specific information post-award at KBAO/Reclamation's discretion. The contractor is responsible for developing all required GIS data with potential KBAO/Reclamation assistance. The 2013 encroachment study and 2008 imagery represent the most current encroachment data available. Because work occurs on Reclamation-owned land, additional landowner access permissions are not required; private property access, if necessary, will be coordinated case-by-case through Reclamation or the Klamath Irrigation District.

View the file

Other files

File Type Posted
C5_5_Attachment_2_-_Price_Schedule_(v3)_0001.xlsx XLSX spreadsheet
Sol_140R2026Q0112_Amd_0001.pdf PDF
C5_5_Attachment_2_-_Price_Schedule_(v2).xlsx XLSX spreadsheet
C5_5_Attachment_1_-_A_CANAL-Encroachments_Map.pdf PDF
Sol_140R2026Q0112.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers – RFQ 140R2026Q0112 Klamath Project A Canal

General

1. Site visit. Will a site visit be held? – A site visit is not anticipated at this time.

2. Page limit (52.212-1 Addendum, item 4). Do the following count toward the 75-page Technical Proposal Approach limit: - No, the following do not count toward the 75-page limit. Key personnel resumes, the project experience list, the staffing plan/roster, subcontractor letters of commitment, cover letter, table of contents, and any compliance matrix? Are there required font size, margin, or page size requirements, and can 11x17 pages be used for schedules (and if so, do they count as one or two pages)? – Standard font size and margins are expected, and yes if 11x17 parges are needed, they can be used and count as 1 page each.

3. Past performance references (52.212-1 Addendum, item 5). How many references are wanted? If a survey or questionnaire is required, is there a template we should use, and who should we send the response to? – As many as the contractor believe are applicable and relate to the work in this requirement. However, try to keep it under 7 references and no there is no template you should use. You can pull CPARS or create your won questionnaire and submit to your references.

Price Schedule (Attachment 2)

4. Option Period 2 total. The Option Period 2 "Total" cell (P5) contains the formula =I43=R29, which returns TRUE/FALSE rather than a dollar amount. Will a corrected Attachment 2 be issued, or may quoters correct this formula? – Contractor may correct so P5 = R29. However, a corrected Price Schedule is attached (v3).

5. Travel. 52.212-4 Alt I states travel will be reimbursed at actual cost, while Attachment 2 requests a price per trip. Should the price per trip be an estimate for evaluation purposes only? Please also confirm the assumed trip duration and number of travelers, if any. – Correct, the price per trip is an estimate for evaluation purposes only. As for trip duration, it will vary depending on the need; however, we assume 2-3 days at most per trip, and no more than 5 travelers.

6. Wage determination. No Service Contract Labor Standards wage determination is attached. Please confirm whether one applies to this requirement. – This will be a labor hour contract, and we ask that contractors provide their fully burdened labor rates on the Price Schedule. Since we ask for fully burdened rates, there is no wage determination for this action.

7. Labor Categories. May we include additional labor categories in our price for our larger team, such as our NEPA resource experts? – We ask that Contractors do not alter the Price Schedule. Please fill it out in its entirety and submit with your quote package.

However, if a contractor would like to add other labor categories, we suggest they create a separate Price Schedule and include those labor categories with applicable rates and provide both Price Schedules for evaluation.

Schedule and Period of Performance

8. End date. The PWS Period of Performance paragraph references "date of award to" the end of Option Period 2, while PWS 1.0 and Attachment 2 show the Base Year beginning 2/1/2027 and Option Period 2 ending 5/31/2029. Please confirm the anticipated award date and the 5/31/2029 end date. – The Period of Performance paragraph in the PWS specifically states: “The contract will cover approximately a 2-½ year period. The period of performance shall be for one (1) Base Year of 12 months, one (1) 12-month option year, and one (1) partial option period extending from end date of OY1 to 5/31/2029.” We anticipate a start date of Feb 2027 and a completion date of May 2029, but these dates are flexible depending on when the award can be made.

9. Milestones. PWS Table 1 lists the Biological Evaluation and Cultural Resources Report as due 18 months after award (June 2028). With a 2/1/2027 start, 18 months would be approximately August 2028. Which date should quoters plan to? – The milestone dates provided are estimates only. All required reports would be due within 18 months of contract award, which is currently anticipated to be August 2028.

Technical

10. Government-furnished information. Will the A Canal appraisal study, existing engineering and condition assessments, prior cultural resources surveys, and GIS data be provided to contractors? Can any of these be made available before the quote due date?

- After consulting with KBAO's Engineering Department, we confirmed that the A Canal appraisal study, along with existing engineering and condition assessment documents, are internal KBAO/Reclamation documents and are not routinely released. In addition, no government-furnished information will be made available to prospective contractors prior to contract award. Some of the information may contain proprietary or otherwise sensitive material and therefore will not be considered for release until after a contract has been awarded. Following award, the contractor may submit requests for specific information, and KBAO/Reclamation will determine what information, if any, can be provided.

After contract award regarding previous cultural resource surveys, if surveys were conducted during the more than 100 years since construction of the A Canal, the contractor would be responsible for conducting a detailed records search.

KBAO/Reclamation may be able to assist with that effort as appropriate.

Regarding GIS data, KBAO/Reclamation can assist in providing available information; however, the contractor will be responsible for developing and producing all required GIS data. This is the reason for including a GIS/Graphics Specialist among the required personnel.

11. Encroachment map. Attachment 1 reflects the 2013 encroachment study and 2008 imagery. Is a more recent encroachment inventory available? - The 2013 encroachment study and 2008 imagery represent the most current encroachment data available to KBAO, with the exception of certain very site-specific surveys that remain internal to KBAO/Reclamation. Again, Contractors may submit requests for specific information; however, KBAO/Reclamation retains the discretion to determine what information, if any, will be released.

12. Landowner access. Will Reclamation or the Klamath Irrigation District assist with right-of-entry or notification letters to private property owners along the canal, or is this solely the contractor's responsibility? - Because the proposed work will occur on Reclamation-owned land, no additional access permissions should be required to complete the scope of work. If access to private property becomes necessary, requests for entry would be coordinated through Reclamation or the Klamath Irrigation District on a case-by-case basis, depending on site-specific circumstances or requirements.