Solicitation RFQ 140P027Q0056 – Specifications for Window Retrofit/Replacement

This document is the technical specifications attachment for a Request for Quote (RFQ) issued by the National Park Service for the Lava Beds National Monument Visitor Center window replacement project located in Tulelake, California. The project requires removal and retrofit installation of 22 total window units with bronze matte finish for both exterior and interior surfaces. Specific window types include: six 66" x 41" horizontal sliders (two office, one library, three law office); two 52" x 42" horizontal sliders (restroom); four 34" x 44" horizontal sliders (office, single hung); one 36" x 44" horizontal slider (breakroom, single hung); and nine fixed windows in various sizes, with five featuring P516 obscure glass. The existing windows, installed in 2004, have failed prematurely due to harsh climate conditions including extreme temperature fluctuations, high winds, and intense UV exposure. The contractor must commence work within 30 calendar days of the Notice to Proceed and complete all work within 60 calendar days, with an estimated construction period of 4 weeks (20 working days).

The scope of work encompasses complete removal of existing window units including sashes, frames, and hardware with protection of adjacent stucco siding and interior finishes, followed by retrofit installation of new units within existing stucco frames without full demolition. All work must comply with Federal Regulations Title 40 Part 280, API Recommended Practice 1615-87, current energy efficiency standards for federal facilities, applicable building codes, and National Park Service standards. The installer must be regularly engaged in window installation with experienced and skilled workmen. The contractor must establish and implement a comprehensive accident prevention program, submit a Contractor Quality Control plan with daily reporting requirements, maintain as-constructed drawings, and ensure final inspection and substantial completion per government determination. No on-site work is permitted on federal holidays, nights, or weekends without prior contractor request and Contracting Officer approval. The contractor is prohibited from establishing a construction camp within the park and must confine operations to work limits while preventing damage to natural features and complying with all hazardous material handling and spill response requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation (RFQ) no. 140P027Q0056 – Attachment 3, Specifications

Retrofit/Replace Windows in Visitor Center, Lava Beds National Monument (LABE)

Lava Beds National Monument Visitor Center Window Replacement Project

NATIONAL PARK SERVICE

January 14, 2026

Prepared by:

Don Bowen

Maintenance Supervisor

Lava Beds National Monument

1 Indian Well

Tulelake California 96134

CONTRACT SPECIFICATIONS

A. Removal of all existing window units, including sashes, frames, and associated hardware.

• Protect adjacent stucco siding and interior finishes during removal.

• Remove sealants, fasteners, and related materials.

• Dispose of all removed materials in accordance with federal, state, and park regulations.

B. Installation (Retrofit)

• Furnish and install new retrofit window units sized to fit existing openings.

• Install windows within existing stucco frames without full stucco demolition.

• Ensure windows are plumb, level, square, and securely anchored.

• Provide manufacturer-recommended flashing, sealants, and weatherproofing.

• Install insulation around window perimeters as required.

• Seal all exterior joints to provide a weather-tight installation.

• Restore interior trim as required to achieve a finished appearance.

TABLE OF CONTENTS

DIVISION 1

Section 01010 General Requirements

Section 01270 Definition of Bid Items

Section 01430 Contractor Quality Control

DIVISION 2

Section

APPENDICES

A Site Photos and Drawings

B Site Maps

February 15, 2023 3

Lava Beds National Monument

SECTION 01010

GENERAL REQUIREMENTS

PART 1 GENERAL

Scope of Work

Description

Lava Beds National Monument, located in Tulelake, California, requires the removal and replacement of all exterior windows at its Visitors Center. The existing windows, installed in 2004, show signs of premature failure due to extended exposure to harsh climate conditions. These conditions include extreme temperature fluctuations, high winds, and intense ultraviolet (UV) exposure.

The project will involve removing all current windows and installing retrofit units within the existing stucco-clad wall openings. The existing stucco frames and exterior wall finishes will remain, except for minimal removal necessary to allow for proper flashing and sealing.

Scope of Work

Removal

All existing window units, including sashes, frames, and associated hardware, will be removed. During the removal process, adjacent stucco siding and interior finishes will be protected to prevent damage. Sealants, fasteners, and related materials will be carefully removed, and all discarded materials will be disposed of in accordance with federal, state, and park regulations.

Installation (Retrofit)

New retrofit window units will be furnished and installed, sized to fit the existing wall openings. The installation will occur within the existing stucco frames, avoiding full stucco demolition. Each window will be installed to ensure it is plumb, level, square, and securely anchored. Manufacturer-recommended flashing, sealants, and weatherproofing will be used to protect against the elements. Insulation will be added around the window perimeters as required, and all exterior joints will be sealed to achieve a weather-tight installation.

Interior trim will be restored as necessary to ensure a finished appearance.

Window Schedule

The project includes the replacement of windows with a bronze matte finish for both exterior and interior surfaces.

• 66" x 41" Horizontal Sliders:

• (2) Office windows (1-XO, 1-OX)

• (1) Library window (XO)

• (3) Law office windows (2-OX, 1-XO)

• 52" x 42" Horizontal Sliders:

• (2) Restroom windows (1-XO, 1-OX)

• 34" x 44" Horizontal Sliders:

• (4) Office windows (Single hung)

• 36" x 44" Horizontal Slider:

• (1) Breakroom window (Single hung)

• Fixed Windows:

• (1) 33" x 22" upper window

• (3) 66" x 21" upper fixed windows

• (5) 66" x 21" upper fixed windows (with P516 obscure glass)

Total Windows: 22 Units

February 15, 2023 4

LOCATION: .at Lava Beds National Monument administrative area.

1.1 QUALITY ASSURANCE:

A. All work performed under this section shall meet all requirements of Federal Regulations (CFR), Title 40, Part 280; API Recommended Practice 1615-87, and all other applicable national, state, and local standards and regulations.

B. Installer shall be regularly engaged in the installation and maintenance of window instalaltion and employ workmen experienced and skilled in this trade

C. Windows shall meet current energy efficiency standards applicable to federal facilities. Units shall be rated for local wind and environmental conditions.

D. Glazing in restroom and required locations shall meet safety glazing requirements.

Installation shall comply with applicable building codes and National Park Service standards.

1.2 All work will be performed under a single contract.

PART 2 PRODUCTS

1.1 All new devices and equipment shall be fully compatible with the existing window system.

PART 3 CONTRACTOR’S USE OF PREMISES

3.1 CONSTRUCTION CAMP: Establishment of a camp within the park will not be permitted.

3.2 CLOSURES: The work of this project takes place within occupied housing for the duration of the contract. Contractor shall always conduct his operations in a safe manner and to ensure the least inconvenience to residences. No on-site work shall be performed on federal holidays, nights, or weekends unless requested by the contractor and approved by the Contracting Officer.

3.3 STORAGE - STAGING AREAS: Confine storage of materials to the immediate project area. Limits of use and control shall be subject to Contracting Officer's approval.

3.4 FIELD OFFICE: Should Contractor elect to utilize a field office on the project, the size, location, and construction shall be subject to Contracting Officer's approval.

3.5 PRESERVATION OF NATURAL FEATURES: Confine all operations to work limits of the project.

Heavy equipment will be confined to use on the paved road. Prevent damage to natural surroundings. Avoid unnecessary soil compaction, disturbance of ground cover, and creation of wheel ruts. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government. Do not fasten ropes, cables, or guys to existing trees.

3.6 HAULING RESTRICTIONS: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage, which may result from moving of equipment.

3.7 HOUSEKEEPING: Keep projects neat, orderly, and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all hazardous rubbish. Do not allow rubbish to accumulate. Provide on-site containers for collection of rubbish and dispose of it at frequent intervals during progress of work. Provide enough containers for collecting construction debris and construction materials to be recycled.

February 15, 2023 5

Provide individually marked containers for recycling personal items, such as aluminum cans, newspapers, glass, plastic, corrugated cardboard. These items are to be recycled by the Contractor.

Wet down dry materials and rubbish to prevent blowing dust. Utilize excavated material as soon as possible.

Do not bury refuse inside the park. Dispose of waste materials legally at public or private dumping areas outside the park. Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the park.

3.8 AIR AND WATER POLLUTION CONTROL: Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction. Do not dispose of volatile wastes or oils in storm or sanitary drains. Do not allow waste materials to be washed into streams or bodies of water.

PART 4 - NOT USED

PART 5 COMMENCEMENT, PROSECUTION, AND COMPLETION

5.1 The Contractor shall commence work within 30 calendar days after the date of receipt of the Notice to

Proceed. Construction work shall progress in an orderly and diligent manner and shall be completed within 60 calendar days from the Construction Notice to Proceed.

5.2 The estimated period of construction is 4 weeks (20 working days).

PART 6 EXAMINATION OF THE SITE

6.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids. All bidders will be held to have the same knowledge concerning the site and the on-ground conditions as if they had inspected the job site.

PART 7 ABBREVIATIONS

7.1 The following list of abbreviations, which may be used in the Construction Specifications or Special

Provisions, refer to the organizations and specifications of the organizations listed below:

AAN American Association of Nurseryman

AASHTO American Association of State Highway and Transportation Officials

ACI American Concrete Institute

AISC American Institute of Steel Construction

AI Asphalt Institute

ANSI American National Standards Institute

AST Above Ground Storage Tank

ASTM American Society for Testing and Materials

AWWA American Water Works Association

CALTRANS State of California Department of Transportation

FHWA Federal Highway Administration

FM Factory Mutual

FS Federal Specifications

HVAC Heating Ventilation and Air Conditioning

MSHA Mine Safety and Health Administration

MUTCD Manual on Uniform Traffic Control Devices

NEC National Electric Code

NEMA National Electrical Manufacturers Association

February 15, 2023 6

NFPA National Fire Protection Association

NIOSH National Institute of Occupational Safety and Health

NPS National Park Service

NSF National Sanitation Foundation

OSHA Occupational Safety and Health Administration

PCA Portland Cement Association

UBC Uniform Building Code

UL Underwriters Laboratories, Inc.

PART 8 FIELD ENGINEERING

8.1 LAYOUT OF WORK: The Contractor’s work shall match the existing construction techniques, materials and aesthetics.

8.2 FIELD CONTROLS: Not applicable.

PART 9 ACCIDENT PREVENTION

9.1 DESCRIPTION: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors.

9.2 SUBMITTALS:

A. ACCIDENT PREVENTION PROGRAM: At the preconstruction conference submit for approval an accident prevention program. The program shall include:

a. Name of responsible supervisor to carry out the program.

b. Weekly and monthly safety meetings.

c. First aid procedures.

d. Training, both initial and continuing.

e. Planning for possible emergency situations.

f. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.

B. TEST REPORTS: Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.

C. MEETING AND INSPECTION REPORTS: Submit a report of safety meetings and of inspections.

9.3 QUALIFICATIONS OF EMPLOYEES:

A. Employees known to have allergy sensitivity to poison oak shall not be permitted to work in areas where the plant is present. All other employees shall be briefed on proper precautions to minimize contact with the plants.

B. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.

C. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

D. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.

February 15, 2023 7

E. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

9.4 ACCIDENT REPORTING: The Contractor shall report all accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.

9.5 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.

9.6 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.

9.7 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

9.8 PROTECTIVE EQUIPMENT:

A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

C. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. Change liners before reissuing hats.

D. Contractor must comply with the Covid guidelines at the time of the contract. The COR will provide that information at that time.

9.9 SAFETY MEETINGS: As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the work site.

9.10 Hazardous Material Action: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous

Materials Business Plan.

A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.

B. All vehicles with a load rating of two (2) tons or greater should carry, at minimum, enough absorbent materials to effectively immobilize the total volume of fluids contained within the vehicle. Sand or soil are not approved absorbent materials.

C. Vehicles and operators transporting hazardous materials must be DOT certified and/or registered, and operators must be state licensed and knowledgeable of local emergency response and personal safety protocol.

D. Oil leaks from the various pieces of equipment shall be repaired immediately on discovery.

Repairs shall be performed at the site of discovery or breakdown. Oil pans and absorbent material shall be in place prior to beginning repair work.

February 15, 2023 8

E. Absorbent materials may be ordered from:

Lab Safety Supply

P.O. Box 1368

Janesville, WI 53547-1368

(800) 356-0722 www.labsafety.com

New Pig Corporation

1 Pork Avenue

Tripton, PA 16684

(800) 468-4647 www.newpig.com

F. Oil pans and absorbent materials shall be used to prevent leaks, spills and draining of petroleum fluids from falling onto bare ground and paved surfaces during servicing of equipment. Soils contaminated with such fluids shall be dug up and placed in appropriate safety containers, removed from the Park and disposed of according to California State regulations.

G. Puddles of oil, gas, hydraulic or other similar petroleum-based fluids of one (1) gallon or more or affected areas of more than one (1) square foot shall be considered "Road Damage" on paved surfaces.

I. Loss of any petroleum fluid of forty (40) gallons or greater shall be reported through the 911 emergency phone system immediately to initiate emergency response actions. Clean up shall be according to state regulations.

PART 10 PRECONSTRUCTION CONFERENCE:

10.1 PRECONSTRUCTION CONFERENCE: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following:

1. Claims procedures

2. Correspondence procedures

3. Design Process

4. Designation of responsible personnel

5. Labor standards provisions

6. Payroll reports

7. Changes

8. Payments to Contractor

9. Subcontractors

10. National Park Service regulations

11. Accident prevention program (including name of responsible supervisor)

12. Accident reporting

13. Documents required under the contract

14. Park rules and regulations

15. Saturday, Sunday, holiday and night work

16. Safety program (compliance with the "Accident Prevention" clause of the General Provisions)

17. Tentative construction schedule

18. Submittal of shop drawings, project data, and samples

February 15, 2023 9

19. Relationship of Division 1 to other divisions

20. Spill Response Plan

PART 11 SUBMITTALS

11.1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.

11.2 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES:

A. As specified in the individual sections, forward submittals to Contracting Officer at least 15 days before need for approval.

B. After approving submittals, Contracting Officer will return one copy to the Contractor.

C. If submittals are not approved; Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes.

D. Any work done before approval shall be at Contractor's own risk.

11.3 APPROVED EQUALS: A request for approval constitutes a representation that Contractor:

A. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

B. Will provide the same warranties for the proposed item as for the item specified.

C. Has determined that the proposed item is compatible with interfacing items.

D. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

E. Waives all claims for additional expenses that may be incurred as a result of the substitution.

11.4 MANUFACTURER'S INSTALLATION INSTRUCTIONS: When contract documents require compliance with manufacturer's printed instructions, provide one complete set of instructions for

Contracting Officer and keep another complete set of instructions at the project site until substantial completion.

11.5 PROGRESS SCHEDULES: As soon as possible after Notice of Award and before beginning any work, submit Progress Schedule. Contracting Officer will review the Progress Schedule for format and content. Submit four copies of Progress Schedule (normally in bar chart form) showing estimated starting and completion dates for each part of the work. The first progress payment will not be issued until an acceptable progress schedule is submitted.

PART 12 TEMPORARY SERVICES

12.1 DESCRIPTION: None

12.2 SANITARY FACILITIES: Flushing toilet facilities will be available at the Visitor Center.

12.3 DRINKING WATER: Drinking water is available at the Visitor Center.

12.4 WATER FOR CONSTRUCTION: None

February 15, 2023 10

12.5 FIRE PREVENTION AND PROTECTION:

A. Hazard Control take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

B. Equipment Required: UL Class 2A, 2-1/2-gallon, water-type, stored pressure extinguisher and

UL Class 10, Type I, 15-pound, C. Class ABC fire extinguisher required to be on site. Travel distance from any workstation to the nearest extinguisher shall not exceed 100 feet.

D. Spark Arresters: Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters approved by the U.S. Forest Service. Exceptions will be made for diesel equipment equipped with a turbo-charger. Written determinations of areas and period of potential fire hazard will be issued by Contracting Officer.

E. Welding: Welding or cutting by torch shall be performed only when adequate fire protection is provided. Any work expected to require welding or other “hot” work is required to have a Hot

Work Permit from the NPS. The forms for this may be requested from the COR.

PART 13 PROTECTION OF PUBLIC

13.1 The work of this project takes place in housing for the duration of the contract. Contractor shall always conduct his operations in a safe manner and to ensure the least inconvenience residences.

13.2 Highway traffic control will not be necessary based on the scope of this project.

PART 14 PROJECT CLOSEOUT

14.1 DESCRIPTION: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.

14.2 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. Sweep interior and exterior work areas and restore natural areas to original condition. At time of final inspection, project shall be thoroughly clean and ready for use.

14.3 AS-CONSTRUCTED DRAWINGS: Show all changes and revisions to the original design that affect the permanent structures and will exist in the completed work.

14.4 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certification that project is substantially complete, and a final inspection is requested.

A. When Contracting Officer determines that the work is substantially complete, he will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial

Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may replace, repair, or remedy the work with an appropriate reduction in the contract price.

B. If Contracting Officer determines that the work is not substantially complete, he will immediately notify Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection.

February 15, 2023 11

14.5 ACCEPTANCE OF THE WORK: After all deficiencies have been corrected, a Letter of Acceptance will be issued.

END OF SECTION

SECTION 01270

DEFINITION OF BID ITEMS

DESCRIPTION

Specifications:

The project includes replacement of the following windows: With Bronze matte finish exterior and interior

66" x 41" Horizontal Sliders

(2) Office windows (1-XO,1-OX

(1) Library window ( XO)

(3) Law office windows (2-OX,1-XO)

52" x 42" Horizontal Sliders

(2) Restroom windows (1-XO,1-OX)

34" x 44" Horizontal Sliders

(4) Office windows ( Single hung)

36" x 44" Horizontal Slider

(1) Breakroom window Single hung)

Fixed Windows

(1) 33" x 22" upper window

(3) 66" x 21" upper fixed windows

(5) 66”x21” upper fixed windows (with P516 obscure glass)

Total Windows: 22 Units

PART 2 PRODUCTS Not used.

PART 3 EXECUTION Not used.

April 29, 2021 13

SECTION 01430

CONTRACTOR QUALITY CONTROL

1.1 DESCRIPTION

A. The work of this section consists of preparing and executing a quality control program.

1.2 SUBMITTALS

A. Quality Control Plan: At the time of the preconstruction conference, submit for approval a written

Contractor Quality Control (CQC) plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified. No change in the approved plan may be made without written concurrence of the Contracting Officer. The plan shall include:

1. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

2. A copy of a letter of direction to the Contractor's quality control supervisor outlining assigned duties.

3. Names and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

4. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

5. Methods of performing, documenting, and enforcing quality control of all work.

B. Daily Submittals: Submit Daily Quality Control Report showing all inspections and tests on the first workday following the date covered by the report. Electronic files (MS Word) of the attached Daily

Report and Testing Report forms will be provided to the contractor prior to the notice to proceed being issued.

C. Tests: Submit triplicate copies of complete test results not later than three calendar days after the test was performed. Submit failing test results and proposed remedial actions within four hours of noted deficiency.

D. Off Site Inspection Reports: Submit prior to shipment.

E. Progress Payments: If the CQC plan and Daily Quality Control Reports are not submitted in a timely manner, the Contracting Officer may retain an appropriate amount of the applicable progress payment.

1.3 QUALITY ASSURANCE

A. General: Except for tests or other items of work specified to be performed by the Government, the quality of all work shall be the responsibility of the Contractor. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.

B. Quality Control Staff: The Contractor's job supervisory staff may be used for quality control, supplemented as necessary by additional technicians. The Contractor's designated Quality Control

Supervisor shall be employed full time at the project site whenever contract work is in progress.

C. Testing Laboratory and Equipment.

April 29, 2021 14

1. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NBS requirements. Upon request, measuring and testing devices shall be made available for use by the Government for verification tests.

2. The testing laboratory organization shall be experienced in the type of testing work to be done.

PART 2 PRODUCTS Not used.

PART 3 EXECUTION

3.1 ON-SITE CONTROL

A. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.

B. Preparatory: Perform before beginning each feature of work.

1. Review control submittal requirements with personnel directly responsible for the quality control work.

2. Ensure that provisions have been made for field control testing.

3. Examine the work area to ensure that all preliminary work has been completed.

4. Verify all field dimensions and advise the Contracting Officer of discrepancies.

5. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.

C. Initial: As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship. Review control-testing procedures to ensure compliance with contract requirements.

D. Follow-up: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.

3.2 DOCUMENTATION

A. Maintain Daily Quality Control Reports (sample attached) of quality control activities and tests. Daily

Quality Control Reports may not be substituted for other written reports required under the General

Provisions, such as Disputes, Differing Site Conditions, or Changes.

3.3 ENFORCEMENT

A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer. Construction shall not proceed on any feature of work containing uncorrected work.

PART 4 MEASUREMENT AND PAYMENT

4.1 CONTRACTOR QUALITY CONTROL

A. Payment will be included in the bid item to which this work relates.

CONTRACTOR'S Q.C. DAILY REPORT

PROJECT

CONTRACT NO.

DATE

PARK

CONTRACTOR'S REPRESENTATIVE ON THE JOB

WEATHER (Rain, Snow, Cloudy, Windy, etc.)

RAINFALL

Inches TEMPERATURE GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)

MAX.

MIN.

1. PRIME CONTRACTOR

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

HRS. WORKING

YES NO Comments

WORK PERFORMED BY PRIME CONTRACTOR:

MATERIALS DELIVERED OFFICIAL VISITORS TO SITE

2A. SUBCONTRACTOR, _____________________________________________: (If more than one subcontractor use copies of following page.)

NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON

JOB

NO.

UNITS

WORK PERFORMED BY SUBCONTRACTOR:

3. SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)

4. TESTING: 1 Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)

Type and Location of Testing: ____________________________________________________________________________________

5. VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING

REQUIRED:

6. REMARKS:

7. CERTIFICATION:

I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above. ____________________________________________________________

Contractor's Designated Quality Control Representative

SUBCONTRACTOR WORK CONTINUED:

CONTRACT NO. REPORT NO. _______

SHEET ____ OF ____

2 SUBCONTRACTOR,

JOB

NO.

UNITS

JOB

NO.

UNITS

JOB

NO.

UNITS

JOB

NO.

UNITS

HRS. WORKING

YES NO COMMENT

S

TEST REPORT INFORMATION SHEET

CONTRACT NO. REPORT NO. _____________ SHEET _____ OF _________

1. Individual Making Inspection or Test:

2. Testing Laboratory; Name: Phone #:

Address:

3. Description of Work and Test Method:

4. Location of Samples and Tests or Inspections:

5. Specification Section:

6. Inspection or Test Data:

7. Test Results and Interpretations of Test Results:

8. Comments or Professional Opinion About Compliance of Inspected Work or Tested Work with contract Document Requirements:

9. Recommendations:

10. Corrective Actions Taken:

CERTIFICATION:

I certify that the above testing report is complete and correct and that all testing performed this day for this contract is in strict compliance with the plans and specifications except as noted above.

Signature of Inspector

TABLE OF CONTENTS
SECTION 01010
GENERAL REQUIREMENTS
SECTION 01270
DEFINITION OF BID ITEMS
SECTION 01430
CONTRACTOR QUALITY CONTROL