Amendment_0001_to_Solicitation_140R2025Q0009_0001.pdf
PDF 2 MB Posted
- Attached to
- Keswick PP Asbestos Abatement and Floor Install
- Solicitation number
- 140R2025Q0009
About this file
This document is an Amendment (Number 0001) to a federal solicitation for asbestos abatement and floor installation at the Keswick Powerplant in Redding, California. The amendment modifies the original solicitation (140R2025Q0009) issued by the Bureau of Reclamation's Mid-Pacific Region, providing clarifications and updates to the project requirements. Key modifications include revising the Statement of Work and addressing contractor questions about the project scope, which involves removing asbestos-containing floor tiles and mastic from Rooms 506, 508, 509, and the Security Room, and then installing new vinyl composition tile (VCT) or carpet tiles.
The amendment includes detailed responses to contractor questions about project logistics, such as security procedures, vehicle access, background checks, and work phasing. The project requires a contractor with a California C-22 Asbestos Abatement license, who will perform the work in three phases, with strict requirements for containment, air monitoring, and disposal of asbestos-containing materials. The total floor area to be treated is approximately 3,240 square feet, with a 90-calendar day performance period after Notice to Proceed. Contractors must submit various documentation, including a safety plan, licenses, abatement plan, and waste disposal plan, and must follow specific removal and installation procedures to minimize asbestos fiber release.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R2025Q0009 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815
R20
Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation
03/19/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/19/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. TITLE: Keswick Powerplant Asbestos Abatement and Floor Installation
B. PURPOSE: The purpose of this amendment is to incorporate various changes to solicitation documents.
C. DESCRIPTION: Amendment 0001 Description of Changes:
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Matthew Thomas
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
1.) Offeror's Questions and Answers
2.) Revised Section C - Statement of Work
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment No. 0001
Solicitation No. 140R2025Q0009
Keswick Powerplant Asbestos Abatement and Floor Installation
Offeror Questions and Answers
1. Question: What is the process for security? I saw the security procedures mentioned in the solicitation however, I did not see any specific guidelines.
Response: Provide a list of names, proof of the right to work in the U.S. (if a foreign national), and copies of government-issued identification of employees who will be onsite for the project.
The OGR will accompany employees throughout the project.
2. Question: Can vehicles be driven into Keswick Powerplant with all necessary equipment?
Additionally, do we have to check in each item and check out as we enter and exit?
Response: One vehicle can be driven to the parking area adjacent to the powerplant as there is not much available parking. All other vehicles will remain in the gravel parking lot at the
Keswick Office Building near the powerplant. The OGR will be visually monitoring the equipment that is brought in and removed. Additionally, pets are not allowed onsite.
3. Question: Are background checks required for workers?
Response: No, but the government has the option at any time to perform a background check on any personnel on our site.
4. Question: Will all contents that are not bolted down or built in place be removed prior to the abatement contractor’s mobilization.? This includes all loose contents, desks, computers, printers, shelves, cab, and all items hanging on the walls that are not permanent.
Response: Items not bolted down will be removed by BOR employees as long as removal of the items doesn’t affect operations. Items that cannot be moved must be adequately protected by the contractor from contractor-generated dust, debris, and excessive heat. BOR personnel will advise during the item protection stage (i.e., when wrapping components in protective plastic).
5. Question: In the high-voltage control room, are the switch gears and high voltage control cabinets sensitive to vibration (the same as in the other power plant control rooms we have completed abatement in)? If so, please clarify the need for all quoters to take extreme caution not to bump hit the panels with tools when removing the floor tile.
Response: Please take extreme caution when working near any equipment that cannot be removed from the project area by minimizing use of vibrating tools and/or tools that create a sharp impact. Also be cognizant that all handles, knobs, pushbuttons, etc. should not be touched while performing asbestos abatement and flooring work.
6. Question: Per the SOW its states the work will be completed in two phases. It also expresses the need to allow access to pass through Room 509 to access 512. That being said, once abatement has started in room 509, it must stay under negative pressure and is restricted to asbestos authorized employees only. This causes the need for a third phase to accommodate this request. Is the government willing to revise SOW to accommodate a third phase?
Response: The SOW will be revised so Room 512 can be completely closed off from access.
Appendix B BOR-Proposed Asbestos Phasing is attached.
7. Question: During the site visit, we’ve observed that a worker will need access to at least 1/2 of the control panel at all times, which will require the need of a fourth phase for area containment and same day results for air clearances. Please advise the need for a minimum of three to four containments phases, and requirement for a third party CAC who will test and read the samples with same day results. Please see the proposed air plan below:
Response: As stated in SOW Section 2.1.9, a third-party CAC is required and clearance air monitoring will be completed within 48 hours. The SOW will be revised to reflect three phases.
Appendix B BOR-Proposed Asbestos Phasing is attached.
8. Question: Please confirm if you want the contractor to provide the third part air testing and sampling in our quote submission for this solicitation.
Response: Yes, please include third-party air testing and sampling in the quote.
STATEMENT OF WORK
Keswick Powerplant Asbestos Abatement
Northern California Area Office, Bureau of Reclamation
Shasta Division, Central Valley Project, California
November 1, 2024
1. BACKGROUND/PROJECT CONDITIONS
1.1. Background: The Keswick powerplant has four locations for asbestos abatement and new floor installation: Rooms 506, 508, 509, and the Security Room (entered from Room 509).
1.1.1. Phase 1: The powerplant floor is concrete. In Rooms 506, 508, and 509, the concrete floor is covered with vinyl tile and mastic adhesive that has tested positive for the presence of asbestos. This flooring tile, baseboards, and mastic must be removed. The
Security Room has residual asbestos in the mastic that’s beneath the carpeting. The baseboard and carpeting must be removed and disposed of, and the mastic on the concrete floor must be removed. Phase 1 can be divided into sub-phases as shown in Appendix B: BOR-Proposed Asbestos Abatement and Reflooring.
1.1.2. Phase 2: Once all existing flooring has been removed and the space has been cleared of asbestos, new vinyl composition tile (VCT, color: “classic white” or equivalent) suitable for high-traffic areas shall be installed in Room 506, 508, and 509; carpet tiles (color: “startled” or equivalent) shall be installed in the Security Room.
Approximately 600 feet of new vinyl baseboard shall also be installed.
1.2. Access. Government personnel will remove existing furniture that doesn’t impact facility operations from all flooring surfaces prior to Contractor’s work. Contractor to verify from plans and at pre-construction site visit.
1.3. Testing. All flooring has not been tested for asbestos or other contaminants. Contractor shall assume that all flooring and adhesive material subject to this work contains asbestos.
2. SCOPE OF WORK
2.1. Contractor shall
2.1.1. Prevent contamination from dust and debris generated by flooring removal activities by providing containment:
• immediately around the work area
• for all fire alarm devices
• for all HVAC vents or grates such that contaminated air does not enter the
HVAC equipment o HVAC vents or grates may not be used for exhaust air from the contractor’s work
• for all stationary furniture and equipment that cannot be removed from the work area o Some of the stationary equipment contains circulation fans which need to be protected from distributing any dust generated by the asbestos removal process.
o Room 509 contains high voltage electrical equipment. This equipment must be contained such that no moisture enters the equipment. Extreme caution must be taken when using fluids to remove asbestos-containing material in this area.
2.1.2. Deleted
2.1.3. Remove contaminated and potentially contaminated material from surfaces designated by the government. The approximate floor surface areas are as follows, but must be confirmed prior to bid:
Location Area (ft2)
Room 506 110
Room 508 230
Room 509 2,140
Security Room 760
The surfaces are mostly accessible. There is ancillary equipment that may prevent direct access to some surfaces where flooring is to be removed. Contractor to verify from plans and at pre-construction site visit. Appendix A Asbestos Abatement and
Reflooring shows the approximate areas where flooring will be removed.
2.1.4. Employ asbestos material removal techniques that avoid unduly damaging the underlying building material.
2.1.5. Remove all asbestos containing materials within a full containment under negative air pressure of at least negative 0.020 inches of water. All removed materials and debris generated during removal (including but not limited to carpet) shall be properly packaged and labeled.
2.1.6. Properly encapsulate asbestos-containing surfaces that cannot be completely removed due to existing ancillary equipment.
2.1.7. Properly dispose of all removed materials in the Government-provided Hazardous
Waste Containers.
• The Government shall be responsible for the disposal of the waste placed in the
Hazardous Waste Containers.
2.1.8. After material removal, clean all surfaces inside the containment area to remove all particulate matter.
2.1.9. Provide an air-monitoring specialist (AMS) certified by EPA and California
Department of Safety and Health (DOSH) to conduct a final visual inspection and clearance air monitoring at the conclusion of abatement activities in each work area.
The Contractor shall contact the AMS a minimum of 24 hours prior to applying encapsulant for a visual inspection. Clearance air monitoring will be completed within 48 hours after the visual inspection and application of encapsulant. In the event that the AMS arrives on-site at the request of the Contractor and the area is identified to require additional cleaning or that the encapsulant requires additional drying time, the cost of the additional time required for the AMS will be the contractor’s responsibility. A minimum of 5 samples and 2 blanks will be collected from each work area and will be analyzed by phase-contrast microscopy (PCM). A copy of the Air Clearance shall be provided to the COR.
• The project is considered complete if all samples collected are less than 0.01 f/cc using the NIOSH 7400 method.
2.1.10. Properly prepare the space for installation of VCT (Rooms 506, 508, and 509), carpeting (Security Room only), and vinyl baseboard throughout each room and complete the installation.
3. ADMINISTRATIVE INFORMATION
This section covers the basics of day-to-day operations and normal hours of work.
3.1. Place of Performance. The work to be performed under this contract shall be performed at
Keswick Powerplant (16515 Keswick Dam Rd, Redding, CA 96003).
3.2. Period of Performance. The performance period shall be 90 calendar days after Notice to
Proceed. Period of Performance includes submittals, mobilization, demolition, disposal, installation, and de-mobilization.
3.3. Hours of Operations. The Contractor is responsible for conducting business, between the hours of 7:00 am-5:00 pm Pacific Standard Time, Monday thru Friday. The Contractor shall, at all times, maintain an adequate workforce for the uninterrupted performance of all tasks defined within this Statement of Work when the Government facility is not closed during the daily schedule above. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
3.4. Definitions. The follow acronyms, terms, and wording will be used throughout this
Statement of Work (SOW).
NCAO – Northern California Area Office
CO – Contracting Officer
COR – Contracting Officers Representative
Offeror – Prime Contractor
OGR – Onsite Government Representative
RSHS – Reclamation Safety and Health Standards
3.5. Post Award Meeting. A brief post award meeting will be held prior to commencement of work via Teams. The Contractor shall meet with the designated Bureau of Reclamation
Field Engineer and or Onsite Government Representative. The post award meeting shall provide the Contractor an opportunity to discuss and outline both the safety and work plans, ask any questions relative to the project, and to review the proposed time schedule.
3.6. Security. The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.
3.6.1. All vehicles entering the worksite may be subject to search by government security forces.
3.6.2. The Contractor shall maintain a current and updated list of authorized persons, including subcontractors, and provide a copy to the COR.
3.6.3. A list of ALL employees and copies of their driver’s license shall be provided to the COR before they are permitted on site.
4. CONTRACTOR REQUIREMENTS
The contractor and contractor personnel shall possess licenses, certificates, and training appropriate for removal of asbestos material.
4.1 Asbestos Abatement Activities. All asbestos abatement activities shall be carried out by a contractor with a current California C-22 Asbestos Abatement licensing classification.
Asbestos removal or repair work shall be performed by trained workers, knowledgeable in the hazards of asbestos, and properly trained in the use of personal protective equipment and engineering controls prior to the start of this project. The Contractor shall assume full responsibility and liability for any identified Asbestos Containing materials
(ACMs) that may be impacted during renovation activities that shall be removed or impacted and complying with all applicable federal, state, and local regulations pertaining to work practices, and protection of workers, visitors to the site, and persons occupying areas adjacent to abatement activities. The Contractor is responsible for providing medical examinations and maintaining medical records of personnel as required by the applicable Occupational Safety and Health Administration (OSHA) regulations. The Contractor shall hold the Bureau of Reclamation harmless for failure to comply with any applicable work, safety, health, or other regulations on the part of the
Contractor, the Contractor’s employees, or subcontractors. Where conflict between the regulations and this SOW exist, the most stringent requirements shall be followed.
Contractor shall be responsible to ensure all asbestos workers are compliant with state regulatory laws and federal laws regarding respiratory protection and asbestos abatement work.
4.2 Air Monitoring: Conduct daily monitoring that is representative of each employee working in the regulated area, unless all employees use supplied-air respirators operated in positive-pressure mode or a negative exposure assessment is performed.
4.3 Agencies: Impact to asbestos-containing materials is administered by state and federal regulatory agencies: (1) the California Department of Ecology, under the EPA’s National
Emission Standards for Hazardous Air Pollutants (NESHAP); (2) the California Division of Occupational Safety and Health (DOSH) for construction work and California
Department of Industrial Relations for exposure and worker relations and (3) the
Occupational Safety and Health Agency (OSHA); Contractor shall abide to these state and federal regulatory agencies.
4.4 Removal: The removal of asbestos-containing tile and mastics are regulated by DOSH as
Class II activities. Class II activities require that removal and disposal be conducted in accordance with 8 CCR §1529 and 8 CCR §5208. Workers must have a minimum of eight hours training regarding the hazards and proper removal methods specific to the material being abated, as specified in 8 CCR §1529 and 8 CCR §5208; or must be
California State Certified Asbestos Workers.
4.5 Certificates: A California State Certified Asbestos Supervisor must be present during abatement activities. Maintain a copy of this SOW on-site at all times during construction activities.
4.6 Other Materials: If additional suspect ACMs are encountered during renovation, demolition and/or construction activities, the material shall be treated as asbestos-containing until PLM analysis is conducted to characterize the material.
4.7 Hazardous Waste Training. Contractor personnel on the work site must possess current training certificates for HAZWOPER Supervisor training (40 hour) under 29 CFR
1910.120 (e) (4), and Worker training (24-hour; under 29 CFR 1910.120(e)(3)), as appropriate. All training documentation shall be provided to Contracting Officer
Representative (COR).
4.8 Deliverables. Deliverables to Reclamation will consist of electronic copies of the items specified below. Email address(es) will be provided upon Notice to Proceed.
List of Submittals:
RSN Submittal SOW
Section
Due # of sets to COR
1 Contractor Safety Program, including Certifications and JHA.
6.3, 6.5, 7.5.1
Prior to start of work 1
2 Licenses and Certifications 4.4, 4.5, 4.7, 6.5
Prior to start of work 1
3 Schedule 7.5.3 Prior to start of work 1
4 Abatement Plan to include CA and
EPA Abatement Notifications.
4.2, 7.5.4
Prior to start of work 1
5 Waste Disposal Plan 6.10, 7.5.5
Prior to start of work 1
6 VCT, carpet tile, and baseboard datasheets
2.1.10, 7.5.6
Prior to start of work 1
7 Final Report containing the post-abatement sample results for asbestos.
7.5.4 10 business days after completion
5. COMPLETION REQUIREMENTS
The Contractor’s schedule and plan of work may differ from the order of items described below except where specified.
5.1. Site Cleanup. Remove all construction waste/debris for recycle/disposal at appropriate facilities.
5.2. Final Acceptance Inspection of All Items
5.2.1. Review completion of work with OGR.
5.2.2. Make any corrective actions determined as required during Final Acceptance
Inspection.
5.2.3. Final Inspection may uncover items not discovered during previous inspections.
Contractor shall correct all pertinent items upon discovery.
6. GENERAL REQUIREMENTS
6.1. Cleanup and Disposal of Waste Material. The Contractor shall be responsible for all proper waste materials cleanup and disposal of rubbish generated by their work.
Hazardous Waste Containers will be provided by NCAO and will be checked weekly and removed weekly or as needed. All Hazardous Waste (ACM materials) will be collected in
NCAO-provided Hazardous Waste containers and sealed. NCAO will be responsible for the disposal of the Hazardous Waste generated. This does not include general construction waste for which the contractor is responsible.
6.2. Waste Characterization, Handling and Disposal Plan. Provide this plan in accordance with paragraph 6.5.3.
6.3. Safety and Health.
6.3.1. All contractor employees shall attend the local Hazardous Energy Control Program
(HECP) training before starting any work on site. This training takes approximately ½-hour.
6.3.2. Do not allow Contractor employees (including subcontractors), Government personnel, or the Public to be exposed to, or work under, conditions which are unsanitary, physically hazardous, or a potential exposure danger to their health or safety during performance of the contract.
6.3.3. Since this project will involve removal of asbestos material, ensure Contractor employees (including their subcontractors) and government personnel on site in the vicinity are protected from exposure to these compounds during the removal and disposal process.
6.3.4. The minimum work crew at any time on the construction site shall consist of no less than two people and shall be in accordance with other contractual obligations.
6.3.5. When violations of safety and health requirements contained in these specifications or referenced standards are called to the Contractor’s attention by the CO, COR, or the OGR, immediately correct the condition to which attention has been directed.
6.3.6. When the Contractor fails or refuses to promptly correct a compliance directive, the CO or the COR may issue an order to stop all or any part of the work.
• When satisfactory corrective action is taken, an order to resume work will be issued.
• The Contractor shall not be entitled to extension of time, nor to claim for damage or to additional compensation by reason of either the directive or the stop order.
• Failure of the CO, COR, or the OGR to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
6.3.7. Maintain an accurate record of, and report to the COR in the manner prescribed by the CO for all near misses, accidents or incidents, occupational diseases, traumatic injury, cases of death to Contractor employees (including subcontractors), Government personnel, or the Public, and any property damage occurring during the performance of work under this contract.
6.3.8. In the event there is a conflict between requirements contained in the Reclamation
Safety and Health Standards (RSHS), specification paragraphs, Contractor’s approved Safety Program, referenced safety and health codes, and standards, or the
U.S. Department of Labor Construction Safety and Health Standards, promulgated under Section 107 of the Contract Work Hours and Safety Standards Act (40
U.S.C. 327 et seq.), as amended, the more protective requirement having jurisdiction shall prevail.
6.4. First Aid and Communication:
6.4.1. Provide first-aid kits in accordance with Reclamation RSHS Section 5.
6.4.2. Make first aid and communication services available for providing emergency aid to employees and subcontractor employees.
6.5. Contractor's Onsite Safety Personnel:
6.5.1. Maintain records to comply with all applicable portions of CA Dept of Health, OSHA and EPA requirements, and other requirements of this specification.
6.5.2. Ensure Contractor (and/or subcontractor) personnel are currently licensed and registered with the State of California and have necessary training and personnel to perform Class II asbestos abatement work under the laws and regulations of
Title 8, Section 1529 of the California Code of Regulations (CCR) as a certified asbestos worker and as a Competent Person defined under 29 CFR 1926.1101.
• Contractor must demonstrate that they have (or will have) a sufficient number of skilled trades and licensed abatement workers who have successfully completed EPA model curriculum training in asbestos material abatement, so as to be able to complete all aspects of work covered.
• Contractor shall specify an on-site supervisor/competent person who is fully qualified in all aspects of asbestos abatement practices and procedures and meets all EPA/OSHA supervisor/competent person requirements.
6.5.3. Contractor shall ensure they have a respiratory protection program and current fit testing for all personnel and are providing medical examinations as per 29
CFR1926.1101, in addition the Contractor’s physician shall perform an evaluation of each workers ability to work in heat stress environments.
6.5.4. Contractor to perform air monitoring and sampling in accordance with California
Code of Regulations for ensuring compliance and providing copies of these reports upon request to the COR.
• Air sampling monitoring activities must be conducted by the Contractor or his duly authorized representative during asbestos abatement work or any other work involving asbestos-containing materials. The air monitoring frequency for Contractor operations shall at least be established in accordance with the requirements set forth in 29 CFR 1910.1001 and 29 CFR 1926.1101(f). The results of such sampling shall be posted and provided to the COR upon request within 24 hours after Contractor receipt of results. Contractor must ensure analytical result receipt no later than 5 calendar days after sample collection.
• The Contractor's air sample testing lab shall be an independent third party and certified for testing. Air sample analyses will be by methods described in the
CCR, and the results document must include interpretation of results.
• Air samples shall be taken every shift for the duration of the work shift at the
Contractor's expense. Additional samples must also be taken every time there is a change in the removal operation, either in terms of the location, the type of work, method of abatement, method of engineering control, change in the personnel completing abatement or other change in abatement process that might affect the exposure to asbestos of the workers. Sampling will be used to determine eight-hour exposure in accordance with the CCR. Copies of any air sampling will be provided to the COR.
• There is a need for an on-site safety representative, with at least 3-years of experience, 40-hour OSHA Construction Certification, first-aid, CPR, and
Blood Borne certifications. This person’s certifications need to be submitted with all certifications for approval.
6.6. Temporary Utilities: Applies to utilities available for use by the Contractor.
6.6.1. Electricity.
• Contractor shall coordinate with OGR for use of facility electrical power. If facility power is unavailable, Contractor shall provide required electrical power for construction.
• Remove temporary equipment and facilities upon completion of work.
6.6.2. Water.
• Government shall provide water required for abatement purposes. Contractor shall provide a backflow preventer at point of connection. Location to be coordinated with the OGR.
• Provide means of conveying water to points of use.
• Remove temporary equipment and facilities upon completion of work.
6.7. Vehicular Access and Parking.
6.7.1. Parking is available next to the jobsite building for one vehicle for Contractor use;
all other vehicles will be parked near the abandoned guard station on the access road
6.8. Protection of Existing Installations.
6.8.1. Provide protection for personnel and existing facilities from harm due to the
Contractor's operations. Protection shall be subject to approval of the Government.
6.8.2. Arrange protective installations to permit operation of existing equipment and facilities by the Government while work is in progress.
6.8.3. Do not discharge anything but clear water into onsite drainage system.
6.8.4. Repair, at Contractor's expense, damage to existing installations due to
Contractor's operations or Contractor's failure to provide proper protection. At the
Government's option, damage may be repaired by the Government, and the
Contractor will be charged for the repair costs.
6.9. Protection of Existing Utilities.
6.9.1. Dust Abatement.
• Contractor shall be responsible for damages resulting from dust originating from Contractor operations in accordance with clause at FAR 52.236-7
"Permits and Responsibilities."
6.9.2. Noise Control.
• Comply with all applicable Federal laws and regulations, and with applicable requirements of RSHS regarding the prevention, control, and abatement of harmful noise levels.
6.10. Hazardous Materials and Wastes. Remove and dispose of all hazardous materials and waste products encountered during construction.
6.10.1. Provide a Waste Characterization and Handling Disposal Plan. Include desired location of the Government-furnished hazardous waste container(s).
6.10.2. The Contractor will dispose of waste in Government-furnished hazardous waste containers and the Government will be responsible for the removal of the containers and appropriate disposal of the hazardous waste.
6.11 Emergency Services. In the event of an emergency, cellular service is limited.
Call 8588 Operations in the event of an emergency on any project phone or
9- 911. Provide the operator with the following address: KESWICK POWER
PLANT-16515 Keswick Dam Road, Redding, CA 96003.
7. SUBMITTALS
7.1. Schedule. The Contractor shall submit Required Submittal Notices (RSN) necessary to start work within 14 calendar days of the Notice to Proceed.
7.2. Review. The Government will review the Required Submittal Notices within 14 calendar days of official receipt.
7.2.1. Submittals will be returned as Approved, Conditionally Approved, or Not
Approved.
7.2.2. The Contractor shall resubmit Required Submittal Notices within 14 calendar days of receipt for Required Submittal Notices that are Conditionally Approved or Not
Approved.
7.2.3. The Government will review resubmitted Required Submittal Notices within 14 days of official receipt.
7.3. Address submittal.
7.3.1. Email to: Contracting Officer and COR. Email addresses will be provided with
Notice to Proceed.
7.4. Preparation:
7.4.1. Prepare in English.
7.4.2. Label with contract number, title, and RSN.
7.4.3. Measurement units: US Customary Units.
7.4.4. Sign and seal submittals requiring certification by a California registered professional.
7.4.5. Submittals must be reviewed by Contractor. Submittals without evidence of
Contractor's approval will be returned for resubmission.
7.4.6. Include the following information in transmittal letters:
• Contract number and title.
• RSN for each attached submittal.
• Responsible code.
• Identify submittal as initial or resubmittal.
7.4.7. More than one RSN may be submitted under a transmittal letter, provided the responsible code is the same.
7.4.8. Submittals not listed in this Statement of Work
• Submit in accordance with this section.
7.5. Submittal List and Requirements:
7.5.1. RSN-1, Safety Plan: Written Safety Program in accordance with Section 3 of the
RSHS.
• List of Employees:
Country of citizenship.
Duration and frequency on site.
Company affiliation and title/classification
• Cover all aspects of on-site and applicable off-site operations and activities associated with this contract.
• Program shall follow the format of the outline in Appendix 1.03C of RSHS
2024. Submittal will not be accepted for review by the COR/OGR unless it addresses, in order, lettered and numbered per Appendix B, a narrative for each applicable item in the outline.
• For items in the outline that do not apply to this contract write “Not
Applicable to Contract” next to the number/letter.
• Provide a list of Job Hazard Analyses (JHA) – outlines of work safety regarding protective equipment to be used/ required for removal of hazardous material.
7.5.2. RSN-2, Licenses and Certifications. Provide a list of licenses and certifications held by all employees and subcontractors.
7.5.3. RSN-3, Schedule. Provide a schedule showing all aspects of the work, from mobilization through demobilization.
7.5.4. RSN-4, Abatement Plan. Provide a plan according to regulatory requirements that removes the contaminated material safely and efficiently.
7.5.5. RSN-5, Waste Characterization and Handling Disposal Plan. Provide a waste characterization, handling, and disposal plan for asbestos-containing hazardous material, plus any additional materials that must be disposed.
7.5.6. RSN-6, VCT, Carpet Tile, and Baseboard Datasheets. Provide datasheets for the products to be installed.
7.5.7. RSN-7, Final Report. Report shall include copies of all change requests, sample results, and notes pertaining directly to abatement actions.
8. INSPECTIONS
8.1. Approvals. The COR will make a minimum of four (4) mandatory inspections during the abatement work. Each inspection must be requested by the Contractor to be performed by the COR. The COR must approve the inspected work before work may begin for the next phase of work. Failure on the part of the Contractor to obtain the CORs approval before proceeding to the next phase is regarded as a violation of the contract. The four inspections are as follows:
8.1.1. Work area preparation completed - Contractor shall have all Pre-Abatement preparations of the work area completed and approved by the COR before proceeding to the next step.
8.1.2. Completion of asbestos abatement – Contractor shall have all abatement work completed, inspected, certified clean by test results, and approved before moving to the next step.
8.1.3. Completion of final cleaning inspection - Contractor shall have the final cleanup of all visible debris, waste, dust, and residue approved before moving to the next step. The
Contractor shall perform final cleaning techniques in accordance with CCR requirements before requesting final clearance sampling. Final clearance sampling will not occur until all surfaces are completely dry.
8.1.4. Final Clearance Sampling. COR/Reclamation Safety Office will perform final clearance wipe testing after final clean-up activities are completed The Contractor shall notify the COR at least 24 hours in advance of the need for clearance wipe sampling.
8.1.5. A final punch list inspection is also required after all work is completed.
9. EXECUTION
9.1. Damages. All damages to the structure or property occurring as a result of any and all contract work and/or sub-Contractor work activities or actions shall be repaired or replaced at the Contractor’s sole expense, to the satisfaction of the COR/OGR Representative with no additional cost to the COR/OGR Representative. The Contractor will not be allowed any additional time allowances or extensions for any such circumstance or event.
9.2. General Removal. Procedures in accordance with 29 CFR 1926.1101
9.2.1. Flooring or its backing shall not be sanded.
9.2.2. Vacuums equipped with HEPA filter, disposable dust bag, and metal floor tool
(no brush) shall be used to clean floors.
9.2.3. Resilient sheeting shall be removed by cutting with wetting of the snip point and wetting during delamination. Rip-up of resilient sheet floor material is prohibited.
9.2.4. All scraping of residual adhesive and/or backing shall be performed using wet methods.
9.2.5. Dry sweeping is prohibited.
9.2.6. Mechanical chipping is prohibited.
9.2.7. Tiles shall be removed intact, unless the Contractor demonstrates that intact removal is not possible.
9.2.8. When tiles are heated and can be removed intact, wetting may be omitted.
9.2.9. Resilient flooring material including associated mastic and backing shall be assumed to be asbestos-containing unless an industrial hygienist determines that it is asbestos-free using recognized analytical techniques.
9.2.10. The material shall be thoroughly wetted with amended water prior to and during its removal.
https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=a7a786a167b63129a13d8b14c5465881&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=9053e4af44f9304ae664312df0bf0c88&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=d27e27807c140075daa088ba5d188a4e&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=98ab81808c05b3195400c14802d3d6d0&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=d27e27807c140075daa088ba5d188a4e&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=8ccef255a3f454011e3f8a805dfac967&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=5f19ed6d7d14e1d02b0d0e3d021bdf85&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=8ccef255a3f454011e3f8a805dfac967&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=07030e400428045ca51acfbd1a30e14b&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=15c6db3a551363fa59c8046cdd43c44d&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101
9.2.11. The material shall be removed in an intact state unless the employer demonstrates that intact removal is not possible.
9.2.12. Cutting, abrading or breaking the material shall be prohibited unless the employer can demonstrate that methods less likely to result in asbestos fiber release are not feasible.
9.2.13. Asbestos-containing material removed shall be immediately bagged or wrapped, or kept wetted until transferred to a closed receptacle, no later than the end of the work shift.
9.3 General Installation The Contractor shall be responsible to follow the manufacturer’s recommendations for installing or using their product, including but not limited to surface preparation prior to use, required clearances for product installation, and appropriate safety measures.
9.3.1 Install carpet tiles and baseboard in the Security Room
9.3.2 Install VCT and baseboard in Rooms 506, 508, and 509.
9.3.2.1 After installation, clean VCT and apply protective sealer while following manufacturer’s recommendations.
9.3.3 Remove all construction waste and dispose of properly.
10. REFERENCES
10.1. Bureau of Reclamation Documents:
10.1.1. Reclamation Safety and Health Standards (RSHS) may be downloaded at https://www.usbr.gov/safety/rshs/index.html.
10.2. Code of Federal Regulations:
10.2.1. 29 CFR 1956.1101
Available at https://www.law.cornell.edu/cfr/text/29/1926.1101
10.3. California Code of Regulations:
10.3.1. Title 8 Section 1529
Available at https://www.dir.ca.gov/title8/1529.html https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=d27e27807c140075daa088ba5d188a4e&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=98ab81808c05b3195400c14802d3d6d0&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=d27e27807c140075daa088ba5d188a4e&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=15c6db3a551363fa59c8046cdd43c44d&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=8ccef255a3f454011e3f8a805dfac967&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=35e5e9032da788ecceadced58014c742&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=8ccef255a3f454011e3f8a805dfac967&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=603344483c0fc536631c2bc904245b56&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.law.cornell.edu/definitions/index.php?width=840&height=800&iframe=true&def_id=13fcc9ce7e3476bbfe8f4d4eeded939e&term_occur=999&term_src=Title:29:Subtitle:B:Chapter:XVII:Part:1926:Subpart:Z:1926.1101 https://www.dir.ca.gov/title8/1529.html
Room
Room
Red = Asbestos Tile
ASBESTOS ABATEMENT & REFLOORING
Blue = Carpeting with Mastic
Room 509 Control Room
Security Room
PHASE 1A
PHASE 1B
PHASE 1C
aholland Line aholland Line aholland Line aholland Line aholland Line aholland Text Box Appendix B: BOR-Proposed Asbestos Abatement and Reflooring aholland Text Box Red = Asbestos Tile aholland Text Box Blue = Carpeting with Mastic