(x)

140R1023Q0008 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Boise ID 83706-1234 1150 N. Curtis Road, Ste. 100

R10

Acquisition Management Division Regional Office Pacific Northwest Region Bureau of Reclamation

07/06/20230003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/14/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This amendment is being issued to offer answers from questions from potential vendors.

Questions:

1) Our process is to remove all insulation through the gable vent(s) Sanitize the attic and seal the exposed wood with a sealer/primer as per task 3, then blow in new insulation to specified requirements.

If insulation is removed without new insulation being replaced in September and we have freezing weather it may freeze plumbing and cause more damage, would the contractor share in the liability?

Answer: No, per PWS there will not be any replacing insulation to specified requirements.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Misty Gates

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140R1023Q0008/0003

This contract is to remove all damaged materials per Task #2 of the PWS. If there is a harsh weather or winter and damage is occurred from freezing pipes or other related issues, the contractor would not share liability of damages.

2) At times we do remove carpet, due to damage, age or severe contamination from bat feces/urine.

Best practice is to clean and sanitize to remove these contaminants. But if carpet is to be replaced, removal of all the carpet makes sense.

Removal of all the carpet would help in the cleaning and sanitizing before the final PCR test. If this is the desired outcome please let me know.

Answer: Yes, all carpet must be removed. See previous posted questions and answers from potential vendors.

Quotes due date will remain July 13, 2023.

Period of Performance: 07/15/2023 to 12/31/2025

00010 AP 688 Cascade Facility Pest Removal

Product/Service Code: F105

Product/Service Description: ENVIRONMENTAL

SYSTEMS PROTECTION- PESTICIDES SUPPORT

Requisition No: 0040598457

Period of Performance: 07/15/2023 to 12/31/2023

00020 Option Year 1:

AP 688 Cascade Facility Pest Removal

(Option Line Item)

Anticipated Exercise Date 01/01/2024

Product/Service Code: F105

Product/Service Description: ENVIRONMENTAL

SYSTEMS PROTECTION- PESTICIDES SUPPORT

Period of Performance: 01/01/2024 to 12/31/2024

00030 Option Year 2:

AP 688 Cascade Facility Pest Removal

(Option Line Item)

Anticipated Exercise Date 01/01/2025

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140R1023Q0008/0003

Product/Service Code: F105

Product/Service Description: ENVIRONMENTAL

SYSTEMS PROTECTION- PESTICIDES SUPPORT

Period of Performance: 01/01/2025 to 12/31/2025

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)