This is a Request for Information (RFI) Responses document providing clarifications and answers to contractor questions regarding the SEKI Alternate Helitack Sitework project for Sequoia National Park. The document addresses site-specific conditions and equipment specifications for two distinct locations requiring temporary installation.
Location 1 involves two 12x40 trailers with bathrooms and confirms utility connections (electrical, water, sewer) will be provided by the Park Service, though contractors must supply support connections and hoses. The road is navigable for trucks and 40-foot trailers, though tight turns may require road guard assistance. Location 2 requires one 8x32 trailer (revised from 10x36 for maneuvering safety) with office space, one 8x20 storage container, one 1,100-watt generator, and 1,100 feet of six-foot fencing with two vehicle gates and one man gate. For Location 2, the contractor is responsible for electrical connections. Key specifications clarified include: no privacy windscreen required for fencing, no data hubs needed (Starlink will be used with standard 120V outlets provided), no trailer skirting required, and a ramp required for storage container access. Service Contract Act Wage Determination 2015-5657 applies to this requirement. Contractors must submit a Site Health & Safety Plan prior to installation and provide on-site communication (cellphone/satellite) during installation, servicing, and demobilization only. Site maintenance and cleanliness requirements apply only during active work phases. The government requests estimated start/delivery dates that balance cost considerations with schedule feasibility, as quotes will be evaluated on multiple factors with best value as the award basis.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8526Q0028_Amd_0002.pdf | ||
| B08_Attachment_1_Updated_Statement_of_Work-Alternate_Work_Site_0002.docx | DOCX document | |
| Sol_140P8526Q0028_Amd_0001.pdf | ||
| B08_Attachment_3_WD_2015-5657.pdf | ||
| B08_Attachment_1_Statement_of_Work-Alternate_Work_Site.docx | DOCX document | |
| Sol_140P8526Q0028.pdf | ||
| B08_Attachment_2_Pricing_Schedule.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P8526Q0028-SEKI Alternate Helitack Sitework RFIs V.1. 4/6/2026
Location 1 2-12x40 Trailers with bathrooms
1. Are there utility connections at this location? elec, water and sewer. YES
2. Will the Park service make the connections? - YES, however support connections and hoses need to be supplied.
3. If no sewer, the bathrooms will require holding tanks with periodic service. Should we include in our quote? If holding tanks are necessary, what would be the service interval be? - N/A 4.. Please confirm that the road to the site is navigable for a truck and 40' trailer. - YES, however there are a couple tight turns where road guard may need to be used. This can be coordinated with Park personnel.
5. Please confirm that the drop site for the trailers is dry, compacted, level. - YES.
Location 2 1- 10x36 Trailer with office, no bathroom 1- 8x20 Storage Container 1- generator 1100 ft 6' Fence w/ 2 vehicle gates and 1 man gate
6. Confirm that there are no restroom, water, or sewer considerations? Correct
7. Please confirm if the govt or KTR is responsible for making the electrical connection. - Contractor is responsible with making connections
8. Please confirm that the road to the site is navigable for a truck and 36' trailer. -We went and measured again and are fairly confident the 36' trailer with hitch and truck will be able to get up to Location 2. Maneuvering it into place will be tricky. We will change the specifications to an 8’x32’ trailer for this location to be safe. (SOW adjusted accordingly)
9. Please confirm that the drop site for the trailers is dry, compacted, level. – YES
---------------------Break-------------------------------------------------------------------------
10. Fencing: Please confirm whether green privacy windscreen is required as part of the fencing installation. - No privacy screen needed
11. Trailers Data: Please confirm whether data hubs or data connections are required within the office trailers. - No data hubs. Crew will be utilizing Starlink system. Standard 120V electrical ports/outlets need to be provided.
12. Trailer Skirting: Please confirm whether skirting is required for the trailers. - No skirting required.
13. Storage Container Access: Please confirm whether a ramp is required for the storage container. - Ramp is required
14. Wage Determination: The solicitation includes Service Contract Act Wage Determination 2015-5657. Please confirm whether this wage determination is applicable to this requirement, or if the scope is considered supply with incidental installation only. -The wage determination is applicable to this requirement.
15. Site Health & Safety Plan (SHSP): Please confirm whether submission of an SHSP is required prior to installation, as there’s no site visit. - YES. Contractor can coordinate with COR or PI for local information needs.
16. On-Site Communication: Please confirm whether the requirement for a cellphone (AT&T or satellite) applies only during active installation or throughout the entire rental period or not at all. - Only during installation, any servicing visits, and demobilizations.
17. Site Maintenance: Please confirm whether “keeping the site clean and orderly” applies only during installation activities for the trailers, container, generator and fencing. - Correct, only applies during installation, any servicing visits, and demobilization.
18. Start Date: Can you confirm your expected or approximate start date. – ASAP, Please provide an estimated start/delivery date that you feel is most advantageous to the government keeping in mind that price is also an evaluation factor, and that the government will evaluate the quotes based on all evaluation factors listed in the solicitation, and the basis for award will be based on best value to the government.