About this file
This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the Kachess Dam Embankment Repair Materials project, issued by the Bureau of Reclamation's Pacific Northwest Region. The amendment addresses four contractor questions, providing clarification on project requirements: (1) contractors should price equipment to manage material piles at the dump site, with final material placement to be performed by the government; (2) no access roads need to be constructed; (3) no silt fence or wattles are required to be installed; and (4) there will be a location near the site where contractors can turn around a trailer, with the exact location and route to be coordinated after award.
The amendment is numbered 0002, dated 06/03/2025, and relates to solicitation number 140R1725Q0059. It maintains all other existing terms and conditions of the original solicitation, serving primarily to provide additional operational details and answer potential contractor inquiries about site-specific work requirements for the dam embankment repair materials project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 33-109-60030_Map_for_Material_Delivery_0001.pdf | ||
| Sol_140R1725Q0059_Amd_0001.pdf | ||
| Sol_140R1725Q0059.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R1725Q0059 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Grand Coulee WA 99133
R17
Hwy 155, PO Box 620 Grand Coulee Acquisition Group Pacific Northwest Region Bureau of Reclamation
06/03/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/03/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to answer questions.
Question #1. Do we need to have a price for having a machine up there to push up the piles at the dump site?
Answer #1. Yes, please price in some equipment to manage the piles. Final placement of the materials will be performed by the government, but since there is a lot of material, a piece of equipment to push the piles up would be helpful.
Question #2. Do we need to build any access roads?
Answer # 2.¿Contractor does not need to build any access roads.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Terry Mest
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R1725Q0059/0002
Question #3. Do we need to put the silt fence and wattles up along access road or anything like that?
Answer #3. Contractor will not need to install any silt fence or wattles.
Question #4 Can we get truck and trailer into the job? or solo dump access only?
Answer #4 There is a place the contractor can turn around a trailer near the site. We will coordinate with the contractor regarding the exact location and route once this is awarded.
All other terms and conditions remain the same.