Klondike Gold Rush NHP
NATIONAL PARK SERVICE
Install Heat Pump, Ventilation Equipment and Associated Mechanical System Components at the Historic YMCA and Arctic Meat Company Building Complex
Skagway, Alaska 99840 March 1st, 2021
Background
The purpose of this award is to install heating and ventilation mechanical systems for YMCA and Arctic Meat Company buildings complex currently under rehabilitation and located in Klondike Gold Rush National Historical Park. The proposed mechanical systems installation includes Government furnished indoor/outdoor heat pump units, buffer tank, heat recovery ventilation equipment, a ventilation fan, crawl space ducting, control systems and propylene glycol. Additional work includes supply of remaining ducting to connect ventilation equipment to crawlspace ducting and interior air return locations, as well as, the startup and commissioning of all mechanical systems.
Objectives
The Contractor shall furnish the necessary personnel, material, equipment, and services (except as otherwise specified), to install a new air-to-water heat pump (indoor and outdoor units), one buffer tank, heating system components, two (2) heat recovery ventilators (HRV’s), one (1) ventilation fan, and associated components necessary to complete mechanical systems installations as specified in the description of tasks below.
During the performance of the work, the contractor shall provide adequate professional supervision and quality control to assure the accuracy, quality, completeness, and progress of work.
This scope includes a minimum of 2 site visits.
The purpose of the initial site visit is to complete the following items:
• Inspecting the work location,
• Inventorying/inspecting previously procured ducting to be installed in the crawl space,
• Mounting/Installation of the HRV’s, heat coils and ventilation fan
• Determining the location of exterior and interior wall penetrations to complete the ventilation installation (NPS Day Labor will complete the work of creating these penetrations),
• Determine the remaining ducting take off to fabricate the remaining ducting needed to connect the crawls space ducting to the HRV’s and remaining ducting needed for 1st floor air returns and exterior air exchanges.
• Additional work that can be completed during the initial site visit include the following:
o Mounting/Installation of the crawlspace ducting, sealant and insulation o Installation of the Air to Water Air Source Heat Pump (ASHP) equipment, pumps, valves, etc… o Connection of ASHP hydronics to hydronic manifolds.
o Connection of radiant heating loops to the hydronic manifolds.
o Connection of ASHP hydronics to HRV heat coils.
The subsequent visit(s) will be to complete the following:
• Installation of any remaining ventilation and/or heating equipment, ducting, connection to heating manifolds and all other work specified in the contract documents not performed during initial visit.
• Installation of fabricated ducting to connect crawl space ducting to the HRV’s,
• Installation of interior air return and outdoor air exchange ducting to the HRV’s and ventilation fan.
• Ventilation and Heat Pump Start Up, Commissioning, and Control Sequencing.
It is the responsibility of the contractor to verify that all the information provided is accurate.
All work is to be completed in accordance with this scope, manufactures specifications, and other award documents, as well as all applicable codes and industry standards.
Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with any and all applicable federal, state, and borough, laws, codes, and regulations pertaining to the performance of the service that is to be rendered.
The Contractor shall take proper safety and health precautions to protect workers, the public, and property. The Contractor shall provide the Government all requested reports, and supporting material developed during the performance of the work. The Contractor shall ensure protection of historic structures during work. The initial site visit should be utilized to finalize any alterations that may need to be done to the existing structures so that compliance can be completed prior to installation. Any damage (of building finishes, tenant property, furnishings, etc.) done to the building will result in financial restoration to the Government in order to complete the repairs.
Place of Performance:
Each building is located on the Southwest corner of the State Street and 5 Avenue intersection. The physical address for the YMCA is 475 State Street and the Arctic Meat Company address is 495 State Street, Skagway, AK 99840. Please Note: There are no address numbers on the buildings. The buildings are adjoined. A map is included as an attachment identifying the building locations.
Parking, Staging Area and Storage:
The Contractor will be responsible for parking and storage of materials. NPS parking and staging area directly south of the YMCA can be used by the contractor to store materials in preparation of and during contracted work (see attached map). Overnight storage of supplies allowed; however, the Government is not responsible for any lost or stolen items.
Interior spaces of the buildings can be utilized for storage and staging in coordination with and approval from the designated NPS representative.
Description of Tasks:
1. Heating System Installation:
a) Install government furnished Nordic air source heat pump (ASHP) manufactured by Maritime Geothermal
a. Nordic ATW-75-HACW-P-1T-C (Indoor Unit)
b. Nordic ACE-75-P-1/6-KDE (Outdoor Unit) with 15” stand
b) Install government furnished: 50-gallon, 12 KW buffer tank (BT-1)
c) Install three (3) government furnished Taco VR3452 VFD pumps to meet system flow requirements.
a. Pumps must be installed using isolation flanges, such as Taco
Shut Off Freedom Flanges or equivalent equipped with drains.
d) Connect new heating equipment and buffer tanks to new glycol tank, expansion tank, air separator with vent, and hydronic heating manifolds.
e) Connect radiant heating zones, previously installed by NPS according to Warm Board provided drawings, to hydronic manifolds.
a. Radiant tubing is installed and terminates in the crawlspace.
Contractor will be responsible for bringing tubing through the floor to connect to the heating manifolds.
f) Install adjustable angle solar thermometers with digital LCD display on the supply and return heat pump loops.
g) Insulate all copper pipe with 1” thick self-sealing lap fiberglass pipe insulation.
h) Install all piping and appurtenances to meet applicable design codes and safety standards. Clean, treat, and flush new heating system before operation. Refill with 30% propylene glycol mixture and corrosion inhibitor. KLGO will supply the propylene glycol, but contractor will pressure test and fill the hydronics system.
i) Complete all electrical circuit connects from the designated electrical panel to all installed equipment according to manufacturer specifications and applicable building and electrical codes.
j) Install controls in accordance with the designed control schematic and required performance and manufactures specifications.
a. Testing must be completed to ensure control sequence specifications are met and proper performance of the system.
k) Label all piping (direction of flow and supply/return) and valves as to proper orientation (normally open or closed) and gauges with standard setting or range. Provide valve chart if necessary.
l) Start up and commissioning to be coordinated with Maritime Geothermal Technicians. The start-up and commissioning by the technician will be jointly coordinated with the contractor, Maritime Geothermal and COR.
2. Ventilation System Installation with supply of items listed in q), r), v), and w):
m) Mount and Install all previously purchased ventilation equipment based on Mechanical and Electrical drawings developed by RSA Engineering Services in 2015.
n) Install previously purchased 24-gauge ducting in the crawlspace of the YMCA and AMC Buildings in accordance with the RSA 2015 drawings.
o) Contractor will need to supply all necessary sealant for the ducting installation.
p) Existing Ducting is NOT assembled on the longitudinal seam.
q) Supply and install ducting sealant and 2” insulation on all ducting.
r) Fabricate, Supply and Install ducting required to connect the crawl space ducting with the ventilation equipment in the mechanical room.
s) Installation of heat coils.
t) Heat Coils 1 – 4 are to be installed in the ducting by the vendor.
u) Connect heating coils 1 – 4 to the hydronic heating system.
v) Fabricate, Supply and Install all ducting running from equipment in
Mechanical to the exterior of the building, and, the return ducting from Rooms 104 (Arctic Meat Company) and 100 (Brown Shoe Store) through interior walls and into the mechanical room for connection to
HRV – 1.
w) Furnish and Install any additional controls necessary in accordance with the designed sequence of operations, control sequences and required performance specifications.
x) Complete Start-Up and Commissioning of the newly installed equipment in conjunction with the heating system start-up and commissioning.
In addition to the above tasks, the following shall apply to all work performed as part of this contract.
1. All work to be done in conformance with applicable National, State and Local codes, and at a minimum must meet industry standards.
2. All piping and fittings to be of domestic origin (example “Ward”). All copper fittings and piping to be at a minimum type “L” and of domestic origin (example “Mueller”). All joints shall be soldered, not press fit.
3. All valves to be of domestic origin full port 600 psi ANSI B1.20.s (threaded) and B16.18 (soldered); (example “Nibco” 585-70).
4. All newly installed pumps shall be variable frequency drive (VFD) pumps. Pumps supplied with the heat pumps and related equipment that are not VFD shall be left on site as backup.
5. Insulate all new piping and appurtenances as appropriate with 1” thick self-sealing lap fiberglass pipe insulation. 90-degree bends to be protected with PVC elbows.
6. Heat output shall be a function of exterior temperature using an outdoor reset function.
7. All major components including pumps, heating coils, expansion tanks, air separators and buffer tanks shall be isolated with full port ball valves.
8. Expansion tank shall be installed with hose bib for the purpose of testing tank air pressure, along with a pressure relief valve between the tank and the isolation valve.
9. Demonstrate performance of the newly installed equipment and document testing of new system’s base-line operation on a standard heat pump and ventilation inspection report form.
10. All installation work shall be provided with a minimum 12-month warranty against defects of materials or labor, and a response time to Skagway within 36 hours for emergency repairs, weather permitting.
11. Two complete copies of the manufacturer’s installation and data, and Operations and Maintenance manuals for the installed equipment shall be provided to the COR within 10 days of completion of installation.
12. All materials supplied by contractor shall meet buy American standards.
13. Contractor to furnish all needed equipment and materials not listed under the
“Government Furnished Materials and Labor” section.
14. Identify equipment, i.e. pumps, tanks, control panels, etc., with equipment labels mounted in readily accessible and readable location.
15. Label all valves with “Normally Open” or “Normally Closed” tags.
16. Equipment and Valve labels shall be Minimum 1‐inch high by 1/16‐inch thick, black or red, laminated plastic with white core. Engraved with 3/8‐inch high characters identifying the item or equipment by symbol and description indicated on the Drawings. Valves shall be labeled with red labels for normally closed and black labels for normally open, following the specifications for lettering above.
Government Furnished Materials and Labor
Government will provide (on site) the following equipment in brand new, not previously used condition:
• Fantech_SHR6905R (HRV-1)
• Fantech SHR14104 (HRV-2)
• Fantech Bypass Module (BPM)
• Fantech RTS3 Timer
• Greenheck BSQ-80-3 (VF-1)
• Greenheck Vertical Control Damper
• USA Coil and Air Heating Coils 5-F-2-1-M x 3 (Heat Coils 1-3)
• USA Coil and Air Heating Coils 5-F-2-2-M x 1 (Heat Coil 4)
• Marktime 88 Series Plug-In Timer
• Crawl Space Ducting and Hangers as specified in design and amounts in attachment 16. YMCA-AMC.Bldgs_Ducting_TakeOff_Revised.pdf
• Nordic ATW-75-HACW-P-1T-C (Indoor Unit)
• Nordic ACE-75-P-1/6-KDE (Outdoor Unit)
• Thermo2000 Eco Ultra 50-15
• 10K strap on temperature sensor
• 15” leg kit for outdoor heat pump unit
• 3 Taco VR3452 pumps with shutoff flanges
• 5-Loop Viega ProRadiant Stainless Steel Manifold with Shut-Off/Balancing/flow Meter (1 total)
• 6-Loop Viega ProRadiant Stainless Steel Manifold with Shut-Off/Balancing/flow Meter (2 total)
• Viega ProRadiant ½” SVC Compression Pex Adapter (34 total)
• Axiom DMF300 PressurePal Hydronic System Mini Feeder, 17 gallon
• Propylene glycol with corrosion inhibitor
Government will provide the concrete pad for the outdoor unit of the air source heat pump and provide routing for the refrigerant lines between the indoor and outdoor units.
Government shall provide line voltage and electrical panel for heating equipment and pumps, dampers, and controls.
Government will provide all interior wall, exterior wall and floor penetrations for ducting as determined during initial site visit.
COVID-19 Mitigations/Present Mandates in-Place
Vendor personnel must adhere to the most up-to-date health mandates for the State of Alaska Interstate Travel, whether traveling from out of state or in state. Vendor personnel must adhere to the most up-to-date City of Skagway and Klondike Gold Rush National Historic Park health mandates.
The NPS will provide a secure worksite so the vendor employees can meet the requirement to "minimize interaction" while awaiting COVID-19 travel requirements.
NPS will limit access to worksite and make sure those tasked with site overview and operations maintain social distancing and wear a mask when interacting with contractor personnel.
Pre-Installation Meeting:
The CO will arrange a pre-installation meeting with the Contractor. This meeting can be conducted as a teleconference or in person at the work site. The meeting agenda will include the following as a minimum:
1. Park rules and regulations
2. Correspondence procedures
3. Roles and responsibilities
4. Coordination with NPS Staff during performance of work
5. Site access and staging areas
6. Payments
7. Acceptance/rejection of the work
8. Labor standards and labor law application
9. Modifications
10. Accident Prevention Plan and accident reporting
Initial Full Site Visit and HRV Equipment Installation.
(1) Purpose of the initial site visit is as follows.
b) Inspect Work Location and available space(s).
c) Mount HRV Units 1 & 2 to determine where wall and floor penetrations are to be located for NPS Day Labor to provide.
d) Create Ducting Take-off for remaining ducting needed to connect to crawlspace ducting and ducting to be routed through interior and exterior walls.
e) Inventory existing ducting to determine if there are additional needs.
f) At the vendors discretion the crawl space ducting may be installed during the initial visit.
g) At the vendors discretion the heat pump equipment, piping and appurtenances can be installed and connected to the radiant tubing and ventilation equipment.
Hazard Control
Observe and enforce standards of fire prevention. A capable and qualified person shall be identified and placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting, soldering and welding procedures.
A hot work permit is required from the NPS in coordination with the contracting officer’s representative (see Attached). If producing smoke or conditions that may trigger the fire alarm detectors notify NPS personnel ahead of time to disable fire alarm system.
Contractor shall take all necessary precautions to prevent fire during installation and associated soldering of copper piping/tubing. Soldering or welding shall be performed only when adequate fire protection is provided. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.
Re-performance of Service
When service performed does not conform to award requirements, or when service was not performed in a specific area, the contractor shall perform or re-perform the service in conformity with contract requirements at no additional cost to the government.
Non-Payment for Additional Work
Any additional contractor performed services not specified in contract, either at its own volition or at the request of an individual other than an appointed Contracting Officer, except as may be explicitly authorized, shall be performed at the financial risk of the contractor. Only an appointed Contracting Officer is authorized to bind the Government to a change in specifications, contract terms, or conditions.
Housekeeping
Keep project neat, orderly, and in a safe condition at all times. Work areas shall be cleaned at the end of each day. Contractor will conform with federal smoking laws and regulations within and around federal buildings.
Close-out Project
Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish non historic surfaces that are damaged due to work of this award to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces. Pick up and remove all debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use. Report any damage to historic surfaces to the COR.
Upon receipt of written statement project is substantially complete, the COR will proceed with inspection within 2 business days.
When work is determined to be substantially complete, the COR will prepare a list of deficiencies to be corrected before final acceptance. Contractor shall complete the work described on the list of deficiencies within a reasonable amount of time as agreed upon by the COR. If work is not determined to be substantially complete, the COR will notify the Contractor in writing. After completing work, the Contractor shall resubmit certification and request a new final inspection.
Final Acceptance is reached when all installation specifications from the equipment manufacturer(s) are completed, as well as, all other requirements of this contract for site clean-up, and any remediation that may need to take place due to environmental contamination and acknowledged by COR.
Required Travel and Other Direct Costs
Employee Travel Costs and Lodging: The principal place of performance is Skagway, Alaska. Accordingly, reimbursable travel and per diem for the contractor’s employees performing work on a regular basis at this place of performance is not authorized. Any changes to the cost of travel that affects the final, accepted cost of the contract must be approved in advance by the contracting officer.
Shipment of Equipment and Delivery of Supplies/Materials: The principal place of performance is Skagway, Alaska. Accordingly, reimbursable shipping costs for equipment, supplies or materials to complete the work as specified in this document is not authorized. Any changes to this must be approved in advance by the contracting officer.
Period of Performance
The anticipated period of performance for the resultant contract is from date of award (est June 1st) through October 29th, 2021.
POINT OF CONTACT:
Contracting Officer’s Representative (COR) for Technical Support will be provided at time of award.
Contracting Office for Contractual Support:
Amanda Jordan – Contracting Officer National Park Service, Alaska Regional Office 240 W. 5th Ave.
Anchorage, AK 99501 Amanda_jordan@nps.gov Tel: (907) 644-3311
SUBMIT INVOICE(S) TO:
Submit the original invoice to the Invoice Processing Platform (IPP), https://www.ipp.gov/ and a copy, via email, to the CO.
Lump sum payments will be made upon completion of each line item.
Contracting Officer’s Authority:
The Contracting Officer is the only person with the authority to act as agent of the Government under this contract. Only the Contracting Officer has authority to:
https://www.ipp.gov/
(1) direct or negotiate any changes in the Statement of Work or specifications;
(2) modify or extend the period of performance;
(3) change the delivery schedule; or
(4) otherwise change any terms and conditions of this contract.
The Contracting Officer is the only person authorized to make or approve any changes in any of the requirements of this contract and not withstanding any provisions contained elsewhere in this contract, the said authority remains solely in the Contracting Officer. In the event the Contractor makes any changes at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.