This is a Statement of Work for the urgent rehabilitation of Well #2 in Yosemite Valley, operated by Yosemite Valley Utilities. The work requires a Professional Deep Well Specialist to perform comprehensive well pump maintenance and repair at approximately 187 feet below grade. The well, located at 4,000 feet elevation, produces up to 1,000 gallons per minute and operates at 1,760 RPMs. Current issues include shaft wobbling, excessive noise, pitting and wear to bearings and impellers caused by glacial silt infiltration, resulting in higher amperage readings and reduced production capability.
The scope of work includes: removal of motor and base; extraction of the turbine pump set using skylight/roof access; assessment and refurbishment of all subsurface components including T&C column pipe water lube, 1-1/2" water lube shaft assembly, spider bearings, and bolts; potential replacement of 187-foot well casing and PVC level transducer sounding tube; cost verification against the purchase order amount with written notification to the contracting officer if repairs will exceed the award; reinstallation and shaft adjustment to optimize impeller clearance; onsite presence during NPS startup procedures to verify water production, amperage adequacy, and shaft stability; and compliance with AWWA C654-03 standards for well disinfection. Work must be completed within 5 days of notice to proceed during park hours (7:00 a.m. to 5:00 p.m.) with no weekend or holiday work permitted. The work site is located behind Yosemite Lodge on unpaved, muddy roads with a 45-foot vehicle length restriction on Highway 140. An NPS representative will remain onsite throughout the project. Contact: Jerod Raines, Valley Utilities Supervisor, 209-347-1510.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
URGENT REHAB OF WELL #2 IN YOSEMITE VALLEY
Objective:
Yosemite Valley Utilities needs a Professional Deep Well Specialist to pull well pump, assess repairs needed and replace spider bearings at well pump, approximately 187 feet below grade.
Background:
Well #2 is located in Yosemite Valley at an elevation of 4000’. This well produces up to 1000 gallons per minute (GPM). The well depth is approximately 970 feet with the pump sitting at approximately 187 feet. The shafts are shaking/wobbling and making noises. This well operates at 1760 RPMs and over the years the glacial silt has been pulled through the impellers and spider bearings causing pitting and excessive wear to the packing gland, impellers, head shaft and spider bearings, resulting in higher amp readings, reduced production and an inability to control water spray from the packing box assembly.
Scope of Work:
1. Remove motor and base from the well column.
2. Provide equipment and personnel to pull turbine pump set at approximately 187’ depth.
There is a skylight/roof access to pull the shaft from the building.
3. After pulling the shaft and pump, assess conditions of all components below grade and refurbish as necessary, to include T&C column pipe water lube, 1-1/2” water lube shaft assembly (shaft, sleeve, coupling, retainer and bearing). Shafts and T&C column pipes are in 10’ lengths. It is expected the spider bearings and other bolts will need replacement.
4. It is possible the well casing (187’) and PVC pipe for level transducer sounding tube may need to be replaced due to age and glacial silt damage. Replacement of well casing and level transducer sounding tube should be included in the bid.
5. Verify that the repairs will not exceed the scope or award amount of the purchase order. If the necessary repairs will exceed the purchase order amount, or if repairs are not possible, notify the contracting officer in writing before proceeding with any further work.
6. After repairs are made, re-install all components and adjust shaft to optimum impeller clearance.
7. Vendor shall remain onsite while NPS personnel initiate start up procedures to verify production of water from pump, amperage is adequate to turn impellers, and shaft is stable in place.
8. All work must be done in compliance with AWWA C654-03 (or most recent), sections 4.4,
4.5 and 4.5.1 for disinfection of well and well equipment.
Delivery:
Well #2 is in Yosemite Valley at an elevation of approximately 4000’ and weather conditions can change without warning. The well is located behind Yosemite Lodge on uneven, unpaved road with muddy conditions possible. There is a 45’ vehicle length restriction on Highway 140. All work must be performed during park hours 7am-5pm, no weekend or holiday work permitted without written permission, NPS representative will always be onsite. Work shall be completed within 5 days of notice to proceed.
Contact: Jerod Raines, Valley Utilities Supervisor, 209-347-1510 tmodjeski Cross-Out
| STATEMENT OF WORK |
| Objective: |