This is a Questions and Answers document from a pre-bid site visit held on August 27, 2024, for the Trinity River Division GSU Transformer Replacements project (Solicitation No. 140R2024R0002) issued by the Bureau of Reclamation's California-Great Basin Regional Construction Office.
The document contains a single question regarding concerns about firm-fixed pricing from transformer manufacturers, specifically about the possibility of adjustable pricing due to expected price escalations for future year supplies. The response directs bidders to Section I - Contract Clauses, Article FAR 52.216-2 Economic Price Adjustment-Standard Supplies, and indicates that BOR is exploring alternatives to allow for price adjustments, with further guidance to be provided in a future amendment.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Trinity River Division GSU Transformer Replacements Central Valley Project, California Solicitation No. 140R2024R0002
Questions from Pre-Bid Site Visit
CALIFORNIA-GREAT BASIN
REGIONAL CONSTRUCTION OFFICE
TITLE: Trinity River Division GSU Transformer Replacements
SOLICITATION NO.: 140R2024R0002
Questions/Answers during Pre-Bid Site Visit: 2024-08-27
1. There are some concerns regarding the firm-fixed pricing from transformer manufacturers. Is there possibility for adjustable pricing? There might be some sticker shock if not, as the manufacturers are escalating prices for future year values of supplies.
a. See Section I – Contract Clauses, Article FAR 52.216-2 Economic Price Adjustment- Standard Supplies.
BOR is pursuing available alternatives to allow for adjustment of prices and will provide further guidance in a future amendment.
1. There are some concerns regarding the firm-fixed pricing from transformer manufacturers. Is there possibility for adjustable pricing? There might be some sticker shock if not, as the manufacturers are escalating prices for future year values of sup...