140P9721Q0043 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PAK
Anchorage AK 99501-2327 240 W. 5th Ave, Room 114 DOI, NPS, ARO - Alaska Regional Off
PAK
Anchorage AK 99501-2327 240 W. 5th Ave, Room 114 NPS, ARO - Alaska Regional Office
05/18/20210002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/04/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to:
1 - Post questions and answers posed at scheduled site visit held May 13, 2021 @ 1:00pm.
2 - Post attendees of site visit
Overview of delivery of heat and ventilation for each space/room.
Supply and return venting penetrations in the floor have already been installed. Contract only includes bringing ducting to the penetrations. NPS will provide vent covers/louvers.
All Warm Board and loops for reach radiant floor zone are installed. Tubing terminates in the crawlspace.
Contractor Question: Are manifolds to be mounted in the crawlspace or mechanical room.
Answer: Tubing is to be brought into the mechanical room and manifolds are to be mounted
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Amanda Jordan
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P9721Q0043/0002 on the north wall of the mechanical room.
Contractor Question: Are the electric baseboard heaters mounted in the crawlspace yet?
If so, can you identify the locations.
Answer: Baseboard heaters in the crawlspace will be installed after ducting is installed to avoid conflicts between the two systems.
Contractor Question: Can we see the crawlspace?
Yes, but limited. Panel supplying power to the crawlspace lights turn off while circuits are being added.
Crawlspace is dry, clean and has a full vapor barrier.
Approximately 42¿ from ground to bottom of floor joists.
Crawlspace hatches in the Mechanical Room in the AMC and near south wall in the YMCA.
Contractor Question: Is there any asbestos
Answer: No, there is neither asbestos or lead found on the site as the buildings have received a full rehabilitation and any presence/risk exposure to these hazards have been removed.
Site visit attendees:
In person - NPS Contracting Officer
Representative Cory Thole
In person - NPS Acting Facilities Manager Philip
Clark
On call - NPS Contracting Officer Amanda Jordan
On call - Schmolck Mechanical Vern Waldenberg
On call - Schmolck Mechanical Mike Moffitt
Period of Performance: 06/01/2021 to 09/24/2021
Period of Performance: 06/01/2021 to 10/29/2021