This file is a Request for Information (RFI) responses document that clarifies ambiguities and provides critical guidance for offerors responding to solicitation 140PP027Q0009 for bulk potable water hauling services at Grand Canyon National Park's South Rim facility.
The Government will supply potable water sourced from the City of Flagstaff under the Park's Land Use Agreement at no cost to contractors, who are responsible solely for treatment during transport, hauling, and delivery to the South Rim Water Treatment Plant (SRWTP). The base requirement (CLIN 00010) involves delivery of 500,000 gallons by November 15, 2026 (evaluation date), with an extended Period of Performance through November 30, 2026 to accommodate seasonal weather delays; Option 1 (CLIN 00020) covers 1,000,000 gallons and Option 2 (CLIN 00030) covers an additional 1,000,000 gallons. Pricing must be submitted as a firm-fixed unit price per accepted gallon (the evaluated price) and a corresponding lump-sum price per CLIN for purchase order issuance, with payment made per gallon accepted by the Government inspector. Water pickup occurs at two Flagstaff hydrants (Home Depot East Side or SW Corner of I-40 and Flagstaff Ranch Road), with overhead fill connections of 2.5-inch diameter; contractors bear responsibility for calculating fill and discharge times and configuring necessary equipment. A Government inspector will be on-site from 0700 to 1900 hours daily to approve loads based on a Field Checklist covering trailer identification, driver credentials, free chlorine levels (0.7–1.0 mg/L at offload), pH (7.5–8.5), turbidity (≤1.0 NTU), visual quality, and full truck volume; loads failing critical water quality or visual checks will not be approved for unloading, though the contractor will not be held responsible for water quality failures originating from the Government-supplied source unless caused by transport tank cleanliness issues. Pre-delivery submittals listed in SOW Section 5.1 must be submitted at least four calendar days before hauling begins, and the staging area can accommodate 5–6 trucks simultaneously, with one unloading connection at the SRWTP allowing simultaneous connection of up to two trucks at the contractor's discretion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| # | Topic | RFI | Response |
| 1 | Base CLIN completion date | The SOW (Sections 1.1, 2 and 4.1) requires delivery of the base 500,000 gallons by November 15, 2026. The solicitation (CLIN 00010 description and Period of Performance) states November 30, 2026. Which completion date governs for CLIN 00010? | 11/15/2026 is the required date, however, given the seasonal weather that may occure, the CO set the POP to November 30 in the event of delays. The evaluation date is as stated in the CLIN |
2 Free chlorine at off-load SOW Section 4.3 requires free chlorine of 0.2–1.0 mg/L in transit "at all times" (A.A.C. R18-4-214(F)), but lists the off-load criterion as "at least 0.7 to 1.5 mg/L." Because a load cannot exceed 1.0 mg/L in transit, please confirm the acceptable free chlorine range at off-load. Is the intended range 0.7–1.0 mg/L? 0.2–1.0 mg/L applies to transit per Arizona requirements.
0.7 to 1.5 mg/L is requirement for offload. Additional dosing may be required at time of offload with short period of driving to mix chemical in truck load.
| 3 | Pricing basis | The SOW describes a firm-fixed price with firm-fixed unit prices per gallon. The solicitation describes a "firm-fixed lump sum price arrangement," and the pricing schedule asks for both a price per gallon and a lump sum. Please confirm: | Yes, we are evaluationg on a perfpirce perga;;on, however for the purpose of the PO, we need a lumpsum price to issue the PO |
| a. Is the lump sum for each CLIN equal to the unit price multiplied by the CLIN quantity? | Yes. | ||
| b. Will payment be made per accepted gallon, as described in SOW Section 3.1? | Per accepted gallon. | ||
| c. Which figure will be the evaluated price? | The per gallon price is the evaluated price…the lump sum is for PO issueance. |
4 Pricing schedule CLIN numbering In Section (b), the Unified Pricing Schedule labels both Option 1 (500,000 gal) and Option 2 (1,000,000 gal) as "CLIN 00020." The instructions say the schedule must not be edited. May we label Option 2 as CLIN 00030, or will an amendment correct the schedule? CLIN 0030 is Option 2. RFI responses are used as amendments.
5 Solicitation number on Attachment 4 The Limitations on Subcontracting worksheet (Attachment 4) and page 4 of the solicitation reference "140PP027Q0008." Please confirm that the correct number is 140PP027Q0009 and that we should enter that number on the worksheet. [CO to confirm, assuming that 009 is the right number] Yes If you need to change the 8 to a 9…I will be evaluationg base on the 140PP027Q0009
| 6 | Missing attachments | The SOW references the following attachments, which were not included in the solicitation package: | |
| - Attachment 1 – Site map (delivery routes, South Entrance Station bypass, unloading points, staging areas) | Included in reponses | ||
| - Attachments 2 and 3 – Unloading point details | Photos will be provided [Pat] | ||
| - Attachment 4 – Receiving-water chemistry (SOW Section 1.3). Note that the solicitation's Attachment 4 is the Limitations on Subcontracting worksheet. | Disregard | ||
| - Attachment 5 – Park Cross-Connection Control Program | Disregard | ||
| - Attachment 7 – Required digital manifest data fields | Disregard | ||
| The receiving-water chemistry is needed to show compatibility under SOW Section 4.3. Could these attachments please be provided? | Disregard |
7 Performance Requirements Summary SOW Section 4.14 requires the Quality Control Plan to address each standard in the "Performance Requirements Summary (Section 4.16)." Section 4.16 is Delivery Schedules, and no Performance Requirements Summary table appears in the SOW. Please provide the PRS or confirm that the acceptance criteria and reporting timelines in Sections 4.3–4.4 serve that purpose. The Government will accept each load using its Field Checklist, included in repsonse. The Quality Control Plan shall address each checklist item and the reporting timelines in Section 4.4. The checklist criteria are: trailer ID on the approved vehicle list and matching the manifest; driver on the accepted driver roster (CDL with tank vehicle (N) endorsement); chlorine dose shown on the manifest; free chlorine 0.7 to 1.0 mg/L (see Topic 2); pH 7.5 to 8.5; turbidity not more than 1.0 NTU; clear and colorless, with no particles, sheen, or objectionable odor; and truck full (volume recorded if the tank is not 6,000 gallons). Temperature and conductivity are recorded only. The inspector will not approve unloading if the free chlorine, pH, visual and odor, or truck-full check is not met; any other item not met is recorded as a deficiency for the Contractor to correct. Because the Government furnishes the water, the Contractor is responsible only for its free chlorine level. If a load fails any other water quality criterion, the Contractor will not be held responsible, and a load that is not unloaded will still be paid at the unit price, unless the Government determines that the Contractor’s transport tank cleanliness or other procedures caused the failure. [CO to confirm payment.]
8 Submittal section reference The SOW states that "items in Section 6.1 are due at least four (4) calendar days before the start of hauling," but the pre-delivery submittals are numbered Section 5.1. Please confirm that the four-day requirement applies to the items listed in Section 5.1. Use Section 5.1.
9 Anticipated Notice to Proceed and funding The solicitation notes that funds are not presently available (FAR 52.232-18). With the POP starting November 2 and a 5-calendar-day mobilization requirement, can the Government share an anticipated award or Notice to Proceed date for scheduling purposes If there is a contract let, the awardee will receive adaquate notice, mobilizatiion time...
10 More Questions What is the exact address of the approved water pickup location in Flagstaff? Hydrant #1 is at the Home Depot on the East Side of Flagstaff: Hydrant #2 SW Corner of I-40 and Flagstaff Ranch Rd. (coordinates 35.18394 N, 111.71066 W)
How will tankers be filled at that location, and what connection size and type are available? Overhead fill Hydrant #2; 2 1/2 at Hydrant @1
What is the filling rate or estimated loading time for a 6,000-gallon tanker? Any vendor quoting on the contract should know how to calculate the fill time for a 6,000 gallon tanker; it is not the governments responsibility to calculate this factor
What will the water be discharged into the treatment plant? Please confirm the connection height and any pumping requirements beyond the stated minimum of 35 PSI. Any vendor quoting on the contract should know how to calculate the download time for a 6,000 gallon tanker; it is not the governments responsibility to calculate this factor
Approximately how much hose is needed from the tanker parking area to the unloading connection? Any vendor quoting on the contract should have adaquate hose rescources to configure what they will need to empty a 6,000 gallon tanker; it is not the governments responsibility to calculate this factor
| What is the size and configuration of the unloading camlock connection? | ERROR:#VALUE! | ||
| ERROR:#VALUE! | |||
| Questions from other email below this line | |||
| ERROR:#VALUE! | |||
| 11 | Number of unloading points | SOW Section 4.7 refers to "each unloading point (Section 5; Attachments 2 and 3)" and states that the Contractor "may unload at either point," but Sections 1.1 and 1.2 identify one unloading point, at the SRWTP. How many unloading connections will be available, and may trucks unload at more than one connection at the same time? What is the camlock size at each connection? | One unloading point that the contractro may connect 2 trucks to. See photo: Not, the photo above belongs to the current contractor. Any configuration will be the choice of the awardee. The government is not responsible for this determination |
| 12 | Water source and City of Flagstaff agreement | The pricing schedule describes each CLIN as "LUA Sourced," and SOW Section 4.2 refers to "existing agreements with the City of Flagstaff." However, SOW Section 1.1 states that the Contractor determines the "sources," and Section 2.2 requires the Contractor to "Furnish potable water from approved sources." Please confirm: | The government supplies the water. Quotes are to be developed on the basis…disregard any language about contractor provided water |
| a. Will the Government furnish the water under the Park's Land Use Agreement (LUA) with the City of Flagstaff, at no cost to the Contractor? Should quotes exclude any water cost? | Governemnt will procure and pay for water directly to Flagstaff. Quotes to exclude the purchase cost of water from Flagstaff. | ||
| b. Will the Contractor fill under the Park's agreement, or must it open its own City of Flagstaff bulk water account? | Contractor will fiull under Park's agreement. A aseparate account is not required. | ||
| c. Who meters the water at pickup, and whose meter reading is the record for payment (SOW Sections 3.1 and 9)? | City of Flagstaff meters water and will servev as record for total water hauled. | ||
| d. May the Contractor use other approved sources, and if so, at whose cost? | No other sources authorized. | ||
| e. Is source qualification testing (SOW Section 4.4, "at source qualification") required for the City of Flagstaff source before the first delivery? | Not required. Source is already approved. |
| 14 | Government inspector, staging and unloading rate | SOW Section 5 states that the Government "may choose to omit" the on-site operator and the inspector "at certain times," but Sections 4.2 and 4.4 state that no load may be unloaded without the inspector's approval. Please confirm: | Between 0700 and 1900 there will be an inspector on duty…no water shall be deluivered without an inspector present |
| a. Will a Government inspector be available for every delivery from 0700 to 1900, 7 days per week, including weekends and Federal holidays? | Gov inspector will be onsite at all times | ||
| b. If the inspector or operator is not available, how will loads be approved, and will waiting time be compensated? | Vendors are reminded that a government inspector will be onsite at all times during the stated hours…It is on the vendor to schedule their loads during these times; any load outside the stated times is the vendors responsibility | ||
| c. Where are the designated staging areas (Sections 4.7, 4.12 and 4.13), and how many trucks may stage at one time? | The staging area can hold 5- 6,000 gallon trucks | ||
| d. What unloading flow rate (gpm) can the SRWTP connection accept? | There is a 6" flange on the system it will handle what ever you can send it…The park is public Land, feel free to visit and see for yourself |
File details come from the government source that posted it. Updated .