This document contains questions and answers related to a solicitation for landscaping and grounds maintenance services. The solicitation is for a base year plus four option years to perform landscaping services at the Grand Coulee Power Office, including mowing a total of 2,859 acres across various locations. Clarification is provided that while the Performance Work Statement references appendices, the information is incorporated directly into the PWS. It is confirmed that the period of performance is from January 1st to December 31st each year, with the growing season considered April 15th to October 31st. There are only two animal waste stations included in the requirement, located at North Dam Park. The contractor will be responsible for irrigation system maintenance from the shutoff valves upstream of control valves.

View the file

Other files

File Type Posted
Sol_140R1722Q0002_Amd_0002.pdf PDF
PWS_Final_Landscaping_12_14_Revision_0002.pdf PDF
Sol_140R1722Q0002_Amd_0001.pdf PDF
222-117-15252_Pole_Park_Plantings.pdf PDF
222-117-15012_Roosevelt_Memorial_Park_Architectural_Site_Layout.pdf PDF
Attachment_3_-_List_of_Environmentally_Friendly___BioBased_Products.pdf PDF
222-117-15019_Roosevelt_Memorial_Park_Electrical.pdf PDF
1222-D-5225_VAC_Sprinklers_2.pdf PDF
1222-D-5197_VAC_Landscaping_Mis_.pdf PDF
GCPO_LANDS__2_North.pdf PDF
GCPO_LANDS__1_Total_Overview_and_Legend.pdf PDF
222-116-28994_Area_3_(Dragon_s_Tooth)_Sprinklers.pdf PDF
1222-D-6797_Industrial_Area_Admin_Area_Sprinklers_Details.pdf PDF
222-117-16643_Pump_Plant_Sidewalk_Planter_Section_Details.pdf PDF
222-117-15018_Roosevelt_Memorial_Park_Water_Supply_and_Drain.pdf PDF
GCPO_LANDS__3_East.pdf PDF
1222-D-5224_VAC_Sprinklers.pdf PDF
1222-142-4986_Industrial_Area_Both_Admin_Buildings_Sprinkler_and_Fence.pdf PDF
1222-D-5226_VAC_Sprinklers_3.pdf PDF
222-117-23249_Industrial_Area_New_Admin_Bldg_Sprinklers.pdf PDF
1222-D-5196_VAC_Grading_and_Layout_2.pdf PDF
1222-D-5198_VAC_Planting_Plan.pdf PDF
Sol_140R1722Q0002.pdf PDF
222-117-15030_Highway_155_Cut_Slope_(Industrial_Area)_Plantings.pdf PDF
1222-D-6796_Industrial_Area_Admin_Area_Sprinklers.pdf PDF
222-117-61422_Building_and_Structuring_Numbering.pdf PDF
222-117-19790_Industrial_Area_Admin_Bldg_Sprinklers.pdf PDF
GCPO_LANDS__4_West.pdf PDF
222-117-17797_Pole_Park_Sprinklers.pdf PDF
222-117-15653_Pump_Plant_Sidewalk_Planter_Sprinklers.pdf PDF
1222-D-5199_VAC_Planting_Plan_2.pdf PDF
1222-D-5195_VAC_Grading_and_layout.pdf PDF
1222-142-6639_Topo_Map_Banks_Dam___Feeder_Canal.pdf PDF
Attachment_2_Area_Descriptions_and_Photos.pdf PDF
222-117-15036_Highway_155_(Industrial_Area_Entrance)_Sprinklers.pdf PDF
222-117-15037_Highway_155_Cut_Slope_(Industrial_Area)_Sprinklers.pdf PDF
222-117-15031_Highway_155_Cut_Slope_(Industrial_Area)_Plantings_2.pdf PDF
222-117-15011_Roosevelt_Memorial_Park_Site_Features.pdf PDF
222-117-18571_Trailrace_Overlook_Layout_Plan.pdf PDF
1222-D-6801_Industrial_Area_Admin_Area_Planting.pdf PDF
222-100-340_North_Dam_Park_Rest_Area_Planting_Plan.pdf PDF
222-117-12727_Roosevelt_Memorial_Park_Sprinkler.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question:

There are many references to Appendices A, B, C, D, & E in the solicitation PWS. However, we do not find these documents posted. The exception to this is a document labeled “Attachment_2_Area_Descriptions_and_Photos” which may be Appendix B, albeit mislabeled.

Answer:

There are no appendixes as referenced in the PWS. The appendix language should have been removed with the final PWS version as the appendix information was directly incorporated into the PWS rather than having the extra attachments.

Attached to this amendment is an updated PWS showing deleted language in red wording with a strikethrough. See also the following sections for clarifications:

Section 3.4 Task 4 Unimproved area the title of Attachment 2 Area Descriptions and Photos was added to unimproved area 1 and 2.

Section 3.5 Task 5 Supplementary Area Spraying clarification in acreage size is made for:

• Transformer Decks

• Spreader-yards/Switchyards

• Transmission Towers

• Radio Repeater Control Building

Question:

Please provide information as to the total amount of acres to be mowed within the total of 2,859 acres that are represented in this PWS.

Answer:

Each location listed in the solicitation contains information on acreage and services required in each area.

Question:

Is there currently a CBA associated with this contract? If so, can we be provided with this information.

Answer:

No, there is no current CBA. The Wage Determinations incorporated in this PWS are applicable.

Question:

Can you please confirm that the service dates on this contract will be from January 1 to December 31?

Answer:

From PWS

1.4 Period of Performance: The period of performance will be for one (1) Base Year and four (4) option years. The Period of Performance reads as follows:

Base Year: January 1, 2022 through December 31, 2023

Option Year 1: January 1, 2023 through December 31, 2024 Option Year 2: January 1, 2024 through December 31, 2025 Option Year 3: January 1, 2025 through December 31, 2026 Option Year 4: January 1, 2026 through December 31, 2027 *Dates subject to change based on final award date will be listed on form SF-1449.

Actual work to be performed under this contract will be between March 1st to November 30th of each respective year.

The growing season at GCPO is normally considered to be from April 15th to October 31st, with the first planting historically after Mother’s Day weekend, depending on frost.

With regards to the animal stations, there are 2 listed as part of the requirements, are these the only 2 required under this contract or will the other 8 waste stations be included as well?

Answer: There are only 2 waste stations located at North Dam Park that are included in this solicitation. Other waste stations may be installed in the future, but the location and quantity have not been determined at this point.

At what point does the contractor take over the maintenance of the irrigation system? Will it be at the water main or at the valve boxes for each system?

Answer:

The contractor takes over maintenance at the irrigation shut off valve for each system, that is used for winterizing each system. The irrigation shut off valve is upstream of and typically near, but not necessarily in, the valve boxes containing the automated valves for each system.