Attachment_1_Terms_Clauses_Provisions.pdf
PDF 645 KB Posted
- Attached to
- Replace Visitor Center Windows, Lava Beds N.M.
- Solicitation number
- 140PP027Q0056
- Issued by
- Not on record
About this file
This is a Request for Quotation (RFQ) issued by the National Park Service for commercial construction services to replace and retrofit windows at the Visitor Center building at Lava Beds National Monument in Tulelake, California. The solicitation is a Total Small Business Set-Aside limited to small business concerns, with the applicable NAICS code 238150 (Glass and Glazing Contractors) and a size standard of $19 million. The RFQ is issued on Standard Form 1442 and will result in a firm-fixed-price commercial construction purchase order. Quotations must be submitted electronically to Phaedra_Fuller@ios.doi.gov by the deadline specified in Block 13 of the SF 1442, with a question deadline of 1:00 PM PST on December 7, 2026. An organized site visit is scheduled for Wednesday, December 2, 2026, at 1:00 PM PST at the monument's Visitor Center location, requiring RSVP.
The Government seeks offers within a price range of $55,000 to $75,000, though this is provided as reference information and not a ceiling or floor. The contract performance period extends from January 11, 2027, to May 21, 2027, with work commencement required within ten calendar days of receiving the Notice to Proceed. Davis-Bacon wage rates apply for Siskiyou County, California. Evaluation criteria include price, relevant experience with similar window replacement and retrofitting projects completed within the past six years, technical approach demonstrating compliance with specifications and environmental sensitivity, current California Contractor State License validity, and past performance on comparable projects. Quoters must be registered in SAM with an active record and possess a valid UEI at time of submission and award. Required submissions include completed SF 1442 (blocks 14-20C), price schedule, relevant experience documentation, technical approach narrative (maximum 2 pages), California Contractor State License copy, past performance references, and responses to all representations and certifications. Performance and payment bonds at 100 percent of contract price, liability insurance of $500,000 per person/occurrence/property damage, and workers' compensation coverage are required. The contractor must submit daily logs documenting work performed, personnel, equipment, materials, and site visitors, and comply with Buy American construction materials requirements, archaeological findings protocols, Davis-Bacon wage rates, site-specific safety and health plans, and lead-based paint prohibitions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_5_Past_Performance_Questionnaire.docx | DOCX document | |
| Attachment_4_Forms_and_Provisions_to_Return_with_Proposal.docx | DOCX document | |
| Attachment_2_Wage_Decision_CA20260007_Siskiyou_County_CA.pdf | ||
| Sol_140PP027Q0056.pdf | ||
| Attachment_3_Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation (RFQ)
Release Date:
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
Beds National Monument (LABE)
Table of Contents
I. GENERAL INFORMATION
II. DESCRIPTION OF REQUIREMENT
III. PRICE SCHEDULE
IV. DELIVERIES OR PERFORMANCE
A. Commencement, Prosecution, and Completion of Work
B. Deliverable (Post-Award): Contractor’s Daily Logs
V. CONTRACT CLAUSES
A. Pre-Construction Meeting
B. Wage Rates
C. Site Specific Safety and Health Plan
D. Archeological Findings
E. Conduct of Operations
F. Seasonal Shutdown
G. Payment Information
H. Contractor Performance Assessment Reporting System (Nov 2015)
I. Construction Contract Administration
J. Appointment of Contractor Representative/Superintendent
K. Contract Administration
L. 1452.201-70 – Authorities and Delegations (SEP 2011)
M. 1452.204-70 – Release of Claims – Department of the Interior (JUL 1996)
N. 52.225-9 – Buy American–Construction Materials (OCT 2022)
O. 52.228-13 Alternative Payment Protections (JUL 2000)
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
P. 52.228-15 Performance and Payment Bonds-Construction (JUN 2020) (DEVIATION
MAY 2023)
Q. DIAR 1452.228-70, Liability Insurance (Jul 1996)
R. Workers Compensation
S. 1452.236-70 Prohibition Against Use of Lead-based Paint (JUL 1996)
T. 52.246-12 – Inspection of Construction (AUG 1996)
U. 52.252-2, Clauses Incorporated by Reference (Feb 1998)
V. 52.252-6, Authorized Deviations in Clauses (Nov 2020)
VI. CONTRACT DOCUMENTS, EXHIBITS OR ATTACHMENTS
A. List of Attachments
VII. SOLICITATION PROVISIONS
A. Affordability
B. Site Visit (Construction)
C. Compliance with Executive Orders 14173/14168
D. Compliance with Executive Orders 14148/14208
E. 52.212-1, Instructions to Offerors—Commercial Products and Commercial
Services (Sep 2023) (DEVIATION Mar 2026)
F. 52.212-2, Evaluation—Commercial Products and Commercial Services (Nov 2021)
(DEVIATION Mar 2026)
G. Responsibility Determination
H. 52.216-1 – Type of Contract (APR 1984)
I. 52.225-10 – Notice of Buy American Requirement--Construction Materials (MAY
2014)
J. 52.252-1, Solicitation Provisions Incorporated by Reference (Feb 1998)
K. 52.252-5 Authorized Deviations in Provisions (Nov 2020)
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
I. GENERAL INFORMATION
This solicitation for commercial construction services is a Request for Quote (RFQ) issued on Standard Form (SF) 1442. Award of a contract resulting from this solicitation will be made according to FAR Part 12 Acquisition of Commercial Products and Commercial Services.
The Government contemplates award of a firm-fixed-price commercial construction purchase order on Standard Form (SF) 1442 resulting from this solicitation.
This acquisition is a Total Small Business Set-Aside. Quotations are solicited only from small business concerns. Quotations received from concerns that are not small business concerns shall not be considered.
To be eligible for award as a small business concern, the offeror is required to represent in good faith that it meets the small business size standard corresponding to the North American Industry Classification System (NAICS) code identified in the solicitation. The associated NAICS code is 238150, Glass and Glazing Contractors. The small business size standard is $19M.
To be considered for award your company must have or obtain a Unique Entity Identifier (UEI). Your company must also be registered in the System for Award Management (SAM) at www.sam.gov at the time your quotation is submitted and at the time of award (and throughout contract performance). Registration in SAM is 100% free. “Registered in the System for Award Management (SAM)” is defined at FAR 52.204-7 and includes the requirement that the SAM record is marked “Active".
If you have any registration questions or if you need assistance with registration or updating SAM, please contact the National APEX Accelerator nearest you.
Website: Home - National Apex Accelerator Alliance // APEX Accelerators
II. DESCRIPTION OF REQUIREMENT
The National Park Service (NPS) at Lava Beds National Monument (LABE) has a requirement to replace, including some retrofitting, windows in the Visitor Center building at 1 Indian Well, Tulelake, CA 96134. The Contractor shall provide all supervision, labor, equipment, and supplies necessary to complete the work as identified in the project specifications and associated documents provided as attachments to the solicitation.
http://www.sam.gov/ https://www.napex.us/ https://www.apexaccelerators.us/#/
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
III. PRICE SCHEDULE
Provide pricing using the provided worksheet in Attachment no. 4, Forms and Provisions to Return with
Quote.
IV. DELIVERIES OR PERFORMANCE
A. Commencement, Prosecution, and Completion of Work
The Contractor shall be required to commence work under this contract within 10 calendar days after the date the Contractor receives the Notice to Proceed, prosecute the work diligently, and complete the entire work ready for use not later than *May 21, 2027. The time stated for completion shall include final cleanup of the premises.
*NOTE: Work is somewhat weather dependent, but Government has planned a period of performance from January 11, 2027 to May 21, 2027. The total time builds in enough time that should winter weather prevent much work occurring in Jan or Feb, the contractor should be able to complete work between Spring months of March to May 2027. Government prefers all work to be completed prior to the Memorial Day holiday weekend 2027. By having the project start date be in January 2027, that allows time for product lead times of ordering supplies/materials, for Government review/approval of those submittals ahead of any scheduled onsite work.
(End of Clause)
B. Deliverable (Post-Award): Contractor’s Daily Logs
Contractor shall prepare a daily log for each day work is performed under this contract. Copies of daily logs shall be submitted to the Contracting Officer, and may be compiled and submitted weekly, with payroll.
Time necessary for completion of daily log is approximately 15 to 30 minutes. The contractor may choose to use its own format as long as the following elements are included on the log:
(a) Project Name
(b) Contract number
(c) Date
(d) Prime Contractor and/or Subcontractor
(e) Work performed, including number of employees by job categories (indicate if "prime" or
"sub")
(f) Heavy equipment on job, hours worked (indicate if "prime" or "sub")
(g) Materials delivered
(h) Official visitors to site
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
(i) Inspections performed
(j) Verbal instruction received from government on construction deficiencies
(k) Certification (prime contractor's signature/COR's signature)
V. CONTRACT CLAUSES
A. Pre-Construction Meeting
After award, in January 2027, the Contracting Officer will conduct a preconstruction meeting virtually using MS Teams. Contractor will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, any need for attendance by subcontractors, and information regarding the items to be discussed.
B. Wage Rates
Davis-Bacon Wage Rates apply for this project and are attached to this solicitation (See Section IV). The project is located in Siskiyou County, California.
C. Site Specific Safety and Health Plan
A site specific safety and health plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site specific plan. The site specific safety and health plan shall establish in detail, the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards anticipated. The site specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.
As work proceeds, the site specific safety and health plan shall be adapted to new situations and new conditions. Changes and modifications to the accepted site specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office. Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
Prior to submittal to the COR, the site specific safety and health plan shall be signed and dated by the prime contractor's safety and health manager and site superintendent. The site specific safety and health plan shall be part of the contractor's safety and Health program. The contractor shall submit to the COR the contractor's site specific safety and health plan for review and approval by the safety office.
Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and
Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.
D. Archeological Findings
(a) Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery;
notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, he will be compensated by an equitable adjustment under the General Provisions of the Contract.
E. Conduct of Operations
At all times the Contractor shall conduct his organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements
(except those specified herein) shall be displayed on the construction site or within the park except with approval of the Contracting Officer.
(End of Clause)
F. Seasonal Shutdown
It is recognized that seasonal climatic conditions regularly occur in some of the National Park Service areas that restrict and in some cases prohibit normal construction activities. The actual timing of a seasonal shutdown will be determined by the Contracting Officer. The Contractor shall give the Contracting Officer at least two weeks’ notice prior to the anticipated resumption of work. The actual date that work is resumed is subject to the approval of the Contracting Officer. The amount of time during a seasonal
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava shutdown is taken into consideration when the completion time as stated in the Contract is determined.
Therefore, the contract time will not be extended due to seasonal shutdowns.
G. Payment Information
1) Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (FEB 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
The Contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Contracting Officer’s Representative (COR), with a copy to the Contracting Officer (CO), a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the COR shall provide an acceptability recommendation to both the CO and the Contractor. If the COR recommends acceptance, the Contractor shall submit a copy of the final version of the COR’s checklist and the Invoice Package to the NPS through IPP.
1. Completed copy of the COR’s final Construction Payment Request Checklist (Submit only with the formal submittal to IPP)
2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments as required by contract clause 52.232-5)
3. Certified copies of Payroll Reports per Contract clause 52.222-8 Payrolls and Basic Records, unless already submitted (include completed copy of the Payroll Report PII Certification sheet when submitting certified payroll reports)
4. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
5. A copy of the current construction schedule
6. A copy of the current Schedule of Values or this can be built into the business invoice
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) prior to the contract award date, but no more than 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its quotation.
2) Payment for Material Delivered at Locations Other than the Project Site
In addition to the terms covered by FAR Clause 52.232-5 Payments under Fixed-Price Construction Contracts, progress payments for material delivered to the Contractor at locations other than the project https://www.ipp.gov/
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava site may be taken into consideration at the sole discretion of the Contracting Officer. Payment for off-site delivery of specifically identifiable items required for the fabrication of this project may be considered if the following conditions are met:
1. Prior Approval - The Contractor shall obtain the approval of NPS CO before making any arrangements to obtain a partial payment for materials stored off site. Materials must be suitable for storage and must be properly packaged if this is necessary.
2. Storage Site - The Contractor shall furnish and maintain a suitable storage site and appropriate storage conditions which must be approved in advance by NPS CO.
3. Storage Conditions - The material covered by any request for progress payment must be stored above grade and must be properly protected at all times against weather, heat, cold, moisture and other hazards as the material may require. The storage conditions must be approved by NPS Project Representatives. All protection must be provided by the Contractor at their own expense and must be maintained throughout the storage period.
Material must not be co-mingled with other similar material but must be stored by itself and must be plainly labeled “Property of NPS.”
Material must be stored so that it can be readily inspected, measured, and counted at all times by NPS Project Representatives.
4. Contractor Title - The Contractor shall furnish satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract. The Contractor shall provide an inventory of the stored material together with a description of the storage site by Street Number and City, or by legal description of the premises.
(End of clause)
H. Contractor Performance Assessment Reporting System (Nov 2015)
In accordance with DOI and NPS policy, past performance evaluations may be prepared for this acquisition.
For more information see the Contractor Performance Assessment Reporting System (CPARS), available online at https://cpars.gov/.
(End of clause)
I. Construction Contract Administration
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at:
https://www.doi.gov/pam/acquisition/policy/constructioncontract.
https://cpars.gov/ https://www.doi.gov/pam/acquisition/policy/constructioncontract
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
J. Appointment of Contractor Representative/Superintendent
Prior to the commencement of work under this contract, the Contractor shall provide the Contracting Officer with the name and telephone number of at least one responsible individual who will be available on a daily basis to respond to operational problems and/or emergencies. In the event the contract involves more than one subcontractor, the designated site superintendent shall be a W-2 employee of the prime contractor. The Contractor agrees that notice to the designated representative shall constitute notice to the Contractor and further agrees to be bound by any commitments or representations made by such representative.
K. Contract Administration
1) Points of Contact
The Contracting Officer’s Representative (COR) for this order will be:
Don Bowen Chief of Maintenance Mobile Phone: 530-598-5195 Email: Don_Bowen@nps.gov
The Contracting Officer (CO) with overall responsibility for this order will be:
Phaedra Fuller Mobile/Office Phone: 360-461-1827 Email: Phaedra_Fuller@ios.doi.gov
2) Correspondence
Copies of all correspondence and written notices between the Contracting Officer’s Representative and the Contractor shall be sent to the cognizant Contracting Officer at the email address below. All correspondence shall state the contract number in the subject line of the email.
Phaedra Fuller Mobile/Office Phone: 360-461-1827 Email: Phaedra_Fuller@ios.doi.gov
L. 1452.201-70 – Authorities and Delegations (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award.
The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor.
Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
M. 1452.204-70 – Release of Claims – Department of the Interior (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-
137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
N. 52.225-9 – Buy American–Construction Materials (OCT 2022)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.
supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means— https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-25#FAR_25_105
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together.
Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United
States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding
COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows: none
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i)The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars) *
Item 1
Foreign construction material
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
(End of Clause)
O. 52.228-13 Alternative Payment Protections (JUL 2000)
(a) The Contractor shall submit one of the following payment protections:
(i) A payment bond (NOTE: NPS prefers payment bond on Standard Form 25A (SF-25A)).
(ii) An irrevocable letter of credit (ILC).
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within ten (10) days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.
(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.
(End of clause)
P. 52.228-15 Performance and Payment Bonds-Construction (JUN 2020) (DEVIATION MAY 2023)
(a) Definitions. As used in this clause-
Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds ( Standard Form 25), except that a seal is not required. The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds ( Standard Form 25A), except that a seal is not required. The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of the Treasury, https://www.acquisition.gov/far/subpart-28.1#FAR_28_102_1 https://www.gsa.gov/forms-library/performance-bond https://www.gsa.gov/forms-library/payment-bond
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
Financial Management, Service Surety Bond Branch, 3700 East West Highway, Room 6 F01, Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection ( 40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
Q. DIAR 1452.228-70, Liability Insurance (Jul 1996)
The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$500,000.00 each person $500,000.00 each occurrence $500,000.00 property damage
Each policy shall have a certificate evidencing the insurance coverage. The insurance Company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
R. Workers Compensation
The Contractor is required to be insured against liability for workmen's compensation or to undertake self-insurance. Evidence of coverage is required before commencement of project work.
http://www.fms.treas.gov/c570/ http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
S. 1452.236-70 Prohibition Against Use of Lead-based Paint (JUL 1996)
Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.
(End of Clause)
T. 52.246-12 – Inspection of Construction (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not --
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may --
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting
Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
U. 52.252-2, Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these addresses:
http://www.acquisition.gov/far/ https://www.acquisition.gov/diar https://www.acquisition.gov/caac-letters https://www.acquisition.gov/far-overhaul
52.203-17, Contractor Employee Whistleblower Rights (Nov 2023)
52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017)
52.204-9, Personal Identity Verification of Contractor Personnel (Jan 2011)
52.204-13, System for Award Management—Maintenance (Oct 2018) (DEVIATION Mar 2026)
52.204-19, Incorporation by Reference of Representations and Certifications (DEC 2014)
52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Jan 2025) (DEVIATION May 2026)
52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) (DEVIATION May 2026)
52.212-4, Contract Terms and Conditions— Commercial Products and Commercial Services (Nov 2023) (DEVIATION Mar 2026) http://www.acquisition.gov/far/ https://www.acquisition.gov/diar
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
52.219-6, Notice of Total Small Business Set-Aside (Mar 2020) (DEVIATION Jan 2026)
52.219-28, Postaward Small Business Program Rerepresentation (Jan 2025) (DEVIATION Jan 2026)
52.222-3, Convict Labor (Jun 2003)
52.222-6, Construction Wage Rate Requirements (Aug 2018) (DEVIATION May 2026)
52.222-7, Withholding of Funds (May 2014)
52.222-8, Payrolls and Basic Records (Jul 2021)
52.222-9, Apprentices and Trainees (Jul 2005) (DEVIATION Feb 2025)
52.222-10, Compliance with Copeland Act Requirements (Feb 1988)
52.222-11, Subcontracts (Labor Standards) (May 2014) (DEVIATION May 2026)
52.222-12, Contract Termination-Debarment (May 2014)
52.222-13, Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)
52.222-14, Disputes Concerning Labor Standards (Feb 1988)
52.222-15, Certification of Eligibility (May 2014)
52.222-19, Child Labor—Cooperation with Authorities and Remedies (Mar 2026)
52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (DEVIATION May 2026)
52.222-50, Combating Trafficking in Persons (Oct 2025)
52.222-54, Employment Eligibility Verification (Jan 2025)
52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (Oct 2025) (DEVIATION May 2026)
52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2022)
52.222-90, Addressing DEI Discrimination by Federal Contractors (Mar 2026) (DEVIATION May 2026)
52.223-1, Biobased Product Certification (May 2024) (DEVIATION May 2026)
52.223-2, Reporting of Biobased Products Under Service and Construction (May 2024) (DEVIATION May 2026)
52.223-5, Pollution Prevention and Right-to-Know Information (May 2024)
11/24/2026
Document No.
140PP027Q0056
Document Title
Replace/Retrofit Windows at Visitor Center, Lava
52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (May 2024) (DEVIATION May 2026)
52.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .