This statement of work describes elevator repair and inspection services required at the Golden Gate National Recreation Area headquarters building in San Francisco, California. The scope of work includes repairs to one elevator, including replacement of doors, frames, rollers, switches, and installation of new safety equipment. Additional requirements are to clean, inspect, and paint the elevator cab to ensure it passes state inspections. The period of performance is 30 days from notice to proceed and all work must be done on weekdays during normal business hours. Interested contractors are required to visit the site and hold any necessary licenses and certifications. The related federal contract opportunity is solicitation number 140P8624Q0007 for these elevator repair and inspection services at the Golden Gate National Recreation Area.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

NATIONAL PARK SERVICE

Golden Gate National Recreation Area Building 201, Fort Mason

San Francisco, CA 94123-0022

STATEMENT OF WORK

Golden Gate National Recreation Area

Elevator Repair and Inspection

PMIS 327021

Park headquarters; 201 Fort Mason, S.F

California Conveyance # 148205

1.0 Background

The Golden Gate National Recreation Areas is seeking to repair one elevator within its property. The elevator needs repairs to ensure they comply with OSHA and The State of California Department of Industrial Relations Division of Occupational Safety and Health. These repairs have been identified to ensure passengers can safety operate the elevators. The elevator is located at the Park’s headquarters at 201 Fort Mason, San Francisco, CA 94123.

2.0 Scope

The scope of this project includes repairs to one elevator as identified in the Tasks section. This includes for the elevator to be operated and tested, the elevator should be clean and operational by ensuring all elevators pass California State elevator inspections. Final inspection will be done by the COR after the elevator have passed the California State elevator inspections. The proof of compliance certification is required from the State of California Department of Industrial Relations Division of Occupational Safety and Health. A site visit by each contractor is required to the site. COR representative will coordinate visit.

3.0 Specifications

1. The items that are identified needing replacement should be all new manufacturer products.

4.0 Tasks – Base Bid

1. California Conveyance Identification # 148205

a. New rear hostway doors

b. replace entrance frame (in concrete bldg.), Pickup rollers, Gibs, interlocks, hanger rollers, and Sill closer.

c. New Gate switches, car hanger rollers, door edge detectors, GIBS, Clutches for front and rear entrances.

d. New hanger rollers, pickup rollers, interlocks GIBS.

e. New rear car door tracks

f. Company will provide the following materials to modernize both the front and rear doors:

i. 2 optiguards

ii. 2 Clutches

iii. Lobby Hall Door Tracks

iv. 2 Lobby Door Locks

v. 32 Lobby Door Rollers

vi. 1 Sight Guard

vii. Re-install one handrail inside the cab (existing handrail provided by Government)

viii. Remove existing elevator floor carpet and replace with non-slippery material.

ix. Repaint entire elevator cub with Presidio White color (Color number can be found in section 8.0). Provide sample color before painting.

g. A full safety inspection should be completed, and a report should be submitted to the COR. Full safety inspection needs to be completed accordance with ASME A17.1 Safety Code for Elevator and Escalator.

Materials provided shall be installed in accordance with ASME A17.1 Safety Code for Elevators and Escalators

5.0 Delivery

5.1 Inspections and installation shall be conducted during the business hours of 7:30 AM to 4:30 PM Monday through Friday, excluding Federal Holidays. No weekend work allowed unless a 48-hour notice is given and approved by the CO.

Requests should only be made for emergencies or weather delays. Following the notice to proceed from the Contracting Officer (CO), the contractor shall communicate with the COR to schedule any site visit necessary and provide a project work schedule.

5.2 Submittals

A. Project Schedule- submit a complete schedule outlining lead time for fabrication and installation.

B. Health and Safety Plan –provide a Health and Safety Plan that will ensure that the procedures, methods, and materials used in this removal and installation are compliant with OSHA standards and best practices for employee and site safety. This plan must include name of responsible on-site supervisor, first-aid procedures, outline of each phase of the work, and the hazards associated with each major phase, and methods proposed to ensure property protection and safety of the public.

C. Confined Space Entry Permit – A permit, signed by the entry supervisor, must be provided to the COR and posted at all entrances or otherwise made available to entrants before they enter a permit space. The permit must verify that pre-entry preparations outlined in the OSHA standard have been completed.

D. Licenses and Certificates: provide a copy of all active California Contractor Licenses and Certifications

E. Materials: provide cut sheets for all materials

F. Completion Report: Upon project completion, a written completion report of all tasks performed, accompanied by photographs and any shop drawings produced, shall be provided to the COR

G. All submittals, with the exception of the completion report, must be submitted and approved by the CO and COR before the Notice to Proceed (NTP) is issued by the Contracting Officer (CO).

6.0 Place of Performance

6.1 The elevator is located at 201 Fort Mason, San Francisco, CA 94123. It is the

Golden Gate National Recreation Area Headquarters building within the Fort Mason complex. It is in the upper Fort Mason area.

6.2 Site Conditions – The Contractor is responsible for verifying quantities and existing site conditions. All interested parties are strongly encouraged to do a site visit to familiarize themselves with local conditions that may affect the cost of contract performance. Interested parties may coordinate the site visit through the CO.

6.3 General Conditions – The Contractor shall be responsible for removing and disposing of all old materials and debris from the work areas. All disturbed surfaces must be cleaned and restored to their original condition.

6.4 Post Award Meeting – A post award meeting to discuss and clarify procedures to be followed with the execution of the contract. Installation specs and coordination between contracted work and Park operations must be arranged by the contractor. Contact the COR to schedule an on-site meeting.

7.0 Period of Performance

7.1 The period of performance shall be 30 days after Notice to Proceed (NTP).

7.2 Contractor shall submit written certification that the project is substantially complete, and final inspection is requested, the Contracting Officer’s Representative will make an inspection within seven (7) business days of receipt of request.

7.3 When the COR determines that the work is substantially complete, he will prepare a list of deficiencies to be corrected before final acceptance and a Letter of Substantial Completion will be issued by the CO.

7.4 Contractor shall coordinate manufacturer warranty inspection. Warranty documents shall be provided to the COR within 30 days of project completion.

8.0 Government-Furnished Property

1. One existing elevator handrail for re-handing on the elevator cab.

2. Presidio White paint color (providing paint color number only, not the actual paint) Government Uses Dunn-Edwards in Daly City, California, Paint # 0020- 0129-05181, Presidio White, SSHL50-1 SPRTASHLD EX S/G,5 Gallons L Y Notation /48 - 04:1 Y+ 44.500, 08:0 Y+ 3.750, 13: 0 Y+7.500, Park also uses Kelly Moore in San Rafael, California, Paint # 12-1741-0903 Presidio White

3. One temporary Electronic Key Card for 30 days for entry into facility while performing contracted work.

No other furnished government property provided.

9.0 Definitions

9.1 The Contracting Officer (CO) is the only government official authorized to make changes to the contract. The Contracting Officer’s Representative (COR) is the CO’s onsite representative to address all matters concerning the contract and ensure work is being completed according to the Statement of Work (SOW).

File details come from the government source that posted it. Updated .