(x)
140P9721Q0029 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PAK
Anchorage AK 99501-2327 240 W. 5th Ave, Room 114 NPS, ARO - Alaska Regional Office
03/15/20210002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/15/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Subject Solicitation 140P9721Q0029 is hereby amended as follows:
1. Attached are Contractor questions and their Government replies
2. Response date is not extended
3. All other terms and conditions remain unchanged by this modification.
4. POC for this action is James Bowers 907/644-3307
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
James Bowers
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Block 14 Continuation Sheet AM #2 The following are Contractor questions and their Government responses:
Contractor question 3). Please confirm the areas of cleanup operations will limited to Sandy Bay and Cup Cove.
Government Reply 3) No. The primary target beaches are Sandy Bay, Cup Cove, AND Morning Cove. These three are the goal, and if we got them all we would call it success. That being said, if we cannot get on these beaches because of surf conditions or weather, etc., we have alternate sites we have gone to in other years. Specifically, there are several beaches we clean in Black Bay, Thunder Bay, Taroka Arm and Paguna Arm. If we could not land on our target beaches for some reason, we would try to land at these alternatives in that order. Or, if we somehow ended up with spare time and space, we might try to squeeze one or two of these sites in. The NPS M/V Couloir is planning to accompany the trip to help relieve deck space for debris, and ferry debris back to Seward, if necessary.
Sandy and Cup are relatively exposed and several of our alternative beaches may be accessible when these aren’t. Morning Cove is fairly protected and we anticipate being able to land on that one regardless of weather.
The three primary beaches have never been cleaned and we expect the amount of debris to be significant. It is possible that there is enough debris that we may not be able to clean all three target beaches in the time allotted. The other beaches have been cleaned several times over the past 11 years and we think total debris on any of those beaches will only be around 20% of what we might find at our three target beaches. In 2012 we removed about 1600 pounds from our alternative sites.
Contractor question 4). Once at Sandy Bay and Cup Cove:
1. Please advise how many days steaming is assumed.
2. Please advise how many days holding station is assumed.
3. Please advise how many days at anchor is assumed.
Government Reply 4) We assume one day of transit time once passengers are on board to the first of our target beaches with the possibility of beginning clean-up work later in the day. Up to four days of holding/anchoring/steaming between sites. One day of steaming back to Seward and off loading. So, two days transit then up to six days of work with passengers on board. One of these days is built in for weather. It’s hard to guess, but we anticipate each beach to take at least one full day to clean.
We would anticipate an 8-10hr work day and then anchoring somewhere nearby for the evening.
Depending on where we are there are a variety of options for anchorages. Some close, some perhaps within an hour or two. Morning Cove is a good, protected anchorage. Paguna Arm has a decent anchorage and is a relatively short ride to Sandy Bay or Cup Cove. These time estimates are based on similar types of trips in this region.
Contractor question 5). On Page 1 of the SOW it states, “Actual trip timing and length will depend on weather conditions, vessel capabilities (speed, weather conditions vessel can operate in) and amount of debris on beaches. Can you please advise if there is a maximum number of days for the length of trip?
Government Reply 5). We anticipate a maximum of six days.