This document is an Attachment 8 Questions & Answers (Q&A) for Request for Quote (RFQ) 140P8625Q0061 for a flooring replacement and refinishing project at Fort Cronkhite Building 1042 in the Golden Gate National Recreation Area. The Q&A covers key details about the project scope, including confirmation that flooring work will encompass the entire building's 26 rooms and common areas, with hardwood floors verified underneath existing carpet and linoleum.
Key project details include a 90-day performance period after Notice to Proceed (NTP), demolition work is included, and there will be no building occupants during construction. The contractor will be responsible for moving and replacing all items, with flexibility to stage work by floor or using a storage container. Davis Bacon wages apply, and minimal painting is anticipated (only touch-ups to quarter rounds if damaged during floor sanding). The only additional note is that kitchen cabinets not removable can remain full during the moving portion of the contract. Interested contractors must RSVP to Quinn_Rankin@nps.gov for site visit details.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 140P8625Q0061 Replace/Refinish Flooring Fort Cronkhite 1042
Attachment 8 Questions & Answers Golden Gate National Recreation Area
Question 1: Is the flooring work throughout the whole building (i.e. the 26 rooms and common areas?
Answer: The information is located in both the solicitation and drawings; yes, the floors in the entire building.
Question 2: Please clarify if the movers will move and replace all items in all the rooms. If yes, is there a place on-site to store these items?
Answer: Movers will need to move and replace all items, the idea was they would do one floor at a time and move the items between the floors, but we do not specify how the contractor wants to do this. They could also rent a storage container to store the furniture depending on how they want to stage the flooring work.
Question 3: Do we need to preregister for the site visit? Can we get a POC name?
Answer: The information is located in the solicitation; please RSVP to me at Quinn_Rankin@nps.gov with the information requested.
Question 4: Is this a prevailing wage contract?
Answer: Appropriate Davis Bacon wages are listed in the solicitation documents.
Question 5: Is there interior painting as part of this project?
Answer: No, the only potential painting is to touch up the quarter rounds along the floor if damaged by the sanding of the hardwood floors.
Question 6: Is there demolition work included in this contract?
Answer: Yes
Question 7: What is the length of the period of performance?
Answer: 90 days after NTP
Question 8: Can the kitchen cabinets that are not removable stay full during the moving portion of the contract?
Answer: Yes
Question 9: Will there be occupants in the building during construction?
Answer: No
Question 10: Has it been verified if there are hardwood floors underneath the carpet and linoleum?
Answer: Yes