This document is Amendment 0002 to Solicitation 140P9725R0001 for the removal of an existing wooden/plastic East Boundary fence and replacement with new chain-link fencing at Sitka National Historical Park in Alaska.

The amendment provides responses to 19 contractor questions covering various aspects of the project, including the acceptability of imported products, transportation methods, soil conditions, post hole dimensions, demolition requirements, disposal procedures, and the performance period. Key details include that imported products are acceptable, vehicles can be used to transport materials to the Memorial Loop Trail but not off-trail, hand tools are required for post hole excavation and fence demolition, disposal costs are the contractor's responsibility, and the work is expected to be performed during the mild winter season within a 90-day period of performance. The agency will provide a cultural monitor. The solicitation is for a firm fixed-price order with a period of performance from 11/05/2024 to 02/03/2025.

View the file

Other files for this federal contract opportunity

Other files attached to Sitka - Eastern Fence Boundry, newest first.
File Type Posted
Sol_140P9725R0001_Amd_0001.pdf PDF
Wage_Determination_AK20240001_0001.pdf PDF
A04_SOW_-_SITK_Replace_East_Boundary_Fence_0001.doc DOC document
Sol_140P9725R0001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P9725R0001 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PAK

Anchorage AK 99501-2327 240 W. 5th Ave, Room 114 NPS, ARO - Alaska Regional Office

10/03/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

10/03/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Solicitation 140P9725R0001 is hereby amended as follows:

1. Adding government replies to contractor questions

2. POC for this action is Tyler Groves, Tyler_Groves@nps.gov, (907) 202-0274

3. All other terms and conditions remain unchanged.

Contractor Question #1 Does the project require all products to be made in America? Or would import products be acceptable?

Government Reply #1 Imported products are acceptable.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Francisco Velasco

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P9725R0001/0002

Contractor Question #2 What is the intent for getting the new material placed along the fence line, and removing the existing materials? Would it be permissible to use an ATV with a trailer?

Or does everything need to be hand carried?

Government Reply #2 The parks intent is to have the old fence removed and the new fence installed without causing damage to adjacent natural and cultural resources or property. Vehicles (inc.

light duty trucks) can be used to transport materials and equipment from the contractor staging area to the to an area near the existing fence line via the Memorial Loop Trail (see path highlighted in orange on Map 3 in the Scope of

Work). The use of private ATV's with trailers are not permissible in the park. Existing fencing and new materials will need to be transported by foot

(hand carried) between the Memorial Loop Trail and the fence line.

Contractor Question #3 The soils that are removed from the post holes--Our assumption would be that it can be spread around the holes. Is this correct or does it need to be hauled out as well?

Government Reply #3 Excess soils from post hole excavation can be evenly dispersed along the park side of the fence line.

Contractor Question #4 Is there any access allowed at different places along the fence line?

Or is the only access from either end?

Government Reply #4 The only park approved access to the fence line is from inside the park as indicated on Map 3 in the Scope of Work.

Contractor Question #5 The scope of work calls for the new holes to be 1' deeper, and 6" larger in diameter than the existing ones. How big are the existing concrete slugs?

Government Reply #5 To the best of the park's knowledge, the existing slugs are approximately

8-inches wide and 18-inches deep.

Contractor Question #6 Specifically, what dimensions are you wanting the new holes to be, at a minimum?

Government Reply #6 At a minimum, new holes should be 14-inches wide and 30-inches deep.

Contractor Question #7 What type of soils are we

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

3 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P9725R0001/0002 likely to encounter along this fence area?

Government Reply #7 A mixture of loam and sedimentary soils is typically found around the fence area.

Contractor Question #8 Will it be possible to auger or post-hole dig deeper than the current installation? i.e. is there bedrock or large rocks below the surface?

Government Reply #8 It is assumed that majority of the post hole excavation will be able to be done using hand tools without hitting bedrock.

However, the park cannot guarantee that some large rocks will not be encountered.

Contractor Question #9 What is the intent, for installation, if we run into soils that cannot be excavated with hand tools?

Government Reply #9 If soils are encountered that cannot be removed by hand, then the park will accept pinning into the bedrock prior to installing concrete.

Contractor Question #10 Just to clarify--We are not allowed to use a machine for pulling the existing concrete posts? If this is the case, what would you recommend for pulling these?

Government Reply #10 Correct; in order to protect the parks natural and cultural resources adjacent to the fence line, as well as adjacent private property, the use heavy equipment will not be allowed off trail. It is the vendor/ contractors responsibility to determine how best to remove these components by hand without damaging adjacent resources or property.

Contractor Question #11 To what extent does the fence need to be demolished? i.e. does each board need to be unbolted and the fence completely disassembled? Or can it be cut into panels and removed and disposed of in sections at a time?

Government Reply #11 The entire fence structure that currently exists needs to be removed and disposed of off-site, including all related components such as posts, boards, rails, bracing, concrete footings, fasters, etc. Unbolting each board and completely disassembling the fence in place and/or removing it in sections are both approved methods.

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

4 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P9725R0001/0002

Contractor Question #12 Is there a landfill that will accept these materials?

Government Reply #`12 Sitka does have a landfill as well as solid waste disposal and recycling locations.

Contractor Question #13 Does the concrete and lumber need to be disposed of in separate places?

Government Reply #13 It is the vendor/ contractor's responsibility to verify what materials will be accepted where and what costs are associated with the disposal.

Contractor Question #14 Does the NPS have a relationship with the disposal area where we can dispose of the materials at no cost to the contractor?

Government Reply #14 No. The contractor is responsible for all disposal costs related to this project.

Contractor Question #15 Who is expected to bear the dump fees? Should this be included in our proposal? Or will NPS pay for it directly?

Government Reply#15 The contractor is responsible for all dump fees.

Contractor Question #16 Performance period is stated as 90 days from NTP. Is the intent to award this work in the winter season? If so, what is the intent for performing this work with snow present on the ground?

Government Reply #16 Yes, the intent is to award and complete this work during the winter season when our park visitation is at it's lowest. Sitka

NHP is a temperate rainforest that typically experiences a mild winter season due to its coastal location. Average monthly winter temps' range in the low 40's (f) as a high and low 30's

(f) as a low. Average monthly precipitation amount during winter months ranges from 4-10 inches. Due to these mild conditions, the park believes that this work can be successfully accomplished with in the 90-day performance period as stated.

Contractor Question #17 The narrative mentions that there are remnants of an old chain-link fence. Is removing this part of this

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

5 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P9725R0001/0002 requirement? If so, can you quantify how much of this there is to remove?

Government Reply #17 No, this scope of work does not include removal/ disposal of the old chain-link fence remnants.

Contractor Question #18 We have products that will block up to 98% view, and around 75%. What is the preference for this project?

Government Reply #18 For pricing purposes, anticipate the more expensive option. A final decision will be made during the product submittal process.

Contractor Question #19 We assume that NPS will provide the cultural monitor. Is this correct?

Government Reply #19 Yes, that is correct.

An award from this solicitation will result in a firm fixed price order