Sources_Sought_Draft_Spec_Pages_2.pdf

PDF 899 KB Posted

Attached to
Grand Coulee Right Powerplant, GSU Transformer Replacements, Columbia Basin Pro
Solicitation number
140R1025R0005
Issued by

About this file

This is a draft specification document for the Grand Coulee Right Powerplant Generator Step-Up (GSU) Transformer Replacements project located at Grand Coulee Dam in Okanogan County, Washington, approximately 90 miles west of Spokane. The document outlines requirements for replacing three in-service, single-phase GSU power transformers.

The principal components of work include: manufacturing, factory testing and transporting three new GSU power transformers; removing and disposing of three existing GSU transformers including recycling insulation fluid and disposing of asbestos wiring; installing and commissioning the new transformers; furnishing and installing seismic anchorage systems; modifying the fire protection system; and modifying existing isolated phase bus connections. The work location can be accessed by rail through a Government-owned siding facility in Odair, Washington, approximately 30 miles south of the dam. The specification includes general requirements across multiple divisions covering electrical, thermal/moisture protection, fire suppression, plumbing, and other technical requirements for the transformer replacement project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior April 2026

Grand Coulee Right Powerplant

GSU Transformer Replacements

Columbia Basin Project, Washington

Columbia-Pacific Northwest Region 9 Draft

This page intentionally left blank.Draft

GRAND COULEE RIGHT POWERPLANT

Generator Step Up Transformer Replacements

Columbia Basin Project Washington

FOREWORD

Work is located at Grand Coulee Right Powerplant adjacent to the City of Grand Coulee, Washington, approximately 90 miles west of Spokane, Washington, in Okanogan County. Principal components of the work consist of removing and disposing existing power transformers as well as furnishing and installing replacement power transformers.

PRE-PROPOSAL SITE VISIT: A PRE-PROPOSAL SITE VISIT WILL BE HELD. SEE

SECTION L, FAR PROVISION 52.236-27, FOR PRE-PROPOSAL SITE VISIT INFORMATION.

ATTENDEES ARE TO PROVIDE AND WEAR SAFETY BOOTS, HARD HATS, AND SAFETY

VESTS.

FOR DATE AND PLACE OF PROPOSAL OPENING, SEE “SOLICITATION, OFFER, AND

AWARD,” STANDARD FORM 1442.

FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION

"RECLAMATION SAFETY AND HEALTH STANDARDS" (INCLUDING REVISIONS AT

https://www.usbr.gov/ssle/safety/rshs/index.html) WHICH IS APPLICABLE TO WORK UNDER

THIS CONTRACT, SEE CLAUSE AT “WBR 1452.223-81, SAFETY AND HEALTH."

Foreword – 1

Draft

This page intentionally left blank.

Foreword – 2

GSU Transformer Replacements Columbia Basin Project, Washington Solicitation No. 140R1025R0005

Table of Contents 00 01 10 - 1

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 12 10 Other Contracts 01 14 10 Use of Site 01 14 12 Work Restrictions 01 14 30 Interruption of Service 01 31 22 Coordination Meetings 01 31 30 Contract Document Management System 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety and Health Personnel 01 35 50 Site Security 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 54 20 Use of Government Crane 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 35 Oil Spill Prevention 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 02 - EXISTING CONDITIONS

02 80 10 General Requirements for Hazardous Materials 02 82 20 Removal and Disposal of Asbestos Containing Materials 02 83 33 Removal and Disposal of Equipment Containing Hazardous Materials 02 84 40 Removal and Disposal of Used Oil

DIVISION 03 - CONCRETE

03 62 20 Nonshrink Grout for Equipment and Metalwork

DIVISION 05 - METALS

05 12 73 Power Transformer Anchorage Systems

Columbia Basin Project, Washington Solicitation No. 140R1025R0005

Table of Contents 00 01 10 - 2

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 12 15 Membrane Waterproofing 07 84 00 Firestopping

DIVISION 21 - FIRE SUPPRESSION

21 10 00 Transformer Fire Suppression System

DIVISION 22 - PLUMBING

22 10 00 Unit Cooling Water Piping

DIVISION 26 - ELECTRICAL

26 05 02 Basic Electrical Materials and Methods 26 05 05 Selective Demolition for Electrical 26 05 20 Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceways and Boxes for Electrical Systems 26 05 75 Identification Signs 26 05 90 Wiring Checkout and Operational Tests

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 05 15 Oil-Spill Containment Aggregate

DIVISION 33 - UTILITIES

33 72 26 Outdoor Jumper Bus, Rigid Bus, and Accessories

DIVISION 48 - ELECTRICAL POWER GENERATION

48 19 22 Isolated Phase Bus 48 19 23 Electrical Power Generation Transformers 48 19 24 Transformer Insulating Fluid 48 19 25 Transformer Dissolved Gas Monitor

DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS

51 00 00 Information Available to Offerors 51 00 20 Oil Analytic Test Results 51 02 83 Hazardous Materials Survey and Analytical Results

DIVISION 52 - DRAWINGS

52 00 00 Drawings

END OF CONTENTS

This page intentionally left blank.Draft

Columbia Basin Project, Washington Solicitation No. 140R1025R0005

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located at Grand Coulee Dam Right Powerplant, on the Columbia River adjacent to the City of Coulee Dam in Okanogan County, Washington, approximately 90 miles west of Spokane, Washington.

B. The nearest railhead is a Government-owned siding and unloading facility located in Odair, Washington, on a rail line owned and operated by the Eastern Washington Gateway Railroad Company Railroad, Washington. The siding is located approximately 30 miles to the south of Grand Coulee Dam. Arrangement for rail service may be made by contacting Eastern Washington Gateway Railroad, 111 South Levre Street, Medical Lake, Washington, 99022, phone 509-299-9105 or www.washingtoneasternrr.com.

1. Other rail heads may exist in the area (e.g., Ephrata, Washington).

2. Government is not responsible for the contractor’s failure to secure the use of rail system.

1.02 PRINCIPAL COMPONENTS OF WORK

A. Replace three (3), in-service, single-phase Generator Step-Up (GSU) power transformers.

The following work to be completed:

1. Supply (manufacture, factory test, and transport) three (3) Generator Step-Up (GSU) power transformers for in-service operation.

2. Remove and dispose of three (3) GSU power transformers from in-service operation.

a. Recycle or dispose of existing insulation fluid per requirements of Section 02 87 20 – Removal and Disposal of Used Oil.

b. Remove and dispose of existing asbestos wiring per requirements of Section 02 82 20 - Removal and Disposal of Asbestos Containing Materials.

3. Install and commission three (3) GSU power transformers for in-service operation.

4. Furnish and install seismic anchorage systems for new transformers.

5. Modify the fire protection system for new transformers.

6. Modify existing isolated phase bus for connection to new transformers.

Columbia Basin Project, Washington Solicitation No. 140R1025R0005

Summary of Work 01 11 00 - 2

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.04 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52.

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative. May also be referred to as Government Representative and used interchangeably.

3. RSN: Required Submittal Number

4. TSC: Technical Service Center.

5. RPH: Right Power House.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

File details come from the government source that posted it. Updated .